| -- | -- | Contact Cody Frye 540-908-5586 | Called Cody 4 Times 3 messages and no answer as of 9/21 GWB | |
| -- | -- | Bring paint and brush to cody | Greg to bring paint over GWB | |
| Tue | Dec 16 | Ratified Contract? (0) | ||
| Tue | Dec 16 | $2500 Deposit Received (0) | ||
| Tue | Dec 16 | Association Packet Requested (0) | ||
| Tue | Dec 16 | Association Packet Received (0) | ||
| Tue | Dec 16 | Selections Meeting (0) | ||
| Tue | Dec 16 | Selections Sheet Signed (0) | ||
| Tue | Dec 16 | Amendment for Upgrades (B,S,L,T,BCP) (0) | ||
| Tue | Dec 16 | Deposit For Upgrades Received (0) | ||
| Tue | Dec 16 | Inspection (Concrete Wall) (1) | ||
| Wed | Dec 17 | Inspection (Conduit Under Slab) (1) | ||
| Thu | Dec 18 | Inspection (Drain Tile) (0) | ||
| Thu | Dec 18 | Settlement Agent Confirmed (0) | ||
| Thu | Dec 18 | Verify Window & Roof Structure (0) | ||
| Thu | Dec 18 | Patio (0) | ||
| Thu | Dec 18 | Rough In Microwave Vent (0) | ||
| Thu | Dec 18 | Inspection (Rough In Plumbing) (1) | ||
| Fri | Dec 19 | Inspection (Rough In Electric) (1) | ||
| Mon | Dec 22 | Inspection (Framing) (1) * | ||
| Tue | Dec 23 | Inspection (Deck Piers) (0) | ||
| Tue | Dec 23 | Exterior Stone (0) | ||
| Tue | Dec 23 | Set Electric Meter (0) * | ||
| Tue | Dec 23 | Inspection (Main Water Line) (0) | ||
| Tue | Dec 23 | Loan Approval (0) | ||
| Tue | Dec 23 | Deed Preparation (0) | ||
| Tue | Dec 23 | Mailbox (0) | ||
| Tue | Dec 23 | Interior Trim - Paint (1) | ||
| Wed | Dec 24 | Ceiling Fans (0) | ||
| Wed | Dec 24 | Blower Door Test (1) | ||
| Thu | Dec 25 | Inspection (Final HVAC) (1) | ||
| Fri | Dec 26 | Inspection (Final Plumbing) (1) | ||
| Mon | Dec 29 | Inspection (Final Electric) (1) | ||
| Tue | Dec 30 | Stain Hardwood Stairs (1) * | ||
| Wed | Dec 31 | Request Trash Tote From POA Manager (0) | ||
| -- | -- | Charleston brick, Ivory Vinyl, Green front door | ||
| -- | -- | Charleston Brick, ivory vinyl, gold front door | ||
| -- | -- | Basement bathroom plumbing | ||
| -- | -- | Toilet plumbing basement bath? | ||
| -- | -- | Cabinet hardware | Few missing 8/14 | |
| -- | -- | Lazy Susan cabinet issue 8/14? | ||
| -- | -- | Box labeled for 51 is sitting in basement foyer of 50 | ||
| -- | -- | Upstairs bath vanity top needed 8/28 | ||
| -- | -- | Bathroom door install basement | Tom | |
| -- | -- | Replace fridge door w/dent 9/7 | On order 10/16 spoke to Leslie- will take another 6-8 weeks to come in. | |
| -- | -- | Water leaking HVAC?? 9/7 | ||
| -- | -- | No plumbing/sink in garage? | ||
| -- | -- | Gaps between shoe molding and tile in foyer | Tile guy | |
| -- | -- | Pic of master toilet-comfort height? | ||
| -- | -- | Outside vent cover needed | Installed but obvious gaps between cover and brick | |
| -- | -- | HVAC cover needed upstairs | Throughout house needs covers | |
| -- | -- | Gutter drain needed | ||
| -- | -- | Coded lockbox 5050 | ||
| -- | -- | Drywall patch pantry | ||
| -- | -- | Handrails on steps | ||
| -- | -- | Paint touch up throughout | ||
| -- | -- | |||
| -- | -- | Walk Through - Fri 3:30 PM | ||
| -- | -- | Paint front door | Gold | |
| -- | -- | Fix front overhang | ||
| -- | -- | Touch up paint throughout | ||
| -- | -- | Back door hole plugs | ||
| -- | -- | Stain steps | ||
| -- | -- | Touch up paint basement bath door/install hardware | ||
| -- | -- | Gaps in foyer ceramic tile | ||
| -- | -- | Sand/paint pantry drywall repair | ||
| -- | -- | Sand/paint pantry drywall repair | ||
| -- | -- | |||
| -- | -- | Adjusting cabinet doors | ||
| -- | -- | Touch up paint | ||
| -- | -- | Finish poly on steps | ||
| -- | -- | |||
| -- | -- | Paint kitchen ceiling | Galindez Planning with Cody directly 8/18 GWB | |
| -- | -- | Patch and paint at ceiling light fixture gap | Galindez Planning with Cody directly 8/18 GWB | |
| -- | -- | Repair lazy susan | part in. Installer scheduling with Cody GWB | |
| -- | -- | Contact Cody Frye | 540-908-5586 | |
| -- | -- | Adjust exterior door where daylight can be seen | JB workin at bluestone today 9/3 | |
| -- | -- | Ceiling chipped at light on lower stairs | Galindez Planning with Cody directly 8/18 GWB | |
