- 69  ::  2223 Deyerle Avenue
[ BUILD: 1904-0097 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Fri    Sep 20      Ratified Contract? (0)      
Fri    Sep 20      $2500 Deposit Received (0)      
Fri    Sep 20      Association Packet Requested (0)      
Fri    Sep 20      Association Packet Received (0)      
Fri    Sep 20      Selections Meeting (0)      
Fri    Sep 20      Selections Sheet Signed (0)      
Fri    Sep 20      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Fri    Sep 20      Deposit For Upgrades Received (0)      
Fri    Sep 20      Inspection (Concrete Wall) (1)      
Mon    Sep 23      Inspection (Conduit Under Slab) (1)      
Tue    Sep 24      Inspection (Drain Tile) (0)      
Tue    Sep 24      Settlement Agent Confirmed (0)      
Tue    Sep 24      Verify Window & Roof Structure (0)      
Tue    Sep 24      Patio (0)      
Tue    Sep 24      Rough In Microwave Vent (0)      
Tue    Sep 24      Inspection (Rough In Plumbing) (1)      
Wed    Sep 25      Inspection (Rough In Electric) (1)      
Thu    Sep 26      Inspection (Deck Piers) (0)      
Thu    Sep 26      Inspection (Framing) (1)      
Fri    Sep 27      Exterior Stone (0)      
Fri    Sep 27      Set Electric Meter (0)      
Fri    Sep 27      Inspection (Main Water Line) (0)      
Fri    Sep 27      Loan Approval (0)      
Fri    Sep 27      Deed Preparation (0)      
Fri    Sep 27      Mailbox (0)      
Fri    Sep 27      Interior Trim - Paint (1)      
Mon    Sep 30      Ceiling Fans (0)      
Mon    Sep 30      Blower Door Test (1)      
Tue    Oct 1      Inspection (Final HVAC) (1)      
Wed    Oct 2      Inspection (Final Plumbing) (1)      
Thu    Oct 3      Inspection (Final Electric) (1)      
Fri    Oct 4      Stain Hardwood Stairs (1)      
Mon    Oct 7      Request Trash Tote From POA Manager (0)      
--   --   BRICK Carters Grove, VINYL- Ivory DOOR COLOR green
--   --   Very bumpy/irregular basement floor. Issue?
--   --   Back slider door frame cracked 11/13 At threshold
--   --   Kitchen backsplash just needs grout 2/15
--   --   Drywall repairs to MB 12/18 Still needs sanding 1/15
--   --   MB tile ok? Specs say 12x12
--   --   Missing brick below front window 1/5 Talk to Masons they said they would take care of it. 1/6
--   --   Yes to tile back splash in white subway tile Just needs grout 2/15
--   --   Cover kitchen floor 1/22
--   --   CODED LOCKBOX-6969
--   --   Fire extinguisher 2/1
--   --   Need kitchen & vanity hardware 2/12 Picked up and on site 2/13 GWB
--   --   Few touch ups laundry room 2/12 Mahar touch up 2/17
--   --   Needs MB mirror 2/15 Move towel ring?
--   --   Final HVAC trim out 2/15
--   --   Screens
--   --   Caulk Toilet on mainlevel
--   --   adjust doors in the upstairs closets JB
--   --   Mirror in master bath
--   --   Remove/patch hole MB mirror 2/23 Painter
--   --   Back door hole plugs 2/23 JB
--   --   Screens Just need back slider 2/26
--   --   Kitchen cabinet HVAC vent 2/26 Greg will call Clem or Ronnie
--   --   Clean out basement 2/26
--   --   Remove floor covering
--   --   Shoe mold on front and back doors On site 3/4
--   --   Replace siding on roof of back porch
--   --   Final clean
--   --   Cracked trim above kitchen sink
--   --   Sweep and mop basement Needs one more sweep
--   --   Sweep and mop basement
--   --   Paint edges of cabinets 2/29
--   --   Mulch needed 2/29
--   --   Cracks in MB vanity 2/29 (JB) On order
--   --   Screens needed in basement 2/29
--   --   Mulch needed 2/29
--   --   Quite a few missing lightbulbs 3/4 Painter
--   --   Countertops replaced-need patch/paint 3/4 Painter
--   --   Electric box cover 3/4
--   --   Over spray I master bath Painter
--   --   Cabinet drawer issue?
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1)      
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8)      
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)       Back slider needs installed 11/6
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)       Started 11/13
-- -- Gutters (0)      
-- -- Driveway (0)      
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)       Tom will call Pettit
-- -- HVAC Rough In (4)       Started 10/26
-- -- Inspection (Rough In HVAC) (1)       Nov 14
-- -- Plumbing Rough In (4)       Started 10/30
-- -- Electric Rough In (4)       In process 11/9
-- -- Exterior Vinyl (0)       In process 1/11
-- -- Insulation (2)       Tue, Nov 19
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4)       On site 11/23
-- -- Drywall (Tape, Block, Skim, Sand) (6)      
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2)       Abi installing 1/11
-- -- Granite Installation (1)       feb 6
-- -- Interior Trim - Install (3)      
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3)       Installing kitchen 1/15
-- -- Luxury Vinyl Tile (0)       Going in 12/18
-- -- Paint 2 (3)       In process 1/15
-- -- Cover Floors (1)       Cover newly laid floor in kitchen 1/19
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       In process 1/29
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0)       Box set but not meter 2/25
-- -- Electric Trim Out (3)       Need vanity lights 2/12
-- -- HVAC Trim Out (1)       Furnace set 1/15
-- -- Plumbing Trim Out (2)       95% complete 2/8- just need kitchen sink faucet
-- -- Install Appliances (0)       Set for Thurs 2/20 GWB
-- -- Paint 3 (2)       In process 2/4
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)       Teri Robinson, Vision Appraisal going March 6
-- -- Inspection (Final Building) (2)       After water meter
-- -- Pre Walk Through (0)       Done by Greg and Tom 2/19
-- -- Cleaning (1)       Cleaning started 2/22
-- -- Certificate of Occupancy (1)      
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1)       Fri, Feb 28, 3:00 PM
-- -- Payment for Upgrades (0)       $2,270
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)       West View Title (Sara)
-- -- Closing (1)       Friday, March 13 at 9:00 AM
-- -- Remove Coded Lockbox (0)