| -- | -- | Property Manager = April Watts, 540-607-1068 | Tenant likely not moving in until Jan 3 or 6 | |
| Tue | Dec 16 | Ratified Contract? (0) | ||
| Tue | Dec 16 | $2500 Deposit Received (0) | ||
| Tue | Dec 16 | Association Packet Requested (0) | ||
| Tue | Dec 16 | Association Packet Received (0) | ||
| Tue | Dec 16 | Selections Meeting (0) | ||
| Tue | Dec 16 | Selections Sheet Signed (0) | ||
| Tue | Dec 16 | Amendment for Upgrades (B,S,L,T,BCP) (0) | ||
| Tue | Dec 16 | Deposit For Upgrades Received (0) | ||
| Tue | Dec 16 | Inspection (Concrete Wall) (1) | ||
| Wed | Dec 17 | Inspection (Conduit Under Slab) (1) | ||
| Thu | Dec 18 | Inspection (Drain Tile) (0) | ||
| Thu | Dec 18 | Settlement Agent Confirmed (0) | ||
| Thu | Dec 18 | Verify Window & Roof Structure (0) | ||
| Thu | Dec 18 | Patio (0) | ||
| Thu | Dec 18 | Rough In Microwave Vent (0) | ||
| Thu | Dec 18 | Inspection (Rough In Plumbing) (1) | ||
| Fri | Dec 19 | Inspection (Rough In Electric) (1) | ||
| Mon | Dec 22 | Inspection (Framing) (1) * | ||
| Tue | Dec 23 | Inspection (Deck Piers) (0) | ||
| Tue | Dec 23 | Exterior Stone (0) | ||
| Tue | Dec 23 | Set Electric Meter (0) * | ||
| Tue | Dec 23 | Inspection (Main Water Line) (0) | ||
| Tue | Dec 23 | Loan Approval (0) | ||
| Tue | Dec 23 | Deed Preparation (0) | ||
| Tue | Dec 23 | Mailbox (0) | ||
| Tue | Dec 23 | Interior Trim - Paint (1) | ||
| Wed | Dec 24 | Ceiling Fans (0) | ||
| Wed | Dec 24 | Blower Door Test (1) | ||
| Thu | Dec 25 | Inspection (Final HVAC) (1) | ||
| Fri | Dec 26 | Inspection (Final Plumbing) (1) | ||
| Mon | Dec 29 | Inspection (Final Electric) (1) | ||
| Tue | Dec 30 | Stain Hardwood Stairs (1) * | ||
| Wed | Dec 31 | Request Trash Tote From POA Manager (0) | ||
| -- | -- | Ivory vinyl, red front door | ||
| -- | -- | Missing window 8/3 | ||
| -- | -- | Bathroom framing issue 8/21 (pic) | ||
| -- | -- | NEED PHOTOS OF CLEAN WALLS BEFORE INSULATION | Taken 8/24 | |
| -- | -- | Hole in drywall/basement. See pic 8/24 | Covered w/insulation 8/28 | |
| -- | -- | Door lock in broken. Drywaller requests master key. | ||
| -- | -- | Basement does not appear finished 9/25 | flooring 12/1 Kyle should be installing 12/4 or 12/5 | |
| -- | -- | Siding repairs to front | ||
| -- | -- | Pedestal sink not in 11/13 | ||
| -- | -- | Lazy Susan door needs installed 10/26 | ||
| -- | -- | Missing trim in MB and hall bath | ||
| -- | -- | Cabinet hardware | Boxed in corner cabinet | |
| -- | -- | Vanity will arrive on Nov 11 | ||
| -- | -- | CODED LOCKBOX 6060 | ||
| -- | -- | Cover carpet 11/6 | ||
| -- | -- | FINANCING ISSUES - Nov 12 | ||
| -- | -- | Need candlesticks lightbulbs in chandelier | Need all kitchen lightbulbs 11/23 | |
| -- | -- | Install hardware in kitchen and bathrooms. Hardware all in kitchen | Kyle today 12/9 | |
| -- | -- | Pushback and anchor range | Tom | |
| -- | -- | Finish electrical. Install plates | ||
| -- | -- | Lights over vanities and sconce lights to be installed | Sconces in 12/1 | |
| -- | -- | Stain handrail | ||
| -- | -- | Adjust closet doors | Upstairs bedroom closet doors | |
| -- | -- | Finish installing shelving | ||
| -- | -- | Plumbing trim out toilets faucets | All plumbing complete except basement vanity 12/4 | |
| -- | -- | Trim bottom of master bathroom door | JB | |
| -- | -- | Shoe needed bottom of master bathroom vanity | ||
| -- | -- | Paint touch up throughout | ||
| -- | -- | Caulk pedestal sink toilets and in front of tubs | ||
| -- | -- | BASEMENT need to be FINISHED | ||
| -- | -- | Stair railings need installed 11/13 | Basement not in 12/1 | |
| -- | -- | |||
| -- | -- | Trim needed around cabinetry 11/16 | ||
| -- | -- | |||
| -- | -- | Needs gutters extended 11/20 | ||
