- 44  ::  2210 Deyerle Avenue
[ BUILD: 1908-0091 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Scott Cason 540-830-1417
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Ceiling Fans (0)      
Fri    Dec 6      Blower Door Test (1)      
Mon    Dec 9      Inspection (Final HVAC) (1)      
Tue    Dec 10      Inspection (Final Plumbing) (1)      
Wed    Dec 11      Inspection (Final Electric) (1)      
Thu    Dec 12      Stain Hardwood Stairs (1)      
Fri    Dec 13      Request Trash Tote From POA Manager (0)      
--   --   Buyer wants to know if he can widen the driveway NO DRIVEWAY UPGRADE
--   --   Bone Vinyl, Red Door
--   --   Salinas White Granite tagged at Fenco
--   --   12x18 patio? Framed for one 6/14
--   --   Garage interior door needed 6/28 On site 7/15 needs installed
--   --   Install flooring in kitchen 7/4
--   --   Cabinet-not pedestal in powder bath 7/4 In error?
--   --   Replace fronts of cabinets where mis-drilled Onsite and David will 8/8 GWB
--   --   Cover carpet 7/8 Jill
--   --   Trim needed powder bath 7/15 Galindez knows 7/17 GWB
--   --   Mirrors Ron to install 8/3 GWB
--   --   Paint touch up needed Galindez over weekend or Monday 8/3
--   --   Hardware on garage interior door needed Greg will contact Jeff at Davenport
--   --   Few electric fixtures needed installed (the correct ones) Patrick to take care of 7/30 GWB
--   --   Paint door
--   --   Stain steps In process 8/2
--   --   Final clean Kelly starting to clean today - final to complete 8/4 GWB
--   --   Take up cardboard
--   --   Final inspection
--   --   Crack in master tub Kevin to repair Tues 8/4 GWB
--   --   Cut ac vent under kitchen sink
--   --   Cut ac vent under kitchen sink
--   --   Put in screen door JB
--   --   put in remaining window screens JB
--   --   Door Plugs JB
--   --   Replace weather stripping JB
--   --   Paint Attic cover Galindez Mon. 8/3 GWB
--   --   Fix drain issue on patio Tom
--   --   Seal exterior light in rear JB should have done yesterday 8/5
--   --   Water main leak in front?
--   --   Cut down grade at back of patio Tom is in touch with Partners
--   --   Paint touch up Painte to complete 9/3 GWB
--   --   Grass seed Roger to seed 9/4 GWB
--   --   Power wash back around patio JB -to finish 9/4 GWB
--   --   Power Wash garage door John Weeks
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)      
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)      
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       Started 3/25
-- -- Inspection (Rough In HVAC) (1)       Friday, April 24
-- -- Plumbing Rough In (4)       In process 4/19
-- -- Electric Rough In (4)       In process 4/22
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2)       Tuesday, April 28
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)       basments hooked up of all units. wiring rest of the houses this week
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        In process 5/3
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        set to finish Friday 5/29
-- -- Paint 1 (1)       Issac Set to start 6/4
-- -- Garage Door (0)       set to install today 5/21
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        All but upstairs bath completed 7/4
-- -- Granite Installation (1) *        Set to install 7/14 GWB
-- -- Interior Trim - Install (3)       Almost complete 6/10
-- -- Order Plumbing / Lighting Fixtures (0)       Plumbing fixtures on site and some Electrical GWB 7/1
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Eric Set to deliver 5/29 install 6/2 Joe
-- -- Paint 2 (3)       will paint later next week 6/25
-- -- Cover Floors (1)       Jill to cover today 6/25 GWB
-- -- Deliver Plumbing / Lighting Fixtures (0)       Lighting on site 6/24 GWB Plumbing on order and set to deliver 6/29
-- -- Shoe Moulding (0)       Issac to order and install next week 7/13 GWB
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       Ron waiting on final paint. Should have everything else set this week GWB
-- -- Install Coded Lockbox (add extra keys) (0)       Courtney asked Cary to install one 7/16 GWB
-- -- Pay Water / Sewer Taps (0)       Greg taking water check today 7/13 GWB
-- -- Set Water Meter (0)       waiting on closing to cut jet. Tom setting jumper 7/15
-- -- Electric Trim Out (3)       Quite a bit still needs done 7/25 Patrick will get done GWB
-- -- HVAC Trim Out (1)       Ronnie asked to finish this week 7/20 GWB
-- -- Plumbing Trim Out (2)       In process 7/15
-- -- Install Appliances (0) *        CJ set for 7/20 GWB
-- -- Paint 3 (2) *        Galindez set to complete 7/17
-- -- Carpet (2)       Eric notified its ready for carpet 6/23 GWB waiting to hear install date
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Monday, July 27pm or Tues am GWB or 31st
-- -- Pre Walk Through (0)       July 30 11:30
-- -- Cleaning (1)       Kelly set to start 7/28 GWB
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)       Passed final 7/29 waiting on CO from City
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1)       Thursday, July 30 at 11:30 AM
-- -- Payment for Upgrades (0)       $1700
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       Mon, Aug 10? walk through at 9am
-- -- Remove Coded Lockbox (0)