- 71  ::  2219 Deyerle Avenue
[ BUILD: 1904-0095 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Apr 29      Ratified Contract? (0)      
Tue    Apr 29      $2500 Deposit Received (0)      
Tue    Apr 29      Association Packet Requested (0)      
Tue    Apr 29      Association Packet Received (0)      
Tue    Apr 29      Selections Meeting (0)      
Tue    Apr 29      Selections Sheet Signed (0)      
Tue    Apr 29      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Apr 29      Deposit For Upgrades Received (0)      
Tue    Apr 29      Inspection (Concrete Wall) (1)      
Wed    Apr 30      Inspection (Conduit Under Slab) (1)      
Thu    May 1      Inspection (Drain Tile) (0)      
Thu    May 1      Settlement Agent Confirmed (0)      
Thu    May 1      Verify Window & Roof Structure (0)      
Thu    May 1      Patio (0)      
Thu    May 1      Rough In Microwave Vent (0)      
Thu    May 1      Inspection (Rough In Plumbing) (1)      
Fri    May 2      Inspection (Rough In Electric) (1)      
Mon    May 5      Inspection (Deck Piers) (0)      
Mon    May 5      Inspection (Framing) (1) *       
Tue    May 6      Exterior Stone (0)      
Tue    May 6      Set Electric Meter (0) *       
Tue    May 6      Inspection (Main Water Line) (0)      
Tue    May 6      Loan Approval (0)      
Tue    May 6      Deed Preparation (0)      
Tue    May 6      Mailbox (0)      
Tue    May 6      Interior Trim - Paint (1)      
Wed    May 7      Ceiling Fans (0)      
Wed    May 7      Blower Door Test (1)      
Thu    May 8      Inspection (Final HVAC) (1)      
Fri    May 9      Inspection (Final Plumbing) (1)      
Mon    May 12      Inspection (Final Electric) (1)      
Tue    May 13      Stain Hardwood Stairs (1)      
--   --   Closet by front door for taking shoes off?
--   --   Small show closet located off front door- to be determined at a framing walk through- When should this be scheduled TOM?
--   --   Small shoe closet to be built by front door for shoes. Culturally important. Perhaps a small ceramic entry as well. DO be determined at buyer walk thorugh. TOM WHEN CAN WE SCHEDULE? TOM tell Kate
--   --   Buyer Requesting price for steps from deck to yard. Tom tell Kate
--   --   BRICK Charleston, VINYL- Bone DOOR COLOR red
--   --   Lots of mildew on LR walls Tom will address
--   --   FINANCING ISSUES - Nov 12
--   --   Under contract sticker (court)
--   --   Bathtub liners needed 11/23
--   --   Set tub in basement 12/1
--   --  
--   --   Repair basement bath wall 12/15
--   --   DISCUSS - Lease ends January 31
--   --   Add stud to laundry room for washer/dryer hookup
--   --   Gold Door Color
--   --   Missing trim in MB 2/1
--   --   Missing trim basement bath
--   --   Locked out 2/8 Keys???
--   --   CODED LOCKBOX 7171
--   --   Missing trim kitchen also 2/12
--   --   Board in upper window/remove 2/15
--   --   Vanity hardware needed 2/15 On site and should be installed today 3/12
--   --   Hump in floor Floor pulled up and prepared to sand 2/27
--   --   Cut sewer pipe down
--   --   Trim cabinets 2/19
--   --   Very squeaky steps to upper level. 2/19
--   --   Vanity lights 2/26
--   --   Mulch needed 2/29
--   --   Replace shoe molding in areas its been pulled up 2/29 In progress 3/8
--   --   Finish shelving 2/29
--   --   Mirrors needed 2/29
--   --  
--   --   Trim on shoe cabinet needed 3/4
--   --   Poly staircase 3/8 Finishing now 3/12
--   --   Landing needs flooring installed 3/8 Eric
--   --   Panel to water shut off needed 3/11 JB- needs painted 3/14
--   --   Knobs for shoe cabinet ordered? On site and should be installed today 3/12
--   --  
--   --   Install 7 missing window screens Checking with JB and Tom
--   --   Touch up paint Just a few spots left 3/14
--   --   Final cleaning almost complete 3/14
--   --   Replace kitchen faucet onsite. Bobby will install Monday morning 3/23
--   --   Touch up front door 3/14
--   --   Basement hall lights 3/14 make same direction
--   --   Door touch up needed 3/25 Lock is fixed-needs paint touch-up3/29
--   --   Financing issues - closing is delayed
--   --   Home Inspection, May 21 at 9AM Mike Donitzen
--   --   Expanded deck 12 x 18
--   --   Expanded Patio In process 5/13
--   --   Radon test Mon May 18 - Thu May 21
--   --   Remove gravel and leave back yard Fill dirt on site. Set to finish this week
--   --   HVAC is not working properly cuts on and off and does not get hot enough (on a cold day)
--   --   Doorbell broken 5/25
--   --   Adjust Electrical Panel Patrick to go over while Kumud is home
--   --   Adjust screw sticking out JB
--   --   Creaky floors (8/24) Greg will follow up with Eric
--   --   Replace siding in rear under deck John weeks
--   --   Bathroom and bedroom door handle wont lock Ron to call Kumud 9/23 to schedule GWB
--   --   Creeks in floor upstairs John Weeks
--   --   Kumud contact 202-425-9888
--   --   Hump in floor Eric to handle 1/20 GWB
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0) *        Back slider needs installing 11/6
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)       In process 11/13
-- -- Gutters (0)      
-- -- Driveway (0) *        set to poor stoop Tuesday 2/18. Set to start poor sidewalk 2/14 Patio done 1/29
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       Started 10/26
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)       Almost complete 11/23. Basement tub needs set
-- -- Electric Rough In (4)       In process 12/11
-- -- Exterior Vinyl (0) *        In process
-- -- Insulation (2) *        Tues, Dec 17
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        In process 1/1
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process of taping/mudding 1/15
-- -- Paint 1 (1)      
-- -- Garage Door (0) *       
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Installing 2/1
-- -- Granite Installation (1) *        Set date for 2/25 GWB
-- -- Interior Trim - Install (3) *        In process 1/29
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *        Week of Feb 10
-- -- Luxury Vinyl Tile (0)       Starting Jan 23
-- -- Paint 2 (3)      
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)       Looks like plumbing fixtures are here GWB missing bathroom fixtures and basement 2/14
-- -- Shoe Moulding (0)       Down in flooring that hasn’t been pulled up 2/29
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        In process 2/14 GWB most shelves and handles done
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3)       All but vanity lights 2/23
-- -- HVAC Trim Out (1)       Furnace set 1/19
-- -- Plumbing Trim Out (2)      
-- -- Install Appliances (0) *        Thursday March 5- appliances are now SS as Black is on back order through end of March- buyer approved
-- -- Paint 3 (2) *        Happening now 2/27
-- -- Carpet (2)       Going in 2/26
-- -- Appraiser Confirms Construction Completion (0)       Dawn Showalter, March 16
-- -- Inspection (Final Building) (2) *        Maybe afternoon of March 5
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       in process 5/28
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)       Friday, May 29
-- -- Buyer Walk Through (1)      
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Request Trash Tote From POA Manager (0)      
-- -- Closing (1)      
-- -- Remove Coded Lockbox (0)       Grab on Wednesday