CONGERS-2
•
ADDR
- 100 ::
CRITICAL PATH
|
INSPECTIONS
|
FLOOR PLANS
|
SELECTIONS
|
SPECS
|
CHANGES
|
NHS
view photo archive
Fri
Sep 20
Ratified Contract?
(0)
Fri
Sep 20
$2500 Deposit Received
(0)
Fri
Sep 20
Association Packet Requested
(0)
Fri
Sep 20
Association Packet Received
(0)
Fri
Sep 20
Selections Meeting
(0)
Fri
Sep 20
Selections Sheet Signed
(0)
Fri
Sep 20
Amendment for Upgrades (B,S,L,T,BCP)
(0)
Fri
Sep 20
Deposit For Upgrades Received
(0)
Fri
Sep 20
Building Permit
(30)
Fri
Nov 1
Order Roof & Floor Trusses
(1)
Mon
Nov 4
Order Windows & Doors
(0)
Mon
Nov 4
Stake Out Home
(1)
Tue
Nov 5
Excavate
(2)
Thu
Nov 7
Inspection (Footers)
(1)
Fri
Nov 8
Inspection (Concrete Wall)
(1)
Mon
Nov 11
Pour Footers
(1)
Tue
Nov 12
Set Forms
(2)
Thu
Nov 14
Pour Foundation Walls
(1)
Fri
Nov 15
Plumb Slab
(2)
Tue
Nov 19
Inspection (Plumbing Under Slab)
(1)
Wed
Nov 20
Inspection (Conduit Under Slab)
(1)
Thu
Nov 21
Prepare Slab
(1)
Fri
Nov 22
Inspection (Slab)
(1)
Mon
Nov 25
Inspection (Drain Tile)
(0)
Mon
Nov 25
Pour Slab
(1)
Tue
Nov 26
Settlement Agent Confirmed
(0)
Tue
Nov 26
Framing I
(9)
Mon
Dec 9
Order Steps
(0)
Mon
Dec 9
Order Tubs / Showers
(0)
Mon
Dec 9
Framing II
(8)
Thu
Dec 19
Framing III
(8)
Tue
Dec 31
Verify Window & Roof Structure
(0)
Tue
Dec 31
Install Stairs
(0)
Tue
Dec 31
Windows & Doors
(0)
Tue
Dec 31
House Number and Status in Window
(0)
Tue
Dec 31
Roofing
(0)
Tue
Dec 31
Order Cabinets
(0)
Tue
Dec 31
Order Appliances
(0)
Tue
Dec 31
Deck
(0)
Tue
Dec 31
Gutters
(0)
Tue
Dec 31
Driveway
(0)
Tue
Dec 31
Patio
(0)
Tue
Dec 31
Privacy Divider / Fence
(0)
Tue
Dec 31
Sod / Seed / Landscaping
(0)
Tue
Dec 31
HVAC Rough In
(4)
Mon
Jan 6
Inspection (Rough In HVAC)
(1)
Tue
Jan 7
Rough In Microwave Vent
(0)
Tue
Jan 7
Plumbing Rough In
(4)
Mon
Jan 13
Inspection (Rough In Plumbing)
(1)
Tue
Jan 14
Electric Rough In
(4)
Mon
Jan 20
Inspection (Rough In Electric)
(1)
Tue
Jan 21
Inspection (Deck Piers)
(0)
Tue
Jan 21
Inspection (Framing)
(1)
Wed
Jan 22
Exterior Vinyl
(0)
Wed
Jan 22
Exterior Stone
(0)
Wed
Jan 22
Insulation
(2)
Fri
Jan 24
Inspection (Insulation)
(1)
Mon
Jan 27
Inspection (Electric Service)
(0)
Mon
Jan 27
Set Electric Meter
(0)
Mon
Jan 27
Inspection (Main Sewer Line)
(0)
Mon
Jan 27
Inspection (Main Water Line)
(0)
Mon
Jan 27
Order Interior Doors & Trim
(0)
Mon
Jan 27
Drywall (Hang)
(4)
Fri
Jan 31
Loan Approval
(0)
Fri
Jan 31
Deed Preparation
(0)
Fri
Jan 31
Drywall (Tape, Block, Skim, Sand)
(6)
Mon
Feb 10
Paint 1
(1)
Tue
Feb 11
Garage Door
(0)
Tue
Feb 11
House Numbers
(0)
Tue
Feb 11
Mailbox
(0)
Tue
Feb 11
Cabinet Installation
(2)
Thu
Feb 13
Granite Installation
(1)
Fri
Feb 14
Interior Trim - Install
(3)
Wed
Feb 19
Order Plumbing / Lighting Fixtures
(0)
Wed
Feb 19
Interior Trim - Paint
(1)
Thu
Feb 20
Luxury Vinyl Plank
(3)
Tue
Feb 25
Luxury Vinyl Tile
(0)
Tue
Feb 25
Paint 2
(3)
Fri
Feb 28
Cover Floors
(1)
Mon
Mar 3
Deliver Plumbing / Lighting Fixtures
(0)
Mon
Mar 3
Shoe Moulding
(0)
Mon
Mar 3
Shelving, Door Knobs, Fire Extinguisher
(0)
Mon
Mar 3
Install Coded Lockbox (add extra keys)
(0)
Mon
Mar 3
Pay Water / Sewer Taps
(0)
Mon
Mar 3
Set Water Meter
(0)
Mon
Mar 3
Electric Trim Out
(3)
Thu
Mar 6
Ceiling Fans
(0)
Thu
Mar 6
HVAC Trim Out
(1)
Fri
Mar 7
Blower Door Test
(1)
Mon
Mar 10
Plumbing Trim Out
(2)
Wed
Mar 12
Install Appliances
(0)
Wed
Mar 12
Paint 3
(2)
Fri
Mar 14
Carpet
(2)
Tue
Mar 18
Appraiser Confirms Construction Completion
(0)
Tue
Mar 18
Inspection (Final HVAC)
(1)
Wed
Mar 19
Inspection (Final Plumbing)
(1)
Thu
Mar 20
Inspection (Final Electric)
(1)
Fri
Mar 21
Inspection (Final Building)
(2)
Tue
Mar 25
Pre Walk Through
(0)
Tue
Mar 25
Stain Hardwood Stairs
(1)
Wed
Mar 26
Cleaning
(1)
Thu
Mar 27
Certificate of Occupancy
(1)
Fri
Mar 28
C.O. to Lender
(0)
Fri
Mar 28
Schedule Closing
(0)
Fri
Mar 28
Buyer Walk Through
(1)
Mon
Mar 31
Payment for Upgrades
(0)
Mon
Mar 31
Keys to Settlement Agent
(0)
Mon
Mar 31
Review Settlement Statement
(0)
Mon
Mar 31
Jerry Signs Closing Documents
(0)
Mon
Mar 31
Request Trash Tote From POA Manager
(0)
Mon
Mar 31
Closing
(1)
Tue
Apr 1
Remove Coded Lockbox
(0)