| -- | -- | Needs cabinet trim 11/20 | ||
| -- | -- | Nasty scrape kitchen cabinet door 11/23 | One door has been replaced. Scratched door has not. | |
| -- | -- | Basement vanity needed 11/23 | In bonus room 12/1 | |
| -- | -- | Cabinet trim needed kitchen and baths 11/23 | ||
| -- | -- | |||
| -- | -- | Fill nail holes at handrail stairs | ||
| -- | -- | Holes in master bedroom wall to be filled painted | ||
| -- | -- | Basement being painted 11/25 | ||
| -- | -- | |||
| -- | -- | Back door plugs 12/1 | ||
| -- | -- | Outlet cover needed hall closet main level 12/1 | ||
| -- | -- | Bath fans needed 12/1 | ||
| -- | -- | Outdoor pipes being left on top of ground? 12/1 | ||
| -- | -- | Home Inspection, Dec 13 at 1PM | Benjamin Meredith | |
| -- | -- | Few screens need installed 12/4 | JB | |
| -- | -- | Install kitchen shelves in cabinets 12/4 | Kyle, About half are done. 12/6 | |
| -- | -- | Touch up paint needed throughout 12/4 | ||
| -- | -- | Porch light needed 12/4 | ||
| -- | -- | Touch up front door 12/7 | Isaac | |
| -- | -- | MB vanity drawer broken? 12/7 | Kyle | |
| -- | -- | |||
| -- | -- | |||
| -- | -- | |||
| -- | -- | Missing access panel near breaker | Electrician | |
| -- | -- | Paint touch up basement stair well | ||
| -- | -- | Crack on side of basement light fixture | Still there after touch up 12/17 | |
| -- | -- | Cabinet issues 12/11 see pics | ||
| -- | -- | Caulking around exterior basement light | JB | |
| -- | -- | Install replacement cabinet door on island | ||
| -- | -- | Lightbulb in fan. Main floor | ||
| -- | -- | Scratch above master bedroom fan | ??? | |
| -- | -- | Paint touch up | Here now 12/16 | |
| -- | -- | Final Clean | Kelly on site 12/18 | |
| -- | -- | Need a price for a radon mitigation system | Buyer to decide whether to pay to have it installed | |
| -- | -- | Noted the rear gutter downspouts are not attached properly and the extension pipes are corrugated (not intended for this purpose); recommend having the rear gutter downspout and extensions repaired to reduce water intrusion at the foundation | In process 12/28 | |
| -- | -- | The master bathroom door does not latch when closed; recommend adjusting the door. | JB - Screws loose. Just need to be tightened | |
| -- | -- | Noted the kitchen drawer to the left of the oven does not close as intended; recommend repair | Greg | |
| -- | -- | Noted chipped fiberglass at the basement bathroom shower; recommend repair. | fixing 4/3 | |
| -- | -- | Noted a missing screw at the main electric panel and a missing cover at the data panel in the basement; recommend installing the missing components | Electrician/screw has been installed 12/18 | |
| -- | -- | Noted a hump in the floor on the 1st floor indicating a raised structural component; recommend monitoring over time. | Reinstalling floor 12/28 | |
| -- | -- | Recommend extending gutter downspouts out farther than the concrete splash blocks extend at the front of the house to reduce water intrusion at the foundation | JB | |
| -- | -- | Noted no evidence of flashing where the rear deck intersects the house; recommend enquiring as to the flashing technique. | Tom | |
| -- | -- | Recommend installing anti-tilt bracket at the oven/range as a small child safety precaution. | JB | |
| -- | -- | Needs touch up paint 12/18 | ||
| -- | -- | CONTACT PROPERTY MANAGER (APRIL) @ 540-607-1068 | ||
| -- | -- | |||
| -- | -- | Paint peeling on door? | ||
| -- | -- | Cabinet door not shutting right? | MB drawer | |
| -- | -- | Fan light in Master bath not working | Patrick Graves | |
| -- | -- | Paint chipping on door and back fence | Issac or Mahar | |
| -- | -- | Building Permit (30) * | ||
| Amana Stainless Steel Appliances | ||||
| Maste Upgraded Cabinetry | ||||
| Contract Amendment | ||||
| Increased list price | ||||
| -- | -- | Order Roof & Floor Trusses (1) | ||
| -- | -- | Order Windows & Doors (0) | ||
| -- | -- | Stake Out Home (1) | ||
| -- | -- | Excavate (2) | ||
| -- | -- | Inspection (Footers) (1) | ||
| -- | -- | Pour Footers (1) * | ||
| -- | -- | Set Forms (2) | ||
| -- | -- | Pour Foundation Walls (1) | ||
| -- | -- | Plumb Slab (2) | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) | ||
| -- | -- | Prepare Slab (1) | ||
| -- | -- | Inspection (Slab) (1) | ||
| -- | -- | Pour Slab (1) * | ||
| -- | -- | Framing I (9) | ||
| Fully Finished Basement with full bathroom | ||||
| -- | -- | Order Steps (0) | ||
| -- | -- | Order Tubs / Showers (0) | ||
| -- | -- | Framing II (8) | ||
| -- | -- | Framing III (8) * | ||
| -- | -- | Install Stairs (0) * | ||
| -- | -- | Windows & Doors (0) * | ||
| -- | -- | House Number and Status in Window (0) | ||
| -- | -- | Roofing (0) * | ||
| -- | -- | Order Cabinets (0) | ||
| -- | -- | Order Appliances (0) | ||
| -- | -- | Deck (0) | ||
| -- | -- | Gutters (0) | ||
| -- | -- | Driveway (0) * | ||
| -- | -- | Privacy Divider / Fence (0) * | ||
| -- | -- | Sod / Seed / Landscaping (0) | ||
| -- | -- | HVAC Rough In (4) | ||
| -- | -- | Plumbing Rough In (4) | ||
| -- | -- | Electric Rough In (4) | In process 8/21 | |
| -- | -- | Inspection (Rough In HVAC) (1) | ||
| -- | -- | Exterior Vinyl (0) * | In process 9/18 | |
| -- | -- | Insulation (2) * | ||
| -- | -- | Inspection (Insulation) (1) | Aug 29 | |
| -- | -- | Inspection (Electric Service) (0) | ||
| -- | -- | Inspection (Main Sewer Line) (0) | ||
| -- | -- | Order Interior Doors & Trim (0) | ||
| -- | -- | Drywall (Hang) (4) * | ||
| -- | -- | Drywall (Tape, Block, Skim, Sand) (6) * | Sanding 9/18 | |
| -- | -- | Paint 1 (1) | Ready as of Sep 23 | |
| -- | -- | Garage Door (0) | ||
| -- | -- | House Numbers (0) | ||
| -- | -- | Cabinet Installation (2) * | On site. 9/28 | |
| -- | -- | Granite Installation (1) * | Oct 24 | |
| -- | -- | Interior Trim - Install (3) * | On site 9/28 | |
| -- | -- | Order Plumbing / Lighting Fixtures (0) | ||
| -- | -- | Luxury Vinyl Plank (3) * | ||
| LVP main Level | ||||
| -- | -- | Luxury Vinyl Tile (0) | Underpayment down 9/28 | |
| -- | -- | Paint 2 (3) | ||
| -- | -- | Cover Floors (1) | ||
| -- | -- | Deliver Plumbing / Lighting Fixtures (0) | ||
| -- | -- | Shoe Moulding (0) | ||
| -- | -- | Shelving, Door Knobs, Fire Extinguisher (0) * | In process 11/20. Still needs shelving in one bedroom installed. | |
| -- | -- | Install Coded Lockbox (add extra keys) (0) | ||
| -- | -- | Pay Water / Sewer Taps (0) | ||
| -- | -- | Set Water Meter (0) * | ||
| -- | -- | Electric Trim Out (3) * | Basement Fixtures needed | |
| -- | -- | HVAC Trim Out (1) * | ||
| -- | -- | Plumbing Trim Out (2) * | Mostly complete except basement vanity 11/23 | |
| -- | -- | Install Appliances (0) * | Monday 11/4 | |
| -- | -- | Paint 3 (2) * | ||
| -- | -- | Carpet (2) | ||
| -- | -- | Appraiser Confirms Construction Completion (0) | ||
| -- | -- | Inspection (Final Building) (2) * | Passed except grade of backyard | |
| -- | -- | Pre Walk Through (0) | ||
| -- | -- | Cleaning (1) | Kelly on site 12/11 | |
| -- | -- | Certificate of Occupancy (1) * | ||
| -- | -- | C.O. to Lender (0) | ||
| -- | -- | Schedule Closing (0) | Mon, Dec 30 at 9AM at West View Title | |
| -- | -- | Buyer Walk Through (1) * | Wednesday at 1:00 PM | |
| -- | -- | Payment for Upgrades (0) | ||
| -- | -- | Keys to Settlement Agent (0) | ||
| -- | -- | Review Settlement Statement (0) | ||
| -- | -- | Jerry Signs Closing Documents (0) | ||
| -- | -- | Closing (1) | Mon, Dec 30 at 9AM at West View Title | |
| -- | -- | Remove Coded Lockbox (0) | ||