| -- | -- | Marina Zotov- 540-383-3308 | ||
| Tue | Dec 16 | Ratified Contract? (0) | ||
| Tue | Dec 16 | $2500 Deposit Received (0) | ||
| Tue | Dec 16 | Association Packet Requested (0) | ||
| Tue | Dec 16 | Association Packet Received (0) | ||
| Tue | Dec 16 | Selections Meeting (0) | ||
| Tue | Dec 16 | Selections Sheet Signed (0) | ||
| Tue | Dec 16 | Amendment for Upgrades (B,S,L,T,BCP) (0) | ||
| Tue | Dec 16 | Deposit For Upgrades Received (0) | ||
| Tue | Dec 16 | Inspection (Concrete Wall) (1) | ||
| Wed | Dec 17 | Inspection (Conduit Under Slab) (1) | ||
| Thu | Dec 18 | Inspection (Drain Tile) (0) | ||
| Thu | Dec 18 | Settlement Agent Confirmed (0) | ||
| Thu | Dec 18 | Verify Window & Roof Structure (0) | ||
| Thu | Dec 18 | Order Appliances (0) | ||
| Thu | Dec 18 | Patio (0) | ||
| Thu | Dec 18 | Rough In Microwave Vent (0) | ||
| Thu | Dec 18 | Inspection (Rough In Plumbing) (1) | ||
| Fri | Dec 19 | Inspection (Rough In Electric) (1) | ||
| Mon | Dec 22 | Inspection (Framing) (1) * | ||
| Tue | Dec 23 | Inspection (Deck Piers) (0) | ||
| Tue | Dec 23 | Exterior Stone (0) | ||
| Tue | Dec 23 | Set Electric Meter (0) * | ||
| Tue | Dec 23 | Inspection (Main Water Line) (0) | ||
| Tue | Dec 23 | Loan Approval (0) | ||
| Tue | Dec 23 | Deed Preparation (0) | ||
| Tue | Dec 23 | Mailbox (0) | ||
| Tue | Dec 23 | Interior Trim - Paint (1) | ||
| Wed | Dec 24 | Ceiling Fans (0) | ||
| Wed | Dec 24 | Blower Door Test (1) | ||
| Thu | Dec 25 | Inspection (Final HVAC) (1) | ||
| Fri | Dec 26 | Inspection (Final Plumbing) (1) | ||
| Mon | Dec 29 | Inspection (Final Electric) (1) | ||
| Tue | Dec 30 | Stain Hardwood Stairs (1) * | ||
| Wed | Dec 31 | Request Trash Tote From POA Manager (0) | ||
| -- | -- | Carter’s Grove brick, bone vinyl, green front door | ||
| -- | -- | Corner kitchen cabinet door needed | Kyle | |
| -- | -- | Cover hardwood floors | ||
| -- | -- | Clean out back room | ||
| -- | -- | Clean out garage | ||
| -- | -- | Final electrical trim out | ||
| -- | -- | Outdoor vent cover needed | JB | |
| -- | -- | Large cabinet blemish | One drawer that needs replacing | |
| -- | -- | Where are the keys? | Tom | |
| -- | -- | Fan cover (LR) missing? Broken? | ||
| -- | -- | HVAC covers needed | ||
| -- | -- | Lots of caulk on hall bath fan | ||
| -- | -- | CODED LOCKBOX 5151 | ||
| -- | -- | Walk Through - Tue, Oct 1 | ||
| -- | -- | Touch up paint throughout | ||
| -- | -- | Hoping to close Wednesday- Buyer/agent to walk through on Tuesday afternoon | ||
| -- | -- | Replace front light | ||
| -- | -- | Hook up garage door opener | ||
| -- | -- | Replace damaged drawer | Arrived 10/9 | |
| -- | -- | Add dishwasher brackets | ||
| -- | -- | Exhaust fan grill needed | ||
| -- | -- | Doorstop into garage | ||
| -- | -- | HVAC covers | ||
| -- | -- | Handle master bath vanity | Kyle-hardware at showroom | |
| -- | -- | Window screens | ||
| -- | -- | LR ceiling fan globe | Tom | |
| -- | -- | Stair lights uneven | ||
| -- | -- | Touch up paint | ||
| -- | -- | Closed! | ||
| -- | -- | Marina Zotov 540-383-4308 | ||
| -- | -- | Paint touch up | ||
| -- | -- | Cabinets | ||
| -- | -- | Oven wire/rack | ||
| -- | -- | Master bath hardware | ||
| -- | -- | Building Permit (30) * | ||
| -- | -- | Order Roof & Floor Trusses (1) | ||
| -- | -- | Order Windows & Doors (0) | ||
| -- | -- | Stake Out Home (1) | ||
| -- | -- | Excavate (2) | ||
| -- | -- | Inspection (Footers) (1) | ||
