ADDR
- 74  ::  2213 Deyerle Avenue
[ BUILD: 1904-0092 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Shannon Weaver 540-435-1654
Fri    Sep 20      Ratified Contract? (0)      
Fri    Sep 20      $2500 Deposit Received (0)      
Fri    Sep 20      Association Packet Requested (0)      
Fri    Sep 20      Association Packet Received (0)      
Fri    Sep 20      Selections Meeting (0)      
Fri    Sep 20      Selections Sheet Signed (0)      
Fri    Sep 20      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Fri    Sep 20      Deposit For Upgrades Received (0)      
Fri    Sep 20      Inspection (Concrete Wall) (1)      
Mon    Sep 23      Inspection (Conduit Under Slab) (1)      
Tue    Sep 24      Inspection (Drain Tile) (0)      
Tue    Sep 24      Settlement Agent Confirmed (0)      
Tue    Sep 24      Verify Window & Roof Structure (0)      
Tue    Sep 24      Patio (0)      
Tue    Sep 24      Rough In Microwave Vent (0)      
Tue    Sep 24      Inspection (Rough In Plumbing) (1)      
Wed    Sep 25      Inspection (Rough In Electric) (1)      
Thu    Sep 26      Inspection (Deck Piers) (0)      
Thu    Sep 26      Inspection (Framing) (1)      
Fri    Sep 27      Exterior Stone (0)      
Fri    Sep 27      Set Electric Meter (0)      
Fri    Sep 27      Inspection (Main Water Line) (0)      
Fri    Sep 27      Loan Approval (0)      
Fri    Sep 27      Deed Preparation (0)      
Fri    Sep 27      Mailbox (0)      
Fri    Sep 27      Interior Trim - Paint (1)      
Mon    Sep 30      Ceiling Fans (0)      
Mon    Sep 30      Blower Door Test (1)      
Tue    Oct 1      Inspection (Final HVAC) (1)      
Wed    Oct 2      Inspection (Final Plumbing) (1)      
Thu    Oct 3      Inspection (Final Electric) (1)      
Fri    Oct 4      Stain Hardwood Stairs (1)      
Mon    Oct 7      Request Trash Tote From POA Manager (0)      
--   --   Brick-charleston VInyl Ivory Door Color- green
--   --   Two windows missing in basement 11/23
--   --   Two windows missing in basement 11/23
--   --  
--   --   Additional cable drop not found 12/28
--   --   Stud needed in laundry room 1/5 Tom
--   --   Exposed pipe bonus room 1/29
--   --   Fix siding 2/29 JB to fix 3/26
--   --   Mulch needed 2/29
--   --   New globe light in kitchen 2/29
--   --   Extra cabinet in LR 2/29 Still there 3/8
--   --  
--   --   Hump in floor
--   --   Vinyl repair above porch needed 3/8
--   --   Replace fans as noted below 3/8 On site 3/14-2 installed
--   --   CODED LOCKBOX 7474
--   --   CODED LOCKBOX 7474
--   --  
--   --   All ceramic is 12x24 and no extra charge that I see 3/11 Basement is 12x12 (see specs)
--   --   Peep hole 3/11
--   --   Kate - is ceramic installed correctly? installed sizes are different than selection sheet - extra cost?
--   --   Attic cover JB
--   --   Install railings Issac to be done this week 3/24ish
--   --   Install switches for new fans 3/14
--   --   Missing upper level tub fixtures 3/22
--   --   MB Mirror needed (in LR) 3/22 Needs to be installed - Ron
--   --   Water valve cover 3/25 JB working on it today 4/1
--   --   Few tweaks in shelving 3/25 Ron
--   --   Refrigerator handles needed 3/29
--   --   Microwave installed 3/29
--   --   Needs cleaning 4/1
--   --   Screens needed 4/1 Checking with JB and Tom
--   --   Chip in marble counter basement bath 4/1
--   --  
--   --   Patch hole behind sink in half bath John weeks
--   --  
--   --  
--   --   Replace siding in front John Weeks
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1)      
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8)      
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)      
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)       In process 11/16
-- -- Gutters (0)      
-- -- Driveway (0)       set to poor stoop Thurs 2/20 Set to start poor sidewalk 2/17 Patio done 1/29
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       Tue
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
-- -- Exterior Vinyl (0)       in process 1/5
-- -- Insulation (2)       Wed, Jan 15
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4)       In process 1/26
-- -- Drywall (Tape, Block, Skim, Sand) (6)      
-- -- Paint 1 (1)       Today 2/20
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2)       Set to deliver 2/25 Abi will install 2/28
-- -- Granite Installation (1)       3/12
-- -- Interior Trim - Install (3)       In process 2/26
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3)       Started today 3/11
-- -- Luxury Vinyl Tile (0)       Tom will tell Eric we are ready for it (2/27)-on site 3/4
-- -- Paint 2 (3)       In process 3/4
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)       Kate submitted to be ordered on 3/2
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       Few mirrors needed 3/18
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0)       Water check up 3/19
-- -- Electric Trim Out (3)       Basement needs trim out/vanity lights needed everywhere 3/18
-- -- HVAC Trim Out (1)       Trim out needed 3/14
-- -- Plumbing Trim Out (2)       In process 3/14
-- -- Install Appliances (0)       Thursday, March 26
-- -- Paint 3 (2)       In process 3/25
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2)       Friday, March 27
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       In process
-- -- Certificate of Occupancy (1)      
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1)       Thursday, April 2 at 6PM
-- -- Payment for Upgrades (0)       $15,595
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)       Bankers Title, Susan Miller
-- -- Closing (1)       Friday, April 3rd
-- -- Remove Coded Lockbox (0)