ADDR
- 48  ::  2222 Deyerle Avenue
[ BUILD: 1812-0087 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Order Appliances (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Ceiling Fans (0)      
Fri    Dec 6      Blower Door Test (1)      
Mon    Dec 9      Inspection (Final HVAC) (1)      
Tue    Dec 10      Inspection (Final Plumbing) (1)      
Wed    Dec 11      Inspection (Final Electric) (1)      
Thu    Dec 12      Stain Hardwood Stairs (1)      
Fri    Dec 13      Request Trash Tote From POA Manager (0)      
--   --   Want electrical walk through
--   --   Send Mirror Sizes to buyer and credit amount On site 9/4
--   --   Savannah brick, country beige vinyl, green front door
--   --   4 snap lights in living room on dimmer Needs dimmer switch
--   --   Electrical outlet in patio for future hot tub See pic. I think is in 6/26
--   --   By requesting two parking spaces in driveway if possible?
--   --   loghting and plubing to be obtained by Ferguson- see selections sheet.
--   --   Cut brick above door (pic)
--   --   Realtor says patio was not expanded?
--   --   Wash brick
--   --   Cabinet hardware needed
--   --   Do not finish bonus room in the garage. Will not get carpet or paint.
--   --   Missing kitchen island granite 9/4
--   --   Courtney please take pictures of the mastr shower door once installed and email/text to Kate so she can send them to the T62 buyer!
--   --  
--   --   Small holes in front brick mortar
--   --   Dining chandelier credit? On counter but may be providing their own?
--   --   CODED LOCKBOX 4848
--   --  
--   --   Need sheet vinyl in closet under stairs
--   --   Clean out garage
--   --   No dimmer for LR lights per BCP
--   --   Upgraded pedastal sink In garage 9/21
--   --   Install sconce light globes
--   --   Sconce upside down in stairway from basement to main level. Install correct light
--   --   Extend front gutter
--   --   Is house getting backsplash before closing?
--   --   Hand railings
--   --   Rear door dead bolt not lined up Weather stripping
--   --   Hang mirrors
--   --   HVAC covers Plus return at stairs
--   --  
--   --   Returen air cover
--   --   Stain steps
--   --   Paint 2 back bonus room
--   --   Basement bath light crooked Tom
--   --   Touch up paint throughout 10/9 seems to be starting
--   --   Handrails on stairs
--   --  
--   --   Molding issue steps to main level
--   --   Molding issue steps to main level
--   --  
--   --   Kitchen cabinet missing trim
--   --   Set fridge (not against wall)
--   --   Touch up paint MB closet
--   --   Touch up paint MB closet Working on it 10/16
--   --  
--   --   MB closet light needs replaced w correct snap light
--   --  
--   --  
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       Starting April 1
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)       May 24
-- -- Windows & Doors (0)      
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)       Patio done 7/31
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       Working on it 6/1
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)       In progress 6/5 (most progress in this townhouse)
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2)      
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        In process 7/31
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process 7/31
-- -- Paint 1 (1)       Tues, Aug 13
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        August 9
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3)       In process 8/17
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Done- all tile 12x12
-- -- Paint 2 (3)       No color 9/21
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)       On site 9/7
-- -- Shoe Moulding (0)       In process 9/25
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       In process 9/21. Need shelving.
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       In process 9/28
-- -- HVAC Trim Out (1)       HVAC is set
-- -- Plumbing Trim Out (2)       Done. Extra toilet in basement.
-- -- Install Appliances (0) *        Sep 20
-- -- Paint 3 (2) *       
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *       
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)       Wed, Oct 16 at 9:00 AM
-- -- Buyer Walk Through (1)       Tue, Oct 15 at 4:30 PM
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       Wed, Oct 16 at 9:00 AM @ West View Title
-- -- Remove Coded Lockbox (0)