Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Building Permit (30)      
Thu    Jan 9      Order Roof & Floor Trusses (1)      
Fri    Jan 10      Order Windows & Doors (0)      
Fri    Jan 10      Stake Out Home (1)      
Mon    Jan 13      Excavate (2)      
Wed    Jan 15      Inspection (Footers) (1)      
Thu    Jan 16      Inspection (Concrete Wall) (1)      
Fri    Jan 17      Pour Footers (1)      
Mon    Jan 20      Set Forms (2)      
Wed    Jan 22      Pour Foundation Walls (1)      
Thu    Jan 23      Plumb Slab (2)      
Mon    Jan 27      Inspection (Plumbing Under Slab) (1)      
Tue    Jan 28      Inspection (Conduit Under Slab) (1)      
Wed    Jan 29      Prepare Slab (1)      
Thu    Jan 30      Inspection (Slab) (1)      
Fri    Jan 31      Inspection (Drain Tile) (0)      
Fri    Jan 31      Pour Slab (1) *       
Mon    Feb 3      Settlement Agent Confirmed (0)      
Mon    Feb 3      Framing I (9)      
Fri    Feb 14      Order Steps (0)      
Fri    Feb 14      Order Tubs / Showers (0)      
Fri    Feb 14      Framing II (8)      
Wed    Feb 26      Framing III (8) *       
Mon    Mar 10      Verify Window & Roof Structure (0)      
Mon    Mar 10      Install Stairs (0)      
Mon    Mar 10      Windows & Doors (0)      
Mon    Mar 10      House Number and Status in Window (0)      
Mon    Mar 10      Roofing (0)      
Mon    Mar 10      Order Cabinets (0)      
Mon    Mar 10      Order Appliances (0)      
Mon    Mar 10      Deck (0)      
Mon    Mar 10      Gutters (0)      
Mon    Mar 10      Driveway (0)      
Mon    Mar 10      Patio (0)      
Mon    Mar 10      Privacy Divider / Fence (0)      
Mon    Mar 10      Sod / Seed / Landscaping (0)      
Mon    Mar 10      HVAC Rough In (4)      
Fri    Mar 14      Inspection (Rough In HVAC) (1)      
Mon    Mar 17      Rough In Microwave Vent (0)      
Mon    Mar 17      Plumbing Rough In (4)      
Fri    Mar 21      Inspection (Rough In Plumbing) (1)      
Mon    Mar 24      Electric Rough In (4)      
Fri    Mar 28      Inspection (Rough In Electric) (1)      
Mon    Mar 31      Inspection (Deck Piers) (0)      
Mon    Mar 31      Inspection (Framing) (1)      
Tue    Apr 1      Exterior Vinyl (0) *       
Tue    Apr 1      Exterior Stone (0)      
Tue    Apr 1      Insulation (2)      
Thu    Apr 3      Inspection (Insulation) (1)      
Fri    Apr 4      Inspection (Electric Service) (0)      
Fri    Apr 4      Set Electric Meter (0)      
Fri    Apr 4      Inspection (Main Sewer Line) (0)      
Fri    Apr 4      Inspection (Main Water Line) (0)      
Fri    Apr 4      Order Interior Doors & Trim (0)      
Fri    Apr 4      Drywall (Hang) (4) *       
Thu    Apr 10      Loan Approval (0)      
Thu    Apr 10      Deed Preparation (0)      
Thu    Apr 10      Drywall (Tape, Block, Skim, Sand) (6) *       
Fri    Apr 18      Paint 1 (1)      
Mon    Apr 21      Garage Door (0)      
Mon    Apr 21      House Numbers (0)      
Mon    Apr 21      Mailbox (0)      
Mon    Apr 21      Cabinet Installation (2) *       
Wed    Apr 23      Granite Installation (1) *       
Thu    Apr 24      Interior Trim - Install (3)      
Tue    Apr 29      Order Plumbing / Lighting Fixtures (0)      
Tue    Apr 29      Interior Trim - Paint (1)      
Wed    Apr 30      Luxury Vinyl Plank (3) *       
Mon    May 5      Luxury Vinyl Tile (0)      
Mon    May 5      Paint 2 (3)      
Thu    May 8      Cover Floors (1)      
Fri    May 9      Deliver Plumbing / Lighting Fixtures (0)      
Fri    May 9      Shoe Moulding (0)      
Fri    May 9      Shelving, Door Knobs, Fire Extinguisher (0)      
Fri    May 9      Install Coded Lockbox (add extra keys) (0)      
Fri    May 9      Pay Water / Sewer Taps (0)      
Fri    May 9      Set Water Meter (0)      
Fri    May 9      Electric Trim Out (3)      
Wed    May 14      Ceiling Fans (0)      
Wed    May 14      HVAC Trim Out (1)      
Thu    May 15      Blower Door Test (1)      
Fri    May 16      Plumbing Trim Out (2)      
Tue    May 20      Install Appliances (0) *       
Tue    May 20      Paint 3 (2) *       
Thu    May 22      Carpet (2)      
Mon    May 26      Appraiser Confirms Construction Completion (0)      
Mon    May 26      Inspection (Final HVAC) (1)      
Tue    May 27      Inspection (Final Plumbing) (1)      
Wed    May 28      Inspection (Final Electric) (1)      
Thu    May 29      Inspection (Final Building) (2) *       
Mon    Jun 2      Pre Walk Through (0)      
Mon    Jun 2      Stain Hardwood Stairs (1)      
Tue    Jun 3      Cleaning (1)      
Wed    Jun 4      Certificate of Occupancy (1) *       
Thu    Jun 5      C.O. to Lender (0)      
Thu    Jun 5      Schedule Closing (0)      
Thu    Jun 5      Buyer Walk Through (1)      
Fri    Jun 6      Payment for Upgrades (0)      
Fri    Jun 6      Keys to Settlement Agent (0)      
Fri    Jun 6      Review Settlement Statement (0)      
Fri    Jun 6      Jerry Signs Closing Documents (0)      
Fri    Jun 6      Request Trash Tote From POA Manager (0)      
Fri    Jun 6      Closing (1)      
Mon    Jun 9      Remove Coded Lockbox (0)