| -- | -- | Pour Footers (1) * | ||
| -- | -- | Set Forms (2) | ||
| -- | -- | Pour Foundation Walls (1) | ||
| -- | -- | Plumb Slab (2) | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) | ||
| -- | -- | Prepare Slab (1) | ||
| -- | -- | Inspection (Slab) (1) | ||
| -- | -- | Pour Slab (1) * | ||
| -- | -- | Framing I (9) | ||
| -- | -- | Order Steps (0) | ||
| -- | -- | Order Tubs / Showers (0) | ||
| -- | -- | Framing II (8) | ||
| -- | -- | Framing III (8) * | ||
| -- | -- | Install Stairs (0) * | ||
| -- | -- | Windows & Doors (0) * | ||
| -- | -- | House Number and Status in Window (0) | ||
| -- | -- | Roofing (0) * | ||
| -- | -- | Order Cabinets (0) | ||
| -- | -- | Deck (0) | ||
| -- | -- | Gutters (0) | ||
| -- | -- | Driveway (0) * | Patio done 7/31 | |
| Expanded 12x18 Patio | ||||
| Expanded driveway | ||||
| -- | -- | Privacy Divider / Fence (0) * | ||
| -- | -- | Sod / Seed / Landscaping (0) | ||
| -- | -- | HVAC Rough In (4) | ||
| -- | -- | Plumbing Rough In (4) | In process 6/16 | |
| Unfinished bonus room to have rough-in plumbing for future bathroom | ||||
| -- | -- | Electric Rough In (4) | In process 6/16 | |
| -- | -- | Inspection (Rough In HVAC) (1) | Mon Jun 24 or Tue Jun 25 | |
| -- | -- | Exterior Vinyl (0) * | ||
| -- | -- | Insulation (2) * | ||
| -- | -- | Inspection (Insulation) (1) | ||
| -- | -- | Inspection (Electric Service) (0) | ||
| -- | -- | Inspection (Main Sewer Line) (0) | ||
| -- | -- | Order Interior Doors & Trim (0) | ||
| -- | -- | Drywall (Hang) (4) * | On site 7/7 | |
| -- | -- | Drywall (Tape, Block, Skim, Sand) (6) * | ||
| -- | -- | Paint 1 (1) | ||
| -- | -- | Garage Door (0) | ||
| -- | -- | House Numbers (0) | ||
| -- | -- | Cabinet Installation (2) * | Installing 8/14 | |
| -- | -- | Granite Installation (1) * | ||
| -- | -- | Interior Trim - Install (3) * | In process 8/14 | |
| -- | -- | Order Plumbing / Lighting Fixtures (0) | ||
| -- | -- | Luxury Vinyl Plank (3) * | ||
| -- | -- | Luxury Vinyl Tile (0) | Week of Aug 19 | |
| -- | -- | Paint 2 (3) | ||
| Front door to be dark green used in the neighborhood | ||||
| -- | -- | Cover Floors (1) | Please | |
| -- | -- | Deliver Plumbing / Lighting Fixtures (0) | ||
| -- | -- | Shoe Moulding (0) | Week of Sep 16 | |
| -- | -- | Shelving, Door Knobs, Fire Extinguisher (0) * | In process 9/18 | |
| -- | -- | Install Coded Lockbox (add extra keys) (0) | ||
| -- | -- | Pay Water / Sewer Taps (0) | ||
| -- | -- | Set Water Meter (0) * | ||
| -- | -- | Electric Trim Out (3) * | 90%done 9/25 | |
| -- | -- | HVAC Trim Out (1) * | Furnace set 8/7 | |
| -- | -- | Plumbing Trim Out (2) * | ||
| -- | -- | Install Appliances (0) * | ||
| -- | -- | Paint 3 (2) * | ||
| -- | -- | Carpet (2) | ||
| -- | -- | Appraiser Confirms Construction Completion (0) | ||
| -- | -- | Inspection (Final Building) (2) * | ||
| -- | -- | Pre Walk Through (0) | ||
| -- | -- | Cleaning (1) | Completed Sunday 10/6 and 10/7 | |
| -- | -- | Certificate of Occupancy (1) * | ||
| -- | -- | C.O. to Lender (0) | ||
| -- | -- | Schedule Closing (0) | Wednesday 10/8? | |
| -- | -- | Buyer Walk Through (1) * | ||
| -- | -- | Payment for Upgrades (0) | $1,400 | |
| -- | -- | Keys to Settlement Agent (0) | ||
| -- | -- | Review Settlement Statement (0) | ||
| -- | -- | Jerry Signs Closing Documents (0) | ||
| -- | -- | Closing (1) | Title Alliance, Wed, Oct 9 at 11AM | |
| -- | -- | Remove Coded Lockbox (0) | ||