- 46  ::  2214 Deyerle Avenue
[ BUILD: 1908-0093 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Inspection (Concrete Wall) (1)      
Wed    Dec 17      Inspection (Conduit Under Slab) (1)      
Thu    Dec 18      Inspection (Drain Tile) (0)      
Thu    Dec 18      Settlement Agent Confirmed (0)      
Thu    Dec 18      Verify Window & Roof Structure (0)      
Thu    Dec 18      Patio (0)      
Thu    Dec 18      Rough In Microwave Vent (0)      
Thu    Dec 18      Inspection (Rough In Plumbing) (1)      
Fri    Dec 19      Inspection (Rough In Electric) (1)      
Mon    Dec 22      Inspection (Framing) (1) *       
Tue    Dec 23      Inspection (Deck Piers) (0)      
Tue    Dec 23      Exterior Stone (0)      
Tue    Dec 23      Set Electric Meter (0) *       
Tue    Dec 23      Inspection (Main Water Line) (0)      
Tue    Dec 23      Loan Approval (0)      
Tue    Dec 23      Deed Preparation (0)      
Tue    Dec 23      Mailbox (0)      
Tue    Dec 23      Interior Trim - Paint (1)      
Wed    Dec 24      Ceiling Fans (0)      
Wed    Dec 24      Blower Door Test (1)      
Thu    Dec 25      Inspection (Final HVAC) (1)      
Fri    Dec 26      Inspection (Final Plumbing) (1)      
Mon    Dec 29      Inspection (Final Electric) (1)      
Tue    Dec 30      Stain Hardwood Stairs (1) *       
Wed    Dec 31      Request Trash Tote From POA Manager (0)      
--   --   Please send photo of Azul Platina slab for buyer to decide
--   --   Fire trying to decide between Azul Platino and silver missed. Need to receive picture of slab for both from Joy prior to template
--   --   Need to receive photos of both granite selections so buyers can choose. Kate to get these photos from Joy and Greg prior to template.
--   --   Buyer needs to decide between two granite selections. Kate to get photos from Joy/Greg prior to template.
--   --   Outlet for Tesla Added to changes- waiting for confirmation from buyer.
--   --   Country Beige Vinyl Red Door
--   --   Carters Grove Brick Bone Vinyl Green Door
--   --   Cabinet hardware needs installed 5/17
--   --   Missing MB vanity handle 5/30 On site. Greg to install 6/15
--   --   CODED LOCKBOX 4646
--   --   Globe for MB fan? 6/14 ordering replacement Kate-replacing today 6/25
--   --   Side by side fridge in 46 not 47? 6/17
--   --   Stain steps b/f walk-through Friday, June 19? Greg talking to Issac-stain is down 6/21
--   --   Railings 6/21 Issac to put back 6/22 GWB
--   --   Dishwasher bracket Greg checking to see if on site 6/25-follow up with Leisa
--   --   Final clean
--   --   Paint touch up Tues, June 30
--   --   Remove screw next to outside kitchen door
--   --   Replace weather stripping on doors JB
--   --   Screen door
--   --   Redo master bedroom light
--   --   Remove temp electrical panel
--   --   Remove temp electrical panel
--   --   Caulking around MB tub spout
--   --   Water spot on kitchen ceiling Drywall needs to be patched
--   --   Secure dishwasher
--   --   Door plugs 6/28 JB
--   --   Remove temp electrical panel
--   --   Remove temp electrical panel
--   --   Garage door drywall patch 7/1 Jeff looking into GWB 7/2
--   --   Leak in basement Called Roto Router. Its a sewage back up GWB 7/6
--   --   Leak at master bathroom sink drain Drywall appears fixed 7/4
--   --   Sewer main back up Called Roto Router Coming out 7/7 GWB
--   --   Few cracks in front patio 7/4
--   --   Carpet In bonus room really wet 7/4 Need dehumidifier. Tom locating GWB 7/6
--   --   Cabinet paint touch up kit needed. Blue tape on cabinets 7/4 Doors coming in Monday 7/13 David to install 7/14 GWB
--   --   Final Clean Kelly coming to do final touch up clean 7/13 GWB
--   --   Touch up front door Mahar coming back today to finish GWB
--   --   Damaged shingles on front stoop Joel will fix Friday 7/10
--   --   Two small dents in window frame Tom to replace today
--   --   Garage door opener does not work Jeff from Davenport going today to fix 7/9 GWB
--   --   Repair dent in garage door flashing Jeremy from Davenport to finish 7/10 GWB
--   --   Replace part of bonus room carpet Eric to replace tomorrow 7/10 GWB
--   --   Clean paint overspray on bathroom floor Kelly to clean today 7/9 GWB
--   --   Install clothes washer pan JB in process 7/9 GWB
--   --   Adjust door on utility room
--   --   Call behind basement toilet
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
    Upgrade hardware Cost  
    Tesla outlet  
    Contract Amendment ($246,000 + $9,175 = $255,175)  
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)       Cabinets ordered Wed 4/29 GWB
-- -- Order Appliances (0)       Ordered 6/9 should be 10 days out
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *        driveway gravel down/patio week of 6/15
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       In process 3/25
-- -- Plumbing Rough In (4)       Appears very near completion 4/4
-- -- Electric Rough In (4)       In process 4/8- appears 90% complete
-- -- Inspection (Rough In HVAC) (1)       Thurs, Apr 9
-- -- Exterior Vinyl (0) *        in process 5/27
-- -- Insulation (2) *        Fri, Apr 10?
-- -- Inspection (Insulation) (1)       Mon, Apr 13
-- -- Inspection (Electric Service) (0)       basments hooked up of all units. wiring rest of the houses this week
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        In process 4/25
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Set to finish Wed 5/6 GWB-in process 5/3
-- -- Paint 1 (