ADDR
- 43  ::  2208 Deyerle Avenue
[ BUILD: 1908-0090 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Ceiling Fans (0)      
Fri    Dec 6      Blower Door Test (1)      
Mon    Dec 9      Inspection (Final HVAC) (1)      
Tue    Dec 10      Inspection (Final Plumbing) (1)      
Wed    Dec 11      Inspection (Final Electric) (1)      
Thu    Dec 12      Stain Hardwood Stairs (1)      
--   --   Finished basement - details TBD
--   --   Pocket doors-Upstairs master bathroom upstairs laundry room main floor pantry in powder bath basement floor bedroom and bathroom
--   --   Pocket doors- basement bath, Powder bath, pantry, laundry room, master bath
--   --   Kate - update pricing for lighting upgrades 4 cans in bonus, under cabinet in kitchen
--   --   Edgecomb Gray- all bathroom walls
--   --   Portsmouth Brick, Country Beige Vinyl Green Door
--   --   Tilted basement wall? 3/29 HVAC company appears to have moved it
--   --   Non-refundable deposit to avoid appraisal issues?
--   --   Basement bonus room appears to have sound-proofing insulation all around 5/3. Living room (main level) has standard insulation.
--   --   Door Color- Light Gray- Kate to confirm with Isaac BM Gray Huskie 1473
--   --   Missing door to garage On site. Needs installed 7/15
--   --   Tile for shower-on site? 7/1 Classic should have delivered it GWB
--   --   Classic delivery in LR 7/4
--   --   Broken farmhouse sink 7/12 Farm sink coming in today. Should be set friday 7/17 GWB
--   --   I see all kitchen upgrades except trash pull out 7/15 Jeff to order new hardware. It never came with it GWB
--   --   Take out bathroom shower tile joe working today 7/27
--   --   Trash can pull out added Classic has it. waiting on installer. 8/11 GWB
--   --   Peephole needed and door pull to interior garage door Ron knows to install
--   --   Trim needed foyer area Issac to install Monday 8/10
--   --   Herringbone pattern tile in master bath Joe to tile 8/4 GWB-needs grout 8/5
--   --   Stain 2 sets of steps In process 8/2
--   --   Two plugs on kitchen island added 8/2 GWB
--   --   Trim pieces for 1/2 bath vanity needed Issac to install Monday 8/10
--   --   Trim in hall bath needed Issac to install Monday 8/10
--   --   Touch up paint 8/5
--   --   Ceiling blemishes in bonus room
--   --   Cabinet door adjustments Few never cabinets/don’t stay closed
--   --   Stove drawer issue? CJ to check on 8/11
--   --   Seed/straw removed concrete areas 8/5
--   --   RED DOOR Galindez to paint 8/17 GWB
--   --  
--   --   Trim in basement bath needed Issac to install Monday 8/10
--   --   Few sink drains missing Drains on order. Hawkeye to install 8/10
--   --   Speakers for bonus room? Wires installed
--   --   Drain pans for washer/dryer (in garage)
--   --   HVAC trim out partially complete 8/8 Set to finish 8/11 GWB
--   --   Set mirror Ron install 8/10
--   --   Install new microwave CJ to install 8/11
--   --   Fillers for bathroom vanity On order from Classic
--   --   Powder Pocket door seems high l?
--   --   Powder Pocket door seems high
--   --   Make sure garage door opener works
--   --   Caulk and paint trim
--   --   Adjust doors to utility room
--   --   Door plugs
--   --   Patch hole in living room In process 8/12
--   --   Quarter round on all bathroom vanities
--   --   Quarter round on all bathroom vanities
--   --   Back deadbolt doesn’t line up
--   --   Home Inspection - Aug 20 at 10AM Brad Van Horn
--   --   Final Walk Through - Aug 24 with buyer at 11:30 AM
--   --   Handrails put back on Galindez GWB
--   --   Dining room light needs bulbs Greg will put bulbs in.
--   --   Paint touch up Galindez
--   --   Pull up cardboard on floors 8/19 Jill today 8/19
--   --   Few paint dings on MB vanity. Touch up pen should conceal. 8/19 Greg will use Touch up kit to conceal GWB
--   --   Lightbulbs in dining room 8/19
--   --   Remove large subdivision site signs Tom
--   --   Few nail holes to putty on steps 8/23
--   --   Coded lockbox 4343
--   --   Paint touch up Galindez scheduled for the week of 9/1 GWB
--   --   Fix j channels on windows. Greg Sigmon - today, September 14
--   --   Re-caulk front door JB - rain pending
--   --   Caulk around rear door JB - rain pending
--   --   Caulk around rear door
--   --   Bill Polen 703-343-3846
--   --   Fix drywall in master bedroom Joe to fix 11/11 GWB
--   --   Semi Frameless shower door master bath Might have been installed on Friday, Sep 4 - Greg will check
--   --   pin hole in tub
--   --   Nail pops (ceiling of upper steps and upstairs wall between bath & laundry room)
--   --   Three windows in LR have marks between the glass seals, need replacing
--   --   Electric wall switches in bathroom (2nd level bath & upper level bath need to be changed so overhead light switch is first switch that is turned on)
--   --   2nd level hall bath molding has moved away from wall and needs adjusting.
--   --   Shoe molding under the vanity needs to be installed properly
--   --   Ceiling in LR over bottom stairs has a seam that has popped out and needs to be repaired
--   --   Adjustment of the garage door track
--   --   Water pressure on both outside hose bibs needs adjusting
--   --   Tile in basement bathroom is cracked (under toilet)
--   --   Ceiling in kitchen needs retaping/sanded/painted
--   --   Driveway cement cracks
--   --   Back steps not code size.
--   --   Back steps not code size.
--   --   Gutter installation
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)       in process 3/11
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)       12x18 patio
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)       In process again 4/22
-- -- Electric Rough In (4)       In process 4/29
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2)       4/30
-- -- Inspection (Insulation) (1)       Monday, May 4
-- -- Inspection (Electric Service) (0)       basments hooked up of all units. wiring rest of the houses this week
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       Doors ordered waiting to order Trim
-- -- Drywall (Hang) (4) *        In process 5/17
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        6/17
-- -- Paint 1 (1)       Issac set to start 6/22 GWB pushed back due to Drywall not being ready
-- -- Garage Door (0)      
-- -- House Numbers (0)       All electrical outlets have been added
-- -- Cabinet Installation (2) *        Set to install 7/3 GWB
-- -- Granite Installation (1) *        Set to install 7/30 GWB per Cathy Pitts GWB
-- -- Interior Trim - Install (3)       Completed except crown 6/28
-- -- Order Plumbing / Lighting Fixtures (0)       Plumbing fixtures onsite 7/6 need a box of snap lights and 4 ceiling fans GWB
-- -- Luxury Vinyl Plank (3) *        Set to finish today 7/16 GWB
-- -- Luxury Vinyl Tile (0)       On site 6/28 Joe installing today 6/29
-- -- Paint 2 (3)       greg investigating..
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)       plumbing set to deliver 6/29
-- -- Shoe Moulding (0)       Issac to install Monday 8/10
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       started 7/15 GWB
-- -- Install Coded Lockbox (add extra keys) (0)       waiting on permeant door lock
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0)       Pending approval form city 7/5
-- -- Electric Trim Out (3)       In process 7/29 GWB
-- -- HVAC Trim Out (1)       HVAC onsite 6/24
-- -- Plumbing Trim Out (2)       Few missing. Mostly complete 8/8
-- -- Install Appliances (0) *        Installing today 8/3
-- -- Paint 3 (2) *        Galindez set to complete 7/20 or 7/21
-- -- Carpet (2)       set to install 7/16 GWB
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        August 4/5 hopefully
-- -- Pre Walk Through (0)       Greg 8/11 GWB
-- -- Cleaning (1)       In process 8/15
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)       Closing set for 8/25
-- -- Buyer Walk Through (1)       set for 8/19 GWB per Luke
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Request Trash Tote From POA Manager (0)      
-- -- Closing (1)       Tuesday, August 25, 10AM at WVT
-- -- Remove Coded Lockbox (0)