- 50  ::  2226 Deyerle Avenue
[ BUILD: 1812-0089 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Contact Cody Frye 540-908-5586 Called Cody 4 Times 3 messages and no answer as of 9/21 GWB
--   --   Bring paint and brush to cody Greg to bring paint over GWB
Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Inspection (Concrete Wall) (1)      
Wed    Dec 17      Inspection (Conduit Under Slab) (1)      
Thu    Dec 18      Inspection (Drain Tile) (0)      
Thu    Dec 18      Settlement Agent Confirmed (0)      
Thu    Dec 18      Verify Window & Roof Structure (0)      
Thu    Dec 18      Patio (0)      
Thu    Dec 18      Rough In Microwave Vent (0)      
Thu    Dec 18      Inspection (Rough In Plumbing) (1)      
Fri    Dec 19      Inspection (Rough In Electric) (1)      
Mon    Dec 22      Inspection (Framing) (1) *       
Tue    Dec 23      Inspection (Deck Piers) (0)      
Tue    Dec 23      Exterior Stone (0)      
Tue    Dec 23      Set Electric Meter (0) *       
Tue    Dec 23      Inspection (Main Water Line) (0)      
Tue    Dec 23      Loan Approval (0)      
Tue    Dec 23      Deed Preparation (0)      
Tue    Dec 23      Mailbox (0)      
Tue    Dec 23      Interior Trim - Paint (1)      
Wed    Dec 24      Ceiling Fans (0)      
Wed    Dec 24      Blower Door Test (1)      
Thu    Dec 25      Inspection (Final HVAC) (1)      
Fri    Dec 26      Inspection (Final Plumbing) (1)      
Mon    Dec 29      Inspection (Final Electric) (1)      
Tue    Dec 30      Stain Hardwood Stairs (1) *       
Wed    Dec 31      Request Trash Tote From POA Manager (0)      
--   --   Charleston brick, Ivory Vinyl, Green front door
--   --   Charleston Brick, ivory vinyl, gold front door
--   --   Basement bathroom plumbing
--   --   Toilet plumbing basement bath?
--   --   Cabinet hardware Few missing 8/14
--   --   Lazy Susan cabinet issue 8/14?
--   --   Box labeled for 51 is sitting in basement foyer of 50
--   --   Upstairs bath vanity top needed 8/28
--   --   Bathroom door install basement Tom
--   --   Replace fridge door w/dent 9/7 On order 10/16 spoke to Leslie- will take another 6-8 weeks to come in.
--   --   Water leaking HVAC?? 9/7
--   --   No plumbing/sink in garage?
--   --   Gaps between shoe molding and tile in foyer Tile guy
--   --   Pic of master toilet-comfort height?
--   --   Outside vent cover needed Installed but obvious gaps between cover and brick
--   --   HVAC cover needed upstairs Throughout house needs covers
--   --   Gutter drain needed
--   --   Coded lockbox 5050
--   --   Drywall patch pantry
--   --   Handrails on steps
--   --   Paint touch up throughout
--   --  
--   --   Walk Through - Fri 3:30 PM
--   --   Paint front door Gold
--   --   Fix front overhang
--   --   Touch up paint throughout
--   --   Back door hole plugs
--   --   Stain steps
--   --   Touch up paint basement bath door/install hardware
--   --   Gaps in foyer ceramic tile
--   --   Sand/paint pantry drywall repair
--   --   Sand/paint pantry drywall repair
--   --  
--   --   Adjusting cabinet doors
--   --   Touch up paint
--   --   Finish poly on steps
--   --  
--   --   Paint kitchen ceiling Galindez Planning with Cody directly 8/18 GWB
--   --   Patch and paint at ceiling light fixture gap Galindez Planning with Cody directly 8/18 GWB
--   --   Repair lazy susan part in. Installer scheduling with Cody GWB
--   --   Contact Cody Frye 540-908-5586
--   --   Adjust exterior door where daylight can be seen JB workin at bluestone today 9/3
--   --   Ceiling chipped at light on lower stairs Galindez Planning with Cody directly 8/18 GWB
--   --   Caulk/Grout splitting on stairs, bathrooms, hallways Galindez Planning with Cody directly 8/18 GWB
-- -- Building Permit (30) *       
    Plumbing for sink in garage and add 18 guage sink  
    Whirlpool SS appliances  
    Comfort Height Toilet in Master  
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       Starting April 1
    Finished room behind garage (carpet, ceiling light, wall outlets) with full bathroom  
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *        Patio done 7/31
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)       Started 6/5
    Installation of pipe for possible future radon mitigation system  
-- -- Electric Rough In (4)       In process 6/16
-- -- Inspection (Rough In HVAC) (1)       Fri, Jun 20
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *        Mon, Jun 24
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        All but garage/basement 7/10
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process 7/13
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        All installed/need hardware
-- -- Granite Installation (1) *        8/21
-- -- Interior Trim - Install (3) *        In process 7/31
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       In garage 8/7
-- -- Paint 2 (3)       In process 8/21
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)       On site 9/7
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *       
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3) *        All done but bath fans
-- -- HVAC Trim Out (1) *        Set 8/7
-- -- Plumbing Trim Out (2) *        Set basement toilet/pedestal sink
-- -- Install Appliances (0) *        Stove, Mon, Sep 16
-- -- Paint 3 (2) *       
-- -- Carpet (2)       Week of Sep 16
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Thursday, 10/17
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       This week
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1) *        Thursday 10/17 2:30
-- -- Payment for Upgrades (0)       $1,575
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       Botkin Rose, Fri, Oct 18 at 2:30 PM
-- -- Remove Coded Lockbox (0)