| -- | -- | Caulk/Grout splitting on stairs, bathrooms, hallways | Galindez Planning with Cody directly 8/18 GWB | |
| -- | -- | Building Permit (30) * | ||
| Plumbing for sink in garage and add 18 guage sink | ||||
| Whirlpool SS appliances | ||||
| Comfort Height Toilet in Master | ||||
| -- | -- | Order Roof & Floor Trusses (1) | ||
| -- | -- | Order Windows & Doors (0) | ||
| -- | -- | Stake Out Home (1) | ||
| -- | -- | Excavate (2) | ||
| -- | -- | Inspection (Footers) (1) | ||
| -- | -- | Pour Footers (1) * | ||
| -- | -- | Set Forms (2) | ||
| -- | -- | Pour Foundation Walls (1) | ||
| -- | -- | Plumb Slab (2) | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) | ||
| -- | -- | Prepare Slab (1) | ||
| -- | -- | Inspection (Slab) (1) | ||
| -- | -- | Pour Slab (1) * | ||
| -- | -- | Framing I (9) | Starting April 1 | |
| Finished room behind garage (carpet, ceiling light, wall outlets) with full bathroom | ||||
| -- | -- | Order Steps (0) | ||
| -- | -- | Order Tubs / Showers (0) | ||
| -- | -- | Framing II (8) | ||
| -- | -- | Framing III (8) * | ||
| -- | -- | Install Stairs (0) * | ||
| -- | -- | Windows & Doors (0) * | ||
| -- | -- | House Number and Status in Window (0) | ||
| -- | -- | Roofing (0) * | ||
| -- | -- | Order Cabinets (0) | ||
| -- | -- | Order Appliances (0) | ||
| -- | -- | Deck (0) | ||
| -- | -- | Gutters (0) | ||
| -- | -- | Driveway (0) * | Patio done 7/31 | |
| -- | -- | Privacy Divider / Fence (0) * | ||
| -- | -- | Sod / Seed / Landscaping (0) | ||
| -- | -- | HVAC Rough In (4) | ||
| -- | -- | Plumbing Rough In (4) | Started 6/5 | |
| Installation of pipe for possible future radon mitigation system | ||||
| -- | -- | Electric Rough In (4) | In process 6/16 | |
| -- | -- | Inspection (Rough In HVAC) (1) | Fri, Jun 20 | |
| -- | -- | Exterior Vinyl (0) * | ||
| -- | -- | Insulation (2) * | Mon, Jun 24 | |
| -- | -- | Inspection (Insulation) (1) | ||
| -- | -- | Inspection (Electric Service) (0) | ||
| -- | -- | Inspection (Main Sewer Line) (0) | ||
| -- | -- | Order Interior Doors & Trim (0) | ||
| -- | -- | Drywall (Hang) (4) * | All but garage/basement 7/10 | |
| -- | -- | Drywall (Tape, Block, Skim, Sand) (6) * | In process 7/13 | |
| -- | -- | Paint 1 (1) | ||
| -- | -- | Garage Door (0) | ||
| -- | -- | House Numbers (0) | ||
| -- | -- | Cabinet Installation (2) * | All installed/need hardware | |
| -- | -- | Granite Installation (1) * | 8/21 | |
| -- | -- | Interior Trim - Install (3) * | In process 7/31 | |
| -- | -- | Order Plumbing / Lighting Fixtures (0) | ||
| -- | -- | Luxury Vinyl Plank (3) * | ||
| -- | -- | Luxury Vinyl Tile (0) | In garage 8/7 | |
| -- | -- | Paint 2 (3) | In process 8/21 | |
| -- | -- | Cover Floors (1) | ||
| -- | -- | Deliver Plumbing / Lighting Fixtures (0) | On site 9/7 | |
| -- | -- | Shoe Moulding (0) | ||
| -- | -- | Shelving, Door Knobs, Fire Extinguisher (0) * | ||
| -- | -- | Install Coded Lockbox (add extra keys) (0) | ||
| -- | -- | Pay Water / Sewer Taps (0) | ||
| -- | -- | Set Water Meter (0) * | ||
| -- | -- | Electric Trim Out (3) * | All done but bath fans | |
| -- | -- | HVAC Trim Out (1) * | Set 8/7 | |
| -- | -- | Plumbing Trim Out (2) * | Set basement toilet/pedestal sink | |
| -- | -- | Install Appliances (0) * | Stove, Mon, Sep 16 | |
| -- | -- | Paint 3 (2) * | ||
| -- | -- | Carpet (2) | Week of Sep 16 | |
| -- | -- | Appraiser Confirms Construction Completion (0) | ||
| -- | -- | Inspection (Final Building) (2) * | Thursday, 10/17 | |
| -- | -- | Pre Walk Through (0) | ||
| -- | -- | Cleaning (1) | This week | |
| -- | -- | Certificate of Occupancy (1) * | ||
| -- | -- | C.O. to Lender (0) | ||
| -- | -- | Schedule Closing (0) | ||
| -- | -- | Buyer Walk Through (1) * | Thursday 10/17 2:30 | |
| -- | -- | Payment for Upgrades (0) | $1,575 | |
| -- | -- | Keys to Settlement Agent (0) | ||
| -- | -- | Review Settlement Statement (0) | ||
| -- | -- | Jerry Signs Closing Documents (0) | ||
| -- | -- | Closing (1) | Botkin Rose, Fri, Oct 18 at 2:30 PM | |
| -- | -- | Remove Coded Lockbox (0) | ||