- 74  ::  2213 Deyerle Avenue
[ BUILD: 1904-0092 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Shannon Weaver 540-435-1654
Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Inspection (Concrete Wall) (1)      
Wed    Dec 17      Inspection (Conduit Under Slab) (1)      
Thu    Dec 18      Inspection (Drain Tile) (0)      
Thu    Dec 18      Settlement Agent Confirmed (0)      
Thu    Dec 18      Verify Window & Roof Structure (0)      
Thu    Dec 18      Patio (0)      
Thu    Dec 18      Rough In Microwave Vent (0)      
Thu    Dec 18      Inspection (Rough In Plumbing) (1)      
Fri    Dec 19      Inspection (Rough In Electric) (1)      
Mon    Dec 22      Inspection (Framing) (1) *       
Tue    Dec 23      Inspection (Deck Piers) (0)      
Tue    Dec 23      Exterior Stone (0)      
Tue    Dec 23      Set Electric Meter (0) *       
Tue    Dec 23      Inspection (Main Water Line) (0)      
Tue    Dec 23      Loan Approval (0)      
Tue    Dec 23      Deed Preparation (0)      
Tue    Dec 23      Mailbox (0)      
Tue    Dec 23      Interior Trim - Paint (1)      
Wed    Dec 24      Ceiling Fans (0)      
Wed    Dec 24      Blower Door Test (1)      
Thu    Dec 25      Inspection (Final HVAC) (1)      
Fri    Dec 26      Inspection (Final Plumbing) (1)      
Mon    Dec 29      Inspection (Final Electric) (1)      
Tue    Dec 30      Stain Hardwood Stairs (1) *       
Wed    Dec 31      Request Trash Tote From POA Manager (0)      
--   --   Brick-charleston VInyl Ivory Door Color- green
--   --   Two windows missing in basement 11/23
--   --   Two windows missing in basement 11/23
--   --  
--   --   Additional cable drop not found 12/28
--   --   Stud needed in laundry room 1/5 Tom
--   --   Exposed pipe bonus room 1/29
--   --   Fix siding 2/29 JB to fix 3/26
--   --   Mulch needed 2/29
--   --   New globe light in kitchen 2/29
--   --   Extra cabinet in LR 2/29 Still there 3/8
--   --  
--   --   Hump in floor
--   --   Vinyl repair above porch needed 3/8
--   --   Replace fans as noted below 3/8 On site 3/14-2 installed
--   --   CODED LOCKBOX 7474
--   --   CODED LOCKBOX 7474
--   --  
--   --   All ceramic is 12x24 and no extra charge that I see 3/11 Basement is 12x12 (see specs)
--   --   Peep hole 3/11
--   --   Kate - is ceramic installed correctly? installed sizes are different than selection sheet - extra cost?
--   --   Attic cover JB
--   --   Install railings Issac to be done this week 3/24ish
--   --   Install switches for new fans 3/14
--   --   Missing upper level tub fixtures 3/22
--   --   MB Mirror needed (in LR) 3/22 Needs to be installed - Ron
--   --   Water valve cover 3/25 JB working on it today 4/1
--   --   Few tweaks in shelving 3/25 Ron
--   --   Refrigerator handles needed 3/29
--   --   Microwave installed 3/29
--   --   Needs cleaning 4/1
--   --   Screens needed 4/1 Checking with JB and Tom
--   --   Chip in marble counter basement bath 4/1
--   --  
--   --   Patch hole behind sink in half bath John weeks
--   --  
--   --  
--   --   Replace siding in front John Weeks
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
    Fully Completed Basement with Full Bathroom  
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)       In process 11/16
-- -- Gutters (0)      
-- -- Driveway (0) *        set to poor stoop Thurs 2/20 Set to start poor sidewalk 2/17 Patio done 1/29
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
    Additional Cable drop in Basement( two largest walls opposite e/o)  
-- -- Inspection (Rough In HVAC) (1)       Tue
-- -- Exterior Vinyl (0) *        in process 1/5
-- -- Insulation (2) *        Wed, Jan 15
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        In process 1/26
-- -- Drywall (Tape, Block, Skim, Sand) (6) *       
-- -- Paint 1 (1)       Today 2/20
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Set to deliver 2/25 Abi will install 2/28
-- -- Granite Installation (1) *        3/12
-- -- Interior Trim - Install (3) *        In process 2/26
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *        Started today 3/11
    Upgrade to Luxury Vinyl Plank Main Level  
-- -- Luxury Vinyl Tile (0)       Tom will tell Eric we are ready for it (2/27)-on site 3/4
-- -- Paint 2 (3)       In process 3/4
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)       Kate submitted to be ordered on 3/2
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        Few mirrors needed 3/18
    Peep Hole in front door  
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *        Water check up 3/19
-- -- Electric Trim Out (3) *        Basement needs trim out/vanity lights needed everywhere 3/18
    3 added ceiling fans ( larger up BR, Basement FR and Bonus Rm)  
-- -- HVAC Trim Out (1) *        Trim out needed 3/14
-- -- Plumbing Trim Out (2) *        In process 3/14
-- -- Install Appliances (0) *        Thursday, March 26
-- -- Paint 3 (2) *        In process 3/25
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Friday, March 27
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       In process
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1) *        Thursday, April 2 at 6PM
-- -- Payment for Upgrades (0)       $15,595
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)       Bankers Title, Susan Miller
-- -- Closing (1)       Friday, April 3rd
-- -- Remove Coded Lockbox (0)