-- |
-- |
Shannon Weaver 540-435-1654 |
|
|
Thu |
Nov 28 |
Ratified Contract? (0) |
|
|
Thu |
Nov 28 |
$2500 Deposit Received (0) |
|
|
Thu |
Nov 28 |
Association Packet Requested (0) |
|
|
Thu |
Nov 28 |
Association Packet Received (0) |
|
|
Thu |
Nov 28 |
Selections Meeting (0) |
|
|
Thu |
Nov 28 |
Selections Sheet Signed (0) |
|
|
Thu |
Nov 28 |
Amendment for Upgrades (B,S,L,T,BCP) (0) |
|
|
Thu |
Nov 28 |
Deposit For Upgrades Received (0) |
|
|
Thu |
Nov 28 |
Inspection (Concrete Wall) (1) |
|
|
Fri |
Nov 29 |
Inspection (Conduit Under Slab) (1) |
|
|
Mon |
Dec 2 |
Inspection (Drain Tile) (0) |
|
|
Mon |
Dec 2 |
Settlement Agent Confirmed (0) |
|
|
Mon |
Dec 2 |
Verify Window & Roof Structure (0) |
|
|
Mon |
Dec 2 |
Patio (0) |
|
|
Mon |
Dec 2 |
Rough In Microwave Vent (0) |
|
|
Mon |
Dec 2 |
Inspection (Rough In Plumbing) (1) |
|
|
Tue |
Dec 3 |
Inspection (Rough In Electric) (1) |
|
|
Wed |
Dec 4 |
Inspection (Deck Piers) (0) |
|
|
Wed |
Dec 4 |
Inspection (Framing) (1) |
|
|
Thu |
Dec 5 |
Exterior Stone (0) |
|
|
Thu |
Dec 5 |
Set Electric Meter (0) |
|
|
Thu |
Dec 5 |
Inspection (Main Water Line) (0) |
|
|
Thu |
Dec 5 |
Loan Approval (0) |
|
|
Thu |
Dec 5 |
Deed Preparation (0) |
|
|
Thu |
Dec 5 |
Mailbox (0) |
|
|
Thu |
Dec 5 |
Interior Trim - Paint (1) |
|
|
Fri |
Dec 6 |
Ceiling Fans (0) |
|
|
Fri |
Dec 6 |
Blower Door Test (1) |
|
|
Mon |
Dec 9 |
Inspection (Final HVAC) (1) |
|
|
Tue |
Dec 10 |
Inspection (Final Plumbing) (1) |
|
|
Wed |
Dec 11 |
Inspection (Final Electric) (1) |
|
|
Thu |
Dec 12 |
Stain Hardwood Stairs (1) |
|
|
Fri |
Dec 13 |
Request Trash Tote From POA Manager (0) |
|
|
|
-- |
-- |
Brick-charleston VInyl Ivory Door Color- green |
|
|
-- |
-- |
Two windows missing in basement 11/23 |
|
|
-- |
-- |
Two windows missing in basement 11/23 |
|
|
-- |
-- |
|
|
|
-- |
-- |
Additional cable drop not found 12/28 |
|
|
-- |
-- |
Stud needed in laundry room 1/5 |
Tom |
|
-- |
-- |
Exposed pipe bonus room 1/29 |
|
|
-- |
-- |
Fix siding 2/29 |
JB to fix 3/26 |
|
-- |
-- |
Mulch needed 2/29 |
|
|
-- |
-- |
New globe light in kitchen 2/29 |
|
|
-- |
-- |
Extra cabinet in LR 2/29 |
Still there 3/8 |
|
-- |
-- |
|
|
|
-- |
-- |
Hump in floor |
|
|
-- |
-- |
Vinyl repair above porch needed 3/8 |
|
|
-- |
-- |
Replace fans as noted below 3/8 |
On site 3/14-2 installed |
|
-- |
-- |
CODED LOCKBOX 7474 |
|
|
-- |
-- |
CODED LOCKBOX 7474 |
|
|
-- |
-- |
|
|
|
-- |
-- |
All ceramic is 12x24 and no extra charge that I see 3/11 |
Basement is 12x12 (see specs) |
|
-- |
-- |
Peep hole 3/11 |
|
|
-- |
-- |
Kate - is ceramic installed correctly? |
installed sizes are different than selection sheet - extra cost? |
|
-- |
-- |
Attic cover |
JB |
|
-- |
-- |
Install railings |
Issac to be done this week 3/24ish |
|
-- |
-- |
Install switches for new fans 3/14 |
|
|
-- |
-- |
Missing upper level tub fixtures 3/22 |
|
|
-- |
-- |
MB Mirror needed (in LR) 3/22 |
Needs to be installed - Ron |
|
-- |
-- |
Water valve cover 3/25 |
JB working on it today 4/1 |
|
-- |
-- |
Few tweaks in shelving 3/25 |
Ron |
|
-- |
-- |
Refrigerator handles needed 3/29 |
|
|
-- |
-- |
Microwave installed 3/29 |
|
|
-- |
-- |
Needs cleaning 4/1 |
|
|
-- |
-- |
Screens needed 4/1 |
Checking with JB and Tom |
|
-- |
-- |
Chip in marble counter basement bath 4/1 |
|
|
-- |
-- |
|
|
|
-- |
-- |
Patch hole behind sink in half bath |
John weeks |
|
-- |
-- |
|
|
|
-- |
-- |
|
|
|
-- |
-- |
Replace siding in front |
John Weeks |
|
-- |
-- |
Building Permit (30) |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) |
|
|
-- |
-- |
Order Windows & Doors (0) |
|
|
-- |
-- |
Stake Out Home (1) |
|
|
-- |
-- |
Excavate (2) |
|
|
-- |
-- |
Inspection (Footers) (1) |
|
|
-- |
-- |
Pour Footers (1) |
|
|
-- |
-- |
Set Forms (2) |
|
|
-- |
-- |
Pour Foundation Walls (1) |
|
|
-- |
-- |
Plumb Slab (2) |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
-- |
-- |
Prepare Slab (1) |
|
|
-- |
-- |
Inspection (Slab) (1) |
|
|
-- |
-- |
Pour Slab (1) * |
|
|
-- |
-- |
Framing I (9) |
|
|
-- |
-- |
Order Steps (0) |
|
|
-- |
-- |
Order Tubs / Showers (0) |
|
|
-- |
-- |
Framing II (8) |
|
|
-- |
-- |
Framing III (8) * |
|
|
-- |
-- |
Install Stairs (0) |
|
|
-- |
-- |
Windows & Doors (0) |
|
|
-- |
-- |
House Number and Status in Window (0) |
|
|
-- |
-- |
Roofing (0) |
|
|
-- |
-- |
Order Cabinets (0) |
|
|
-- |
-- |
Order Appliances (0) |
|
|
-- |
-- |
Deck (0) |
In process 11/16 |
|
-- |
-- |
Gutters (0) |
|
|
-- |
-- |
Driveway (0) |
set to poor stoop Thurs 2/20 Set to start poor sidewalk 2/17 Patio done 1/29 |
|
-- |
-- |
Privacy Divider / Fence (0) |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) |
|
|
-- |
-- |
HVAC Rough In (4) |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) |
Tue |
|
-- |
-- |
Plumbing Rough In (4) |
|
|
-- |
-- |
Electric Rough In (4) |
|
|
-- |
-- |
Exterior Vinyl (0) * |
in process 1/5 |
|
-- |
-- |
Insulation (2) |
Wed, Jan 15 |
|
-- |
-- |
Inspection (Insulation) (1) |
|
|
-- |
-- |
Inspection (Electric Service) (0) |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) |
|
|
-- |
-- |
Order Interior Doors & Trim (0) |
|
|
-- |
-- |
Drywall (Hang) (4) * |
In process 1/26 |
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
|
|
-- |
-- |
Paint 1 (1) |
Today 2/20 |
|
-- |
-- |
Garage Door (0) |
|
|
-- |
-- |
House Numbers (0) |
|
|
-- |
-- |
Cabinet Installation (2) * |
Set to deliver 2/25 Abi will install 2/28 |
|
-- |
-- |
Granite Installation (1) * |
3/12 |
|
-- |
-- |
Interior Trim - Install (3) |
In process 2/26 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * |
Started today 3/11 |
|
-- |
-- |
Luxury Vinyl Tile (0) |
Tom will tell Eric we are ready for it (2/27)-on site 3/4 |
|
-- |
-- |
Paint 2 (3) |
In process 3/4 |
|
-- |
-- |
Cover Floors (1) |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) |
Kate submitted to be ordered on 3/2 |
|
-- |
-- |
Shoe Moulding (0) |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) |
Few mirrors needed 3/18 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) |
|
|
-- |
-- |
Set Water Meter (0) |
Water check up 3/19 |
|
-- |
-- |
Electric Trim Out (3) |
Basement needs trim out/vanity lights needed everywhere 3/18 |
|
-- |
-- |
HVAC Trim Out (1) |
Trim out needed 3/14 |
|
-- |
-- |
Plumbing Trim Out (2) |
In process 3/14 |
|
-- |
-- |
Install Appliances (0) * |
Thursday, March 26 |
|
-- |
-- |
Paint 3 (2) * |
In process 3/25 |
|
-- |
-- |
Carpet (2) |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) |
|
|
-- |
-- |
Inspection (Final Building) (2) * |
Friday, March 27 |
|
-- |
-- |
Pre Walk Through (0) |
|
|
-- |
-- |
Cleaning (1) |
In process |
|
-- |
-- |
Certificate of Occupancy (1) * |
|
|
-- |
-- |
C.O. to Lender (0) |
|
|
-- |
-- |
Schedule Closing (0) |
|
|
-- |
-- |
Buyer Walk Through (1) |
Thursday, April 2 at 6PM |
|
-- |
-- |
Payment for Upgrades (0) |
$15,595 |
|
-- |
-- |
Keys to Settlement Agent (0) |
|
|
-- |
-- |
Review Settlement Statement (0) |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) |
Bankers Title, Susan Miller |
|
-- |
-- |
Closing (1) |
Friday, April 3rd |
|
-- |
-- |
Remove Coded Lockbox (0) |
|
|