--   --   Contact Cody Frye 540-908-5586 Called Cody 4 Times 3 messages and no answer as of 9/21 GWB
--   --   Bring paint and brush to cody Greg to bring paint over GWB
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Ceiling Fans (0)      
Fri    Dec 6      Blower Door Test (1)      
Mon    Dec 9      Inspection (Final HVAC) (1)      
Tue    Dec 10      Inspection (Final Plumbing) (1)      
Wed    Dec 11      Inspection (Final Electric) (1)      
Thu    Dec 12      Stain Hardwood Stairs (1)      
Fri    Dec 13      Request Trash Tote From POA Manager (0)      
--   --   Charleston brick, Ivory Vinyl, Green front door
--   --   Charleston Brick, ivory vinyl, gold front door
--   --   Basement bathroom plumbing
--   --   Toilet plumbing basement bath?
--   --   Cabinet hardware Few missing 8/14
--   --   Lazy Susan cabinet issue 8/14?
--   --   Box labeled for 51 is sitting in basement foyer of 50
--   --   Upstairs bath vanity top needed 8/28
--   --   Bathroom door install basement Tom
--   --   Replace fridge door w/dent 9/7 On order 10/16 spoke to Leslie- will take another 6-8 weeks to come in.
--   --   Water leaking HVAC?? 9/7
--   --   No plumbing/sink in garage?
--   --   Gaps between shoe molding and tile in foyer Tile guy
--   --   Pic of master toilet-comfort height?
--   --   Outside vent cover needed Installed but obvious gaps between cover and brick
--   --   HVAC cover needed upstairs Throughout house needs covers
--   --   Gutter drain needed
--   --   Coded lockbox 5050
--   --   Drywall patch pantry
--   --   Handrails on steps
--   --   Paint touch up throughout
--   --  
--   --   Walk Through - Fri 3:30 PM
--   --   Paint front door Gold
--   --   Fix front overhang
--   --   Touch up paint throughout
--   --   Back door hole plugs
--   --   Stain steps
--   --   Touch up paint basement bath door/install hardware
--   --   Gaps in foyer ceramic tile
--   --   Sand/paint pantry drywall repair
--   --   Sand/paint pantry drywall repair
--   --  
--   --   Adjusting cabinet doors
--   --   Touch up paint
--   --   Finish poly on steps
--   --  
--   --   Paint kitchen ceiling Galindez Planning with Cody directly 8/18 GWB
--   --   Patch and paint at ceiling light fixture gap Galindez Planning with Cody directly 8/18 GWB
--   --   Repair lazy susan part in. Installer scheduling with Cody GWB
--   --   Contact Cody Frye 540-908-5586
--   --   Adjust exterior door where daylight can be seen JB workin at bluestone today 9/3
--   --   Ceiling chipped at light on lower stairs Galindez Planning with Cody directly 8/18 GWB
--   --   Caulk/Grout splitting on stairs, bathrooms, hallways Galindez Planning with Cody directly 8/18 GWB
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       Starting April 1
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)      
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)       Patio done 7/31
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       Fri, Jun 20
-- -- Plumbing Rough In (4)       Started 6/5
-- -- Electric Rough In (4)       In process 6/16
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2)       Mon, Jun 24
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        All but garage/basement 7/10
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process 7/13
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        All installed/need hardware
-- -- Granite Installation (1) *        8/21
-- -- Interior Trim - Install (3)       In process 7/31
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       In garage 8/7
-- -- Paint 2 (3)       In process 8/21
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)       On site 9/7
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)      
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       All done but bath fans
-- -- HVAC Trim Out (1)       Set 8/7
-- -- Plumbing Trim Out (2)       Set basement toilet/pedestal sink
-- -- Install Appliances (0) *        Stove, Mon, Sep 16
-- -- Paint 3 (2) *       
-- -- Carpet (2)       Week of Sep 16
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Thursday, 10/17
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       This week
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1)       Thursday 10/17 2:30
-- -- Payment for Upgrades (0)       $1,575
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       Botkin Rose, Fri, Oct 18 at 2:30 PM
-- -- Remove Coded Lockbox (0)