Fri |
Sep 20 |
Ratified Contract? (0)
|
|
|
Fri |
Sep 20 |
$2500 Deposit Received (0)
|
|
|
Fri |
Sep 20 |
Association Packet Requested (0)
|
|
|
Fri |
Sep 20 |
Association Packet Received (0)
|
|
|
Fri |
Sep 20 |
Selections Meeting (0)
|
|
|
Fri |
Sep 20 |
Selections Sheet Signed (0)
|
|
|
Fri |
Sep 20 |
Amendment for Upgrades (B,S,L,T,BCP) (0)
|
|
|
Fri |
Sep 20 |
Deposit For Upgrades Received (0)
|
|
|
Fri |
Sep 20 |
Inspection (Concrete Wall) (1)
|
|
|
Mon |
Sep 23 |
Inspection (Conduit Under Slab) (1)
|
|
|
Tue |
Sep 24 |
Inspection (Drain Tile) (0)
|
|
|
Tue |
Sep 24 |
Settlement Agent Confirmed (0)
|
|
|
Tue |
Sep 24 |
Verify Window & Roof Structure (0)
|
|
|
Tue |
Sep 24 |
Patio (0)
|
|
|
Tue |
Sep 24 |
Rough In Microwave Vent (0)
|
|
|
Tue |
Sep 24 |
Inspection (Rough In Plumbing) (1)
|
|
|
Wed |
Sep 25 |
Inspection (Rough In Electric) (1)
|
|
|
Thu |
Sep 26 |
Inspection (Deck Piers) (0)
|
|
|
Thu |
Sep 26 |
Inspection (Framing) (1)
|
|
|
Fri |
Sep 27 |
Exterior Stone (0)
|
|
|
Fri |
Sep 27 |
Set Electric Meter (0)
|
|
|
Fri |
Sep 27 |
Inspection (Main Water Line) (0)
|
|
|
Fri |
Sep 27 |
Loan Approval (0)
|
|
|
Fri |
Sep 27 |
Deed Preparation (0)
|
|
|
Fri |
Sep 27 |
Mailbox (0)
|
|
|
Fri |
Sep 27 |
Interior Trim - Paint (1)
|
|
|
Mon |
Sep 30 |
Ceiling Fans (0)
|
|
|
Mon |
Sep 30 |
Blower Door Test (1)
|
|
|
Tue |
Oct 1 |
Inspection (Final HVAC) (1)
|
|
|
Wed |
Oct 2 |
Inspection (Final Plumbing) (1)
|
|
|
Thu |
Oct 3 |
Inspection (Final Electric) (1)
|
|
|
Fri |
Oct 4 |
Stain Hardwood Stairs (1)
|
|
|
Mon |
Oct 7 |
Request Trash Tote From POA Manager (0)
|
|
|
|
-- |
-- |
Savanna brick, country beige vinyl, gold front door |
|
|
-- |
-- |
Missing back sliding door |
|
|
-- |
-- |
Plumbing and electrical for future kitchen in basement |
|
|
-- |
-- |
Need square footage for til |
|
|
-- |
-- |
Need square footage for tile back splash-eliminate 4” splash Fenco |
Backsplash needs removed 11/23 |
|
-- |
-- |
Needs shower in basement 8/10 |
|
|
-- |
-- |
Need to set/plumb basement shower 8/21 |
|
|
-- |
-- |
Remove brick |
|
|
-- |
-- |
Bathtub liner needed 8/28 |
|
|
-- |
-- |
Siding repairs to front |
|
|
-- |
-- |
Lazy susan broken/needs installed |
|
|
-- |
-- |
Window issue? |
Appears fixed 11/3 |
|
-- |
-- |
Cabinet hardware needed |
Kyle over 12/4 -12/5 |
|
-- |
-- |
CODED LOCKBOX 6161 |
|
|
-- |
-- |
|
|
|
-- |
-- |
Needs gutter extended 11/20 |
|
|
-- |
-- |
Needs gutter extended 11/20 |
|
|
-- |
-- |
HVAC covers needed 11/23 |
|
|
-- |
-- |
1/2 bath mirror needed 11/23 |
|
|
-- |
-- |
Need basement bath mirror and fan 11/23 |
|
|
-- |
-- |
Vinyl needed under basement stairs 11/23 |
|
|
-- |
-- |
Up bath needs mirror 11/23 |
And MB |
|
-- |
-- |
Needs shower rods 11/23 |
|
|
-- |
-- |
Needs porch light 11/23 |
|
|
-- |
-- |
Window screens needed |
Tom |
|
-- |
-- |
Doorstop at between powder bath and hall closet door |
JB |
|
-- |
-- |
paint touch up |
1125 through 1127 |
|
-- |
-- |
Living room window adjustment |
Tom looking at today 12/16 |
|
-- |
-- |
Remove cardboards |
Wednesday 11/27 |
|
-- |
-- |
Mirror needed in master bath |
|
|
-- |
-- |
Towel bars in both bathrooms |
|
|
-- |
-- |
Add two cut offs where future basement kitchen will go |
|
|
-- |
-- |
Nail pop upper level in stairwell 12/1 |
|
|
-- |
-- |
Lenoleim under stairs in basement? Not there 12/1 |
|
|
-- |
-- |
Adjust light above island 12/4 |
JB |
|
-- |
-- |
Review Inspection Repairs Request |
|
|
-- |
-- |
Install Seven Missing Cabinet Pulls |
|
|
-- |
-- |
Repair chip in floor in basement next to rear exterior wall |
Eagle |
|
-- |
-- |
Repair chips in floor at threshold at top of stairs |
Eagle |
|
-- |
-- |
Straighten and fasten rear gutter downspout |
JB/appears complete 12/7 |
|
-- |
-- |
Adjust grade to slope away from the house |
Partners |
|
-- |
-- |
Caulk top of flashing at the roof returns on the front of the house |
Joel |
|
-- |
-- |
Install Z flashing where deck meets back of house |
JB |
|
-- |
-- |
Hook up water line to refrigerator |
JB |
|
-- |
-- |
Buyers closed and have the key |
John Sizemore 540-383-7642 |
|
-- |
-- |
John Sizemore 540-383-7642 |
|
|
-- |
-- |
Patch drywall below shower |
|
|
-- |
-- |
Building Permit (30)
|
|
|
-- |
-- |
Order Roof & Floor Trusses (1)
|
|
|
-- |
-- |
Order Windows & Doors (0)
|
|
|
-- |
-- |
Stake Out Home (1)
|
|
|
-- |
-- |
Excavate (2)
|
|
|
-- |
-- |
Inspection (Footers) (1)
|
|
|
-- |
-- |
Pour Footers (1)
|
|
|
-- |
-- |
Set Forms (2)
|
|
|
-- |
-- |
Pour Foundation Walls (1)
|
|
|
-- |
-- |
Plumb Slab (2)
|
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1)
|
|
|
-- |
-- |
Prepare Slab (1)
|
|
|
-- |
-- |
Inspection (Slab) (1)
|
|
|
-- |
-- |
Pour Slab (1)
|
|
|
-- |
-- |
Framing I (9)
|
|
|
-- |
-- |
Order Steps (0)
|
|
|
-- |
-- |
Order Tubs / Showers (0)
|
|
|
-- |
-- |
Framing II (8)
|
|
|
-- |
-- |
Framing III (8)
|
|
|
-- |
-- |
Install Stairs (0)
|
|
|
-- |
-- |
Windows & Doors (0)
|
|
|
-- |
-- |
House Number and Status in Window (0)
|
|
|
-- |
-- |
Roofing (0)
|
|
|
-- |
-- |
Order Cabinets (0)
|
|
|
-- |
-- |
Order Appliances (0)
|
|
|
-- |
-- |
Deck (0)
|
|
|
-- |
-- |
Gutters (0)
|
|
|
-- |
-- |
Driveway (0)
|
Patio done 10/9 |
|
-- |
-- |
Privacy Divider / Fence (0)
|
|
|
-- |
-- |
Sod / Seed / Landscaping (0)
|
|
|
-- |
-- |
HVAC Rough In (4)
|
|
|
-- |
-- |
Inspection (Rough In HVAC) (1)
|
Tue, Sep 3 |
|
-- |
-- |
Plumbing Rough In (4)
|
Include basement kitchen area- Tom to mark |
|
-- |
-- |
Electric Rough In (4)
|
8/28 90% done |
|
-- |
-- |
Exterior Vinyl (0)
|
In process 9/18 |
|
-- |
-- |
Insulation (2)
|
Wed, Sep 4 |
|
-- |
-- |
Inspection (Insulation) (1)
|
Sep 9 |
|
-- |
-- |
Inspection (Electric Service) (0)
|
|
|
-- |
-- |
Inspection (Main Sewer Line) (0)
|
|
|
-- |
-- |
Order Interior Doors & Trim (0)
|
|
|
-- |
-- |
Drywall (Hang) (4)
|
Started 9/11 |
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6)
|
Will be done 10/9 |
|
-- |
-- |
Paint 1 (1)
|
Thu, Oct 10 |
|
-- |
-- |
Garage Door (0)
|
|
|
-- |
-- |
House Numbers (0)
|
|
|
-- |
-- |
Cabinet Installation (2)
|
Oct 22 installation |
|
-- |
-- |
Granite Installation (1)
|
|
|
-- |
-- |
Interior Trim - Install (3)
|
Doors hung/working on trim 10/19 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0)
|
|
|
-- |
-- |
Luxury Vinyl Plank (3)
|
|
|
-- |
-- |
Luxury Vinyl Tile (0)
|
On site 10/12 |
|
-- |
-- |
Paint 2 (3)
|
In process 11/16 |
|
-- |
-- |
Cover Floors (1)
|
Wednesday 11/13 |
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0)
|
|
|
-- |
-- |
Shoe Moulding (0)
|
Wednesday 11/13-on site and started 11/13 |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0)
|
Almost complete 11/23. Needs shelving in pantry. Ron to install mirrors finish shelving and missing door knobs 11/26 or 11/27 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0)
|
|
|
-- |
-- |
Pay Water / Sewer Taps (0)
|
11/13 |
|
-- |
-- |
Set Water Meter (0)
|
|
|
-- |
-- |
Electric Trim Out (3)
|
Done except bathrooms/basement 10/26 |
|
-- |
-- |
HVAC Trim Out (1)
|
|
|
-- |
-- |
Plumbing Trim Out (2)
|
In process 11/20 |
|
-- |
-- |
Install Appliances (0)
|
Wed, Nov 20 |
|
-- |
-- |
Paint 3 (2)
|
Friday 11/22 |
|
-- |
-- |
Carpet (2)
|
In process 11/20 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0)
|
|
|
-- |
-- |
Inspection (Final Building) (2)
|
Mon, Nov 25 |
|
-- |
-- |
Pre Walk Through (0)
|
Little too early. Will do end of next week |
|
-- |
-- |
Cleaning (1)
|
Floors on Sunday, Dec 1- Kelly on site 12/1 |
|
-- |
-- |
Certificate of Occupancy (1)
|
|
|
-- |
-- |
C.O. to Lender (0)
|
|
|
-- |
-- |
Schedule Closing (0)
|
Main Street Title Group |
|
-- |
-- |
Buyer Walk Through (1)
|
Tuesday, Nov 26 |
|
-- |
-- |
Payment for Upgrades (0)
|
|
|
-- |
-- |
Keys to Settlement Agent (0)
|
|
|
-- |
-- |
Review Settlement Statement (0)
|
|
|
-- |
-- |
Jerry Signs Closing Documents (0)
|
|
|
-- |
-- |
Closing (1)
|
Main Street Title Group |
|
-- |
-- |
Remove Coded Lockbox (0)
|
|
|