- 53  ::  2232 Deyerle Avenue
[ BUILD: 1812-0092 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Paint touch up in Living room Galindez GWB
--   --   Nancy - 703-965-2167
Fri    Sep 20      Ratified Contract? (0)      
Fri    Sep 20      $2500 Deposit Received (0)      
Fri    Sep 20      Association Packet Requested (0)      
Fri    Sep 20      Association Packet Received (0)      
Fri    Sep 20      Selections Meeting (0)      
Fri    Sep 20      Selections Sheet Signed (0)      
Fri    Sep 20      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Fri    Sep 20      Deposit For Upgrades Received (0)      
Fri    Sep 20      Inspection (Concrete Wall) (1)      
Mon    Sep 23      Inspection (Conduit Under Slab) (1)      
Tue    Sep 24      Inspection (Drain Tile) (0)      
Tue    Sep 24      Settlement Agent Confirmed (0)      
Tue    Sep 24      Verify Window & Roof Structure (0)      
Tue    Sep 24      Patio (0)      
Tue    Sep 24      Rough In Microwave Vent (0)      
Tue    Sep 24      Inspection (Rough In Plumbing) (1)      
Wed    Sep 25      Inspection (Rough In Electric) (1)      
Thu    Sep 26      Inspection (Deck Piers) (0)      
Thu    Sep 26      Inspection (Framing) (1)      
Fri    Sep 27      Exterior Stone (0)      
Fri    Sep 27      Set Electric Meter (0)      
Fri    Sep 27      Inspection (Main Water Line) (0)      
Fri    Sep 27      Loan Approval (0)      
Fri    Sep 27      Deed Preparation (0)      
Fri    Sep 27      Mailbox (0)      
Fri    Sep 27      Interior Trim - Paint (1)      
Mon    Sep 30      Ceiling Fans (0)      
Mon    Sep 30      Blower Door Test (1)      
Tue    Oct 1      Inspection (Final HVAC) (1)      
Wed    Oct 2      Inspection (Final Plumbing) (1)      
Thu    Oct 3      Inspection (Final Electric) (1)      
Fri    Oct 4      Stain Hardwood Stairs (1)      
Mon    Oct 7      Request Trash Tote From POA Manager (0)      
--   --   Charleston Brick, Ivory Vinyl,
--   --   Chalreston Brick, Country Beige Vinyl,green door
--   --   Charleston- Country Beige Vinyl- GREEN DOOR
--   --   Lease ends Aug 31
--   --   Need tub liner upstairs And in basement
--   --   Color issue in brick on side of house?
--   --   Concrete patch needed basement toilet 8/28
--   --   Cabinet hardware needed All vanities need hardware also
--   --   Closet door hardware and adjustments JB
--   --   Repaint back wall in bedroom to paint an incorrect color Accent wall? Upstairs hall and basement bonus room.
--   --   Attic access panel needed in master closet In. Needs painting.
--   --   Install handrails JB
--   --   Stain steps To be scheduled
--   --   Install shoe mold
--   --   Gaps in ceramic tile in foyer between shoe molding Appears to have been caulked. One spot remains near steps.
--   --   CODED LOCKBOX 5353
--   --   Home Inspection - Thurs, Oct 3 at 1PM Benjamin Meredith
--   --   Drain spouts needed
--   --   Touch up paint needed after drywall patches
--   --   Touch up paint throughout needed
--   --   Basement bath hole/tile repair
--   --   Need same colored lightbulbs above island
--   --   Outdoor electrical trim out needed
--   --   HVAC covers needed
--   --   More light bulbs MB
--   --   Home Inspection, Mon, Oct 7 at 4:30 PM Benjamin Meredith
--   --   HVAC covers
--   --   Missing siding at rear of house
--   --   Extend splash blocks
--   --   Washer drain too high to be effective at washer pan
--   --   Two side-by-side switches that control ceiling fan. Recommend repair by an electrician
--   --   Cleaning
--   --   Brick on side of townhouse
--   --   Closed!
--   --   Cracked Drawer needs replacing
--   --   Cracks on wall on 3rd floor John Weeks
--   --   Finish drywall around power box John Weeks
--   --   install cabinet door John Weeks
--   --  
--   --  
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1)      
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8)      
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)      
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)       Patio done 7/31
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       week of 7/1
-- -- Plumbing Rough In (4)       Finishing 6/20
-- -- Electric Rough In (4)       should be done 7/1
-- -- Exterior Vinyl (0)       In process 6/22
-- -- Insulation (2)       Ready as of July 8
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4)       On site 7/31
-- -- Drywall (Tape, Block, Skim, Sand) (6)       Needs sanding 8/17
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2)       August 9
-- -- Granite Installation (1)      
-- -- Interior Trim - Install (3)       In process 8/28
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3)      
-- -- Luxury Vinyl Tile (0)       In garage 8/7
-- -- Paint 2 (3)      
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       Maybe Wed, Sep 18?
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       9/16 in process
-- -- HVAC Trim Out (1)       Set 8/10
-- -- Plumbing Trim Out (2)       All but basement toilet
-- -- Install Appliances (0)       Wed, Sep 18?
-- -- Paint 3 (2)      
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2)       Final Building Inspection Monday 10/7 AM
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Has Begun
-- -- Certificate of Occupancy (1)      
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1)       Tuesday October 8 at 12 NOON to MEET TOM
-- -- Payment for Upgrades (0)       $9,979.74 (or something similar)
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       West View Title, Wed, Oct 9 at 2PM
-- -- Remove Coded Lockbox (0)