CHANGE ORDER ACCOUNTING
    The Townes at Bluestone  ::  43
GE appliance package with washer and dryer (including $2,000 allowance)      $5,300.00
Request for light gray door color      $0.00
Peephole in front door      $50.00
Expand Patio- pad to pad set HVAC on top      $600.00
Crown Moulding Main Level      $750.00
Eggshell Paint      $700.00
Finish Room behind garage with full bath      $6,450.00
LVP Main level      $300.00
LVP at foyer, closet under stairs and Bonus Room      $1,575.00
Oak Stair System to bedroom level      $1,600.00
LVP in upper hallway      $500.00
Semi Frameless shower door master bath      $1,300.00
Baths- Articulo Ceramic tile- 12x24      $400.00
electrical added- Nine receptacles, two quad receptacles, three coax locations      $875.00
Surround Sound (Living Room and Bonus Room)      $0.00
Sound Proofing Ceiling and shared wall in Bonus Room- Roxul 3- (add green glue)      $1,300.00
Sound Proof Living Room shared wall and add green glue      $525.00
Quartz Bathroom Countertops      $3,700.00
CREDIT- standard Bath countertops      $-500.00
Upgraded Kitchen Accessories, farmsink, trash pull out and deeper fridge cabinet and apron front sink      $2,200.00
CREDIT- standard kitchen sink      $-200.00
Powder Bath Vanity Upgrade (cost over pedestal sink)      $300.00
Laundry Cabinets (cost over standard wire shelf)      $750.00
Quartz Kitchen Counters- (cost over standard grantie      $2,000.00
Appliance Installation including washer and dryer      $250.00
Four added pocket doors      $800.00
Concrete Driveway      $2,000.00
Basement surroundsound. Purchasers to provide speakers      $500.00
Four LED snap lights in bonus room      $320.00
Under cabinet lights (4)      $500.00
Plumbing changes      $807.00
Tiled master shower - Tile CK- ($900) Cost for added materials from Eagle ($775 ) Install $2000      $3,675.00
Upgraded Carpet and Pad Over Standard Carpet      $1,400.00
LVP in Upstairs closets      $0.00
CREDIT- Master shower enclosure      $-325.00
Contract price of $281,965 included $26,965 of upgrades      $-26,965.00
CREDIT- Double wastebasket      $-358.00
Contract amendment from $281,965 to $295,044      $-13,079.00
 
 
Total Cost/Credit:  $0.00