Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Building Permit (30) *       
Tue    Jan 27      Order Roof & Floor Trusses (1)      
Wed    Jan 28      Order Windows & Doors (0)      
Wed    Jan 28      Stake Out Home (1)      
Thu    Jan 29      Excavate (2)      
Mon    Feb 2      Inspection (Footers) (1)      
Tue    Feb 3      Inspection (Concrete Wall) (1)      
Wed    Feb 4      Pour Footers (1) *       
Thu    Feb 5      Set Forms (2)      
Mon    Feb 9      Pour Foundation Walls (1)      
Tue    Feb 10      Plumb Slab (2)      
Thu    Feb 12      Inspection (Plumbing Under Slab) (1)      
Fri    Feb 13      Inspection (Conduit Under Slab) (1)      
Mon    Feb 16      Prepare Slab (1)      
Tue    Feb 17      Inspection (Slab) (1)      
Wed    Feb 18      Inspection (Drain Tile) (0)      
Wed    Feb 18      Pour Slab (1) *       
Thu    Feb 19      Settlement Agent Confirmed (0)      
Thu    Feb 19      Framing I (9)      
Wed    Mar 4      Order Steps (0)      
Wed    Mar 4      Order Tubs / Showers (0)      
Wed    Mar 4      Framing II (8)      
Mon    Mar 16      Framing III (8) *       
Thu    Mar 26      Verify Window & Roof Structure (0)      
Thu    Mar 26      Install Stairs (0) *       
Thu    Mar 26      Windows & Doors (0) *       
Thu    Mar 26      House Number and Status in Window (0)      
Thu    Mar 26      Roofing (0) *       
Thu    Mar 26      Order Cabinets (0)      
Thu    Mar 26      Order Appliances (0)      
Thu    Mar 26      Deck (0)      
Thu    Mar 26      Gutters (0)      
Thu    Mar 26      Driveway (0) *       
Thu    Mar 26      Patio (0)      
Thu    Mar 26      Privacy Divider / Fence (0) *       
Thu    Mar 26      Sod / Seed / Landscaping (0)      
Thu    Mar 26      HVAC Rough In (4)      
Wed    Apr 1      Rough In Microwave Vent (0)      
Wed    Apr 1      Plumbing Rough In (4)      
Tue    Apr 7      Electric Rough In (4)      
Mon    Apr 13      Inspection (Rough In HVAC) (1)      
Tue    Apr 14      Inspection (Rough In Plumbing) (1)      
Wed    Apr 15      Inspection (Rough In Electric) (1)      
Thu    Apr 16      Inspection (Framing) (1) *       
Fri    Apr 17      Inspection (Deck Piers) (0)      
Fri    Apr 17      Exterior Vinyl (0) *       
Fri    Apr 17      Exterior Stone (0)      
Fri    Apr 17      Insulation (2) *       
Tue    Apr 21      Inspection (Insulation) (1)      
Wed    Apr 22      Inspection (Electric Service) (0)      
Wed    Apr 22      Set Electric Meter (0) *       
Wed    Apr 22      Inspection (Main Sewer Line) (0)      
Wed    Apr 22      Inspection (Main Water Line) (0)      
Wed    Apr 22      Order Interior Doors & Trim (0)      
Wed    Apr 22      Drywall (Hang) (4) *       
Tue    Apr 28      Loan Approval (0)      
Tue    Apr 28      Deed Preparation (0)      
Tue    Apr 28      Drywall (Tape, Block, Skim, Sand) (6) *       
Wed    May 6      Paint 1 (1)      
Thu    May 7      Garage Door (0)      
Thu    May 7      House Numbers (0)      
Thu    May 7      Mailbox (0)      
Thu    May 7      Cabinet Installation (2) *       
Mon    May 11      Granite Installation (1) *       
Tue    May 12      Interior Trim - Install (3) *       
Fri    May 15      Order Plumbing / Lighting Fixtures (0)      
Fri    May 15      Interior Trim - Paint (1)      
Mon    May 18      Luxury Vinyl Plank (3) *       
Thu    May 21      Luxury Vinyl Tile (0)      
Thu    May 21      Paint 2 (3)      
Tue    May 26      Cover Floors (1)      
Wed    May 27      Deliver Plumbing / Lighting Fixtures (0)      
Wed    May 27      Shoe Moulding (0)      
Wed    May 27      Shelving, Door Knobs, Fire Extinguisher (0) *       
Wed    May 27      Install Coded Lockbox (add extra keys) (0)      
Wed    May 27      Pay Water / Sewer Taps (0)      
Wed    May 27      Set Water Meter (0) *       
Wed    May 27      Electric Trim Out (3) *       
Mon    Jun 1      Ceiling Fans (0)      
Mon    Jun 1      HVAC Trim Out (1) *       
Tue    Jun 2      Blower Door Test (1)      
Wed    Jun 3      Plumbing Trim Out (2) *       
Fri    Jun 5      Install Appliances (0) *       
Fri    Jun 5      Paint 3 (2) *       
Tue    Jun 9      Carpet (2)      
Thu    Jun 11      Appraiser Confirms Construction Completion (0)      
Thu    Jun 11      Inspection (Final HVAC) (1)      
Fri    Jun 12      Inspection (Final Plumbing) (1)      
Mon    Jun 15      Inspection (Final Electric) (1)      
Tue    Jun 16      Inspection (Final Building) (2) *       
Thu    Jun 18      Pre Walk Through (0)      
Thu    Jun 18      Stain Hardwood Stairs (1) *       
Fri    Jun 19      Cleaning (1)      
Mon    Jun 22      Certificate of Occupancy (1) *       
Tue    Jun 23      C.O. to Lender (0)      
Tue    Jun 23      Schedule Closing (0)      
Tue    Jun 23      Buyer Walk Through (1) *       
Wed    Jun 24      Payment for Upgrades (0)      
Wed    Jun 24      Keys to Settlement Agent (0)      
Wed    Jun 24      Review Settlement Statement (0)      
Wed    Jun 24      Jerry Signs Closing Documents (0)      
Wed    Jun 24      Request Trash Tote From POA Manager (0)      
Wed    Jun 24      Closing (1)      
Thu    Jun 25      Remove Coded Lockbox (0)