[ BUILD: 1812-0091 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Wed    Nov 27      Ratified Contract? (0)      
Wed    Nov 27      $2500 Deposit Received (0)      
Wed    Nov 27      Association Packet Requested (0)      
Wed    Nov 27      Association Packet Received (0)      
Wed    Nov 27      Selections Meeting (0)      
Wed    Nov 27      Selections Sheet Signed (0)      
Wed    Nov 27      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Wed    Nov 27      Deposit For Upgrades Received (0)      
Wed    Nov 27      Inspection (Concrete Wall) (1)      
Thu    Nov 28      Inspection (Conduit Under Slab) (1)      
Fri    Nov 29      Inspection (Drain Tile) (0)      
Fri    Nov 29      Settlement Agent Confirmed (0)      
Fri    Nov 29      Verify Window & Roof Structure (0)      
Fri    Nov 29      Patio (0)      
Fri    Nov 29      Rough In Microwave Vent (0)      
Fri    Nov 29      Inspection (Rough In Plumbing) (1)      
Mon    Dec 2      Inspection (Rough In Electric) (1)      
Tue    Dec 3      Inspection (Deck Piers) (0)      
Tue    Dec 3      Inspection (Framing) (1)      
Wed    Dec 4      Exterior Stone (0)      
Wed    Dec 4      Set Electric Meter (0)      
Wed    Dec 4      Inspection (Main Water Line) (0)      
Wed    Dec 4      Loan Approval (0)      
Wed    Dec 4      Deed Preparation (0)      
Wed    Dec 4      Mailbox (0)      
Wed    Dec 4      Interior Trim - Paint (1)      
Thu    Dec 5      Ceiling Fans (0)      
Thu    Dec 5      Blower Door Test (1)      
Fri    Dec 6      Inspection (Final HVAC) (1)      
Mon    Dec 9      Inspection (Final Plumbing) (1)      
Tue    Dec 10      Inspection (Final Electric) (1)      
Wed    Dec 11      Stain Hardwood Stairs (1)      
Thu    Dec 12      Request Trash Tote From POA Manager (0)      
--   --   Buyer is requesting all "daylight" LED bulbs- What does Ferguson provide?
--   --   Lighting Plumbing Portfolio and PRicing
--   --   Ivory vinyl, red front door
--   --   Charleston brick, country beige vinyl, green front door
--   --   Solar tube is on site
--   --   Landing top step of first section upstairs has big “creak” when walked on Many creaks on both sets of stairs
--   --   Tub liner up bath
--   --   Roof issue (see pic) Soffit - Davenport (http://bit.ly/2kj5daw)
--   --   Concrete patch needed at toilet in basement bath 8/28
--   --   1) Crocus Petal Purple - Medium room (two sides) 2) Island Sunset - Small Room (two sides) 3) Banana Yellow - Master bedroom One wall 4) Living Room- Berry wine (TV mount wall only)
--   --   Missing molding/flashing around front entrance (see pic)
--   --   Corner cabinet missing door
--   --   Ceiling fans not installed in bedrooms as per BCP notes
--   --   Needs vinyl under stairs
--   --   Bathroom basement hole. Tile repairs.
--   --   Dining room dimmer switch needed
--   --   Attic access panel needed
--   --   Trim in upstairs hall baths
--   --   Bath lights missing globes
--   --   CODED LOCKBOX 5252
--   --   Handrails needed
--   --   Stain steps
--   --   Gaps in ceramic foyer tile
--   --   Missing smoke detector In basement bonus room
--   --   Back door hole plugs
--   --   Metal strip for dishwasher to attach to counter on site
--   --   Cabinet trim needed
--   --   Cabinet hardware (1) needed
--   --   Needs paint 3
--   --   Globe to bedroom ceiling fan On order
--   --   Globe to bedroom ceiling fan
--   --  
--   --   Solar panel cover install
--   --   Upstairs bath vanity door hits wall
--   --   Attic access needs installed
--   --   Drawer front-left of the stove Teeny chip-is that issue or wrong townhouse?
--   --   Crooked plastic porch cover things...
--   --   Broken trim at steps
--   --   Flooring issues (tape) hall bath
--   --   Touch up paint throughout
--   --   Hall drywall shower head repair
--   --   Need leg on wire shelf in pantry
--   --   Need white plugs to go in patio doors Half-completed 10/26
--   --   Chips and cabinet to the right of dishwasher In, to be delivered on 10/29
--   --   Dimmer switch on dining room light
--   --   Surround sound-ask Tom
--   --   Cover on hole behind TV
--   --   Half bath plumbing leak
--   --   Cover on fan in half bath
--   --   Adjust closet doors
--   --   Adjust pocket door
--   --   Adjust j channel holding up roof front door Tom (?) - Adjust j channel, fill gap with caulk
--   --   Peep hole front door
--   --  
--   --   Garage door is missing white trim piece
--   --   Paint touch up needed LR ceiling
--   --   Stair trim needed basement to main level
--   --   Dimmer switch on living room lights Kate will follow up
--   --  
--   --   Homeowner wants Tom to widen driveway
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)       Need tub/shower in both up bathrooms
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)      
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)       Patio done 7/31
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)       Buyer wants tub/shower in both Up bath and Master
-- -- Electric Rough In (4)       In process 6/26
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2)       Ready as of June 27
-- -- Inspection (Insulation) (1)       Mon, July 8 ?
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        in process 7/31
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Needs sanding 8/7
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        August 9
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3)       In process 8/28
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Underlayment down 8/21
-- -- Paint 2 (3)      
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)       In foyer
-- -- Shelving, Door Knobs, Fire Extinguisher (0)      
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       In process 9/25
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       Complete except 1/2 bath
-- -- Install Appliances (0) *        In garage 10/9
-- -- Paint 3 (2) *        10/19 in process
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)       Tell Carey when cleaned
-- -- Inspection (Final Building) (2) *       
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1)       Mon, Oct 21 2:30pm
-- -- Payment for Upgrades (0)       $4,310
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       West View Title, Oct 31 at 12PM
-- -- Remove Coded Lockbox (0)