Wed |
Nov 27 |
Ratified Contract? (0) |
|
|
Wed |
Nov 27 |
$2500 Deposit Received (0) |
|
|
Wed |
Nov 27 |
Association Packet Requested (0) |
|
|
Wed |
Nov 27 |
Association Packet Received (0) |
|
|
Wed |
Nov 27 |
Selections Meeting (0) |
|
|
Wed |
Nov 27 |
Selections Sheet Signed (0) |
|
|
Wed |
Nov 27 |
Amendment for Upgrades (B,S,L,T,BCP) (0) |
|
|
Wed |
Nov 27 |
Deposit For Upgrades Received (0) |
|
|
Wed |
Nov 27 |
Inspection (Concrete Wall) (1) |
|
|
Thu |
Nov 28 |
Inspection (Conduit Under Slab) (1) |
|
|
Fri |
Nov 29 |
Inspection (Drain Tile) (0) |
|
|
Fri |
Nov 29 |
Settlement Agent Confirmed (0) |
|
|
Fri |
Nov 29 |
Verify Window & Roof Structure (0) |
|
|
Fri |
Nov 29 |
Patio (0) |
|
|
Fri |
Nov 29 |
Rough In Microwave Vent (0) |
|
|
Fri |
Nov 29 |
Inspection (Rough In Plumbing) (1) |
|
|
Mon |
Dec 2 |
Inspection (Rough In Electric) (1) |
|
|
Tue |
Dec 3 |
Inspection (Deck Piers) (0) |
|
|
Tue |
Dec 3 |
Inspection (Framing) (1) |
|
|
Wed |
Dec 4 |
Exterior Stone (0) |
|
|
Wed |
Dec 4 |
Set Electric Meter (0) |
|
|
Wed |
Dec 4 |
Inspection (Main Water Line) (0) |
|
|
Wed |
Dec 4 |
Loan Approval (0) |
|
|
Wed |
Dec 4 |
Deed Preparation (0) |
|
|
Wed |
Dec 4 |
Mailbox (0) |
|
|
Wed |
Dec 4 |
Interior Trim - Paint (1) |
|
|
Thu |
Dec 5 |
Ceiling Fans (0) |
|
|
Thu |
Dec 5 |
Blower Door Test (1) |
|
|
Fri |
Dec 6 |
Inspection (Final HVAC) (1) |
|
|
Mon |
Dec 9 |
Inspection (Final Plumbing) (1) |
|
|
Tue |
Dec 10 |
Inspection (Final Electric) (1) |
|
|
Wed |
Dec 11 |
Stain Hardwood Stairs (1) |
|
|
Thu |
Dec 12 |
Request Trash Tote From POA Manager (0) |
|
|
|
-- |
-- |
Request for double driveway |
pricing? |
|
-- |
-- |
Charleston Brick , ivory vinyl, gold door |
|
|
-- |
-- |
Install kitchen window 4/4 |
On site |
|
-- |
-- |
Keys? |
garage door |
|
-- |
-- |
Patio not enlarged 6/14 |
Kenny knows |
|
-- |
-- |
CODED LOCKBOX 4545 |
Can we remove house? I think Lockbox was already taken |
|
-- |
-- |
I don’t see comfort height toilets in garage 7/1 |
|
|
-- |
-- |
Kitchen Cabinet broken 7/4? |
on order and should be installed Friday 7/10 |
|
-- |
-- |
Hardware needed for MB vanity/hall/basement 7/15 |
|
|
-- |
-- |
Stain steps |
Saturday, July 25-done. Needs poly. |
|
-- |
-- |
Paint front door |
Asking Issac to complete 7/27 waiting to hear back GWB |
|
-- |
-- |
Vanity hardware needed for hall/MB 7/15 |
Ordered - should arrive 7/23 |
|
-- |
-- |
Upper cabinet trim-remove? 7/15 |
|
|
-- |
-- |
Mirror basement bath needed 7/25 |
no mirrors will be installed |
|
-- |
-- |
HOME INSPECTION - JULY 27 |
Monday, 7/27 at 9:00 AM |
|
-- |
-- |
Towel bar is really tall in basement bath 7/25 |
Ron fixing/patching |
|
-- |
-- |
Trim piece from hall to bonus room needed 7/25 |
TJ will install GWB |
|
-- |
-- |
Paint touch up needed 7/25 |
Galindez to paint 7/30 GWB |
|
-- |
-- |
Shower curtain rod needed mb 7/25 |
Ron Moore - i will contact GWB |
|
-- |
-- |
2 cabinet replacements? MB and kitchen 7/25 |
ordered |
|
-- |
-- |
Set appliances 7/25 |
|
|
-- |
-- |
finish electric trimout |
|
|
-- |
-- |
re-apply white grout to kitchen backsplash |
|
|
-- |
-- |
|
|
|
-- |
-- |
Final clean |
Set for Friday morning GWB |
|
-- |
-- |
Finish and fix all cabinets |
|
|
-- |
-- |
Bulb in master bedroom fan |
|
|
-- |
-- |
Put in fence in backyard |
Posts in 7/29 |
|
-- |
-- |
Cut off pegs on front of the house- outside |
JB started 7/29 |
|
-- |
-- |
Caulk around basement bath |
JB to finish 7/30 |
|
-- |
-- |
Swap master and hall bath toilets |
Hawkeye done |
|
-- |
-- |
Fix erosion on front of patio |
|
|
-- |
-- |
Dishwasher loop |
Maybe complete 7/29 JB |
|
-- |
-- |
Drawer slide broken (Greg knows) 7/29 |
|
|
-- |
-- |
Finish staining steps 7/29 |
Galindez will complete 7/30 GWB |
|
-- |
-- |
Building Permit (30) |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) |
|
|
-- |
-- |
Order Windows & Doors (0) |
|
|
-- |
-- |
Stake Out Home (1) |
|
|
-- |
-- |
Excavate (2) |
|
|
-- |
-- |
Inspection (Footers) (1) |
|
|
-- |
-- |
Pour Footers (1) |
|
|
-- |
-- |
Set Forms (2) |
|
|
-- |
-- |
Pour Foundation Walls (1) |
|
|
-- |
-- |
Plumb Slab (2) |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
-- |
-- |
Prepare Slab (1) |
|
|
-- |
-- |
Inspection (Slab) (1) |
|
|
-- |
-- |
Pour Slab (1) * |
|
|
-- |
-- |
Framing I (9) |
|
|
-- |
-- |
Order Steps (0) |
|
|
-- |
-- |
Order Tubs / Showers (0) |
|
|
-- |
-- |
Framing II (8) |
|
|
-- |
-- |
Framing III (8) * |
|
|
-- |
-- |
Install Stairs (0) |
|
|
-- |
-- |
Windows & Doors (0) |
|
|
-- |
-- |
House Number and Status in Window (0) |
|
|
-- |
-- |
Roofing (0) |
|
|
-- |
-- |
Order Cabinets (0) |
Will likely order today 5/7 GWB waiting to hear from other subs |
|
-- |
-- |
Order Appliances (0) |
|
|
-- |
-- |
Deck (0) |
|
|
-- |
-- |
Gutters (0) |
|
|
-- |
-- |
Driveway (0) |
12x18 patio |
|
-- |
-- |
Privacy Divider / Fence (0) |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) |
wants to sod after closing/give credit 6/11 |
|
-- |
-- |
HVAC Rough In (4) |
In process 3/25 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) |
|
|
-- |
-- |
Plumbing Rough In (4) |
Basement tub not hooked up 4/19 |
|
-- |
-- |
Electric Rough In (4) |
In process 4/12 |
|
-- |
-- |
Exterior Vinyl (0) * |
|
|
-- |
-- |
Insulation (2) |
Definitely April 21 |
|
-- |
-- |
Inspection (Insulation) (1) |
|
|
-- |
-- |
Inspection (Electric Service) (0) |
basments hooked up of all units. wiring rest of the houses this week |
|
-- |
-- |
Inspection (Main Sewer Line) (0) |
|
|
-- |
-- |
Order Interior Doors & Trim (0) |
|
|
-- |
-- |
Drywall (Hang) (4) * |
In process 4/29 |
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
Just needs sanding 5/9 |
|
-- |
-- |
Paint 1 (1) |
Start on Tues, or Wed 5/12 or 5/13 |
|
-- |
-- |
Garage Door (0) |
Installing today 5/21 |
|
-- |
-- |
House Numbers (0) |
|
|
-- |
-- |
Cabinet Installation (2) * |
Installing Now 7/1 |
|
-- |
-- |
Granite Installation (1) * |
Set to install 7/14 GWB |
|
-- |
-- |
Interior Trim - Install (3) |
In process 5/27 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) |
All plumbing is there GWB |
|
-- |
-- |
Luxury Vinyl Plank (3) * |
Needs to be finished in the kitchen as of July 2nd |
|
-- |
-- |
Luxury Vinyl Tile (0) |
Joe will hopefully start Jun 8 |
|
-- |
-- |
Paint 2 (3) |
mahar Said it’s been done. I’ll double check GWB 6/8-not done 6/10 |
|
-- |
-- |
Cover Floors (1) |
Jill or JB today GWB |
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) |
Plumbing in 6/10 |
|
-- |
-- |
Shoe Moulding (0) |
Issac will installed 7/17 after final paint |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) |
Ron says complete. Getting Tom to check 7/20 GWB |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) |
water paid. identified issue with exterior plumbing. Tom fixing 7/22 GWB |
|
-- |
-- |
Set Water Meter (0) |
Greg taking water check today 7/13 GWB |
|
-- |
-- |
Electric Trim Out (3) |
Patrick working to finish today 7/20 GWB |
|
-- |
-- |
HVAC Trim Out (1) |
HVAC is set 6/24 Ronnie tentatively set to trim out 7/17 GWB |
|
-- |
-- |
Plumbing Trim Out (2) |
Set to finish 7/16 |
|
-- |
-- |
Install Appliances (0) * |
CJ set to install 7/20 GWB |
|
-- |
-- |
Paint 3 (2) * |
Galindez to paint Friday 7/17 GWB |
|
-- |
-- |
Carpet (2) |
Back ordered - waiting on delivery |
|
-- |
-- |
Appraiser Confirms Construction Completion (0) |
|
|
-- |
-- |
Inspection (Final Building) (2) * |
Tuesday, July 21 |
|
-- |
-- |
Pre Walk Through (0) |
Tentatively set for 7/17 GWB |
|
-- |
-- |
Cleaning (1) |
Kelly set to start over the weekend 7/25-26 |
|
-- |
-- |
Certificate of Occupancy (1) * |
|
|
-- |
-- |
C.O. to Lender (0) |
|
|
-- |
-- |
Schedule Closing (0) |
|
|
-- |
-- |
Buyer Walk Through (1) |
Tuesday, July 28 at 4:30 PM |
|
-- |
-- |
Payment for Upgrades (0) |
|
|
-- |
-- |
Keys to Settlement Agent (0) |
|
|
-- |
-- |
Review Settlement Statement (0) |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) |
Main Street Title |
|
-- |
-- |
Closing (1) |
7/31 Main Street Title at 11:30 AM |
|
-- |
-- |
Remove Coded Lockbox (0) |
|
|