ADDR
- 48  ::  2222 Deyerle Avenue
[ BUILD: 1812-0087 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Fri    Sep 20      Ratified Contract? (0)      
Fri    Sep 20      $2500 Deposit Received (0)      
Fri    Sep 20      Association Packet Requested (0)      
Fri    Sep 20      Association Packet Received (0)      
Fri    Sep 20      Selections Meeting (0)      
Fri    Sep 20      Selections Sheet Signed (0)      
Fri    Sep 20      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Fri    Sep 20      Deposit For Upgrades Received (0)      
Fri    Sep 20      Inspection (Concrete Wall) (1)      
Mon    Sep 23      Inspection (Conduit Under Slab) (1)      
Tue    Sep 24      Inspection (Drain Tile) (0)      
Tue    Sep 24      Settlement Agent Confirmed (0)      
Tue    Sep 24      Verify Window & Roof Structure (0)      
Tue    Sep 24      Order Appliances (0)      
Tue    Sep 24      Patio (0)      
Tue    Sep 24      Rough In Microwave Vent (0)      
Tue    Sep 24      Inspection (Rough In Plumbing) (1)      
Wed    Sep 25      Inspection (Rough In Electric) (1)      
Thu    Sep 26      Inspection (Deck Piers) (0)      
Thu    Sep 26      Inspection (Framing) (1)      
Fri    Sep 27      Exterior Stone (0)      
Fri    Sep 27      Set Electric Meter (0)      
Fri    Sep 27      Inspection (Main Water Line) (0)      
Fri    Sep 27      Loan Approval (0)      
Fri    Sep 27      Deed Preparation (0)      
Fri    Sep 27      Mailbox (0)      
Fri    Sep 27      Interior Trim - Paint (1)      
Mon    Sep 30      Ceiling Fans (0)      
Mon    Sep 30      Blower Door Test (1)      
Tue    Oct 1      Inspection (Final HVAC) (1)      
Wed    Oct 2      Inspection (Final Plumbing) (1)      
Thu    Oct 3      Inspection (Final Electric) (1)      
Fri    Oct 4      Stain Hardwood Stairs (1)      
Mon    Oct 7      Request Trash Tote From POA Manager (0)      
--   --   Want electrical walk through
--   --   Send Mirror Sizes to buyer and credit amount On site 9/4
--   --   Savannah brick, country beige vinyl, green front door
--   --   4 snap lights in living room on dimmer Needs dimmer switch
--   --   Electrical outlet in patio for future hot tub See pic. I think is in 6/26
--   --   By requesting two parking spaces in driveway if possible?
--   --   loghting and plubing to be obtained by Ferguson- see selections sheet.
--   --   Cut brick above door (pic)
--   --   Realtor says patio was not expanded?
--   --   Wash brick
--   --   Cabinet hardware needed
--   --   Do not finish bonus room in the garage. Will not get carpet or paint.
--   --   Missing kitchen island granite 9/4
--   --   Courtney please take pictures of the mastr shower door once installed and email/text to Kate so she can send them to the T62 buyer!
--   --  
--   --   Small holes in front brick mortar
--   --   Dining chandelier credit? On counter but may be providing their own?
--   --   CODED LOCKBOX 4848
--   --  
--   --   Need sheet vinyl in closet under stairs
--   --   Clean out garage
--   --   No dimmer for LR lights per BCP
--   --   Upgraded pedastal sink In garage 9/21
--   --   Install sconce light globes
--   --   Sconce upside down in stairway from basement to main level. Install correct light
--   --   Extend front gutter
--   --   Is house getting backsplash before closing?
--   --   Hand railings
--   --   Rear door dead bolt not lined up Weather stripping
--   --   Hang mirrors
--   --   HVAC covers Plus return at stairs
--   --  
--   --   Returen air cover
--   --   Stain steps
--   --   Paint 2 back bonus room
--   --   Basement bath light crooked Tom
--   --   Touch up paint throughout 10/9 seems to be starting
--   --   Handrails on stairs
--   --  
--   --   Molding issue steps to main level
--   --   Molding issue steps to main level
--   --  
--   --   Kitchen cabinet missing trim
--   --   Set fridge (not against wall)
--   --   Touch up paint MB closet
--   --   Touch up paint MB closet Working on it 10/16
--   --  
--   --   MB closet light needs replaced w correct snap light
--   --  
--   --  
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1)      
-- -- Framing I (9)       Starting April 1
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8)      
-- -- Install Stairs (0)       May 24
-- -- Windows & Doors (0)      
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)       Patio done 7/31
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       Working on it 6/1
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)       In progress 6/5 (most progress in this townhouse)
-- -- Exterior Vinyl (0)      
-- -- Insulation (2)      
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4)       In process 7/31
-- -- Drywall (Tape, Block, Skim, Sand) (6)       In process 7/31
-- -- Paint 1 (1)       Tues, Aug 13
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2)       August 9
-- -- Granite Installation (1)      
-- -- Interior Trim - Install (3)       In process 8/17
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3)      
-- -- Luxury Vinyl Tile (0)       Done- all tile 12x12
-- -- Paint 2 (3)       No color 9/21
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)       On site 9/7
-- -- Shoe Moulding (0)       In process 9/25
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       In process 9/21. Need shelving.
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       In process 9/28
-- -- HVAC Trim Out (1)       HVAC is set
-- -- Plumbing Trim Out (2)       Done. Extra toilet in basement.
-- -- Install Appliances (0)       Sep 20
-- -- Paint 3 (2)      
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2)      
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1)      
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)       Wed, Oct 16 at 9:00 AM
-- -- Buyer Walk Through (1)       Tue, Oct 15 at 4:30 PM
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       Wed, Oct 16 at 9:00 AM @ West View Title
-- -- Remove Coded Lockbox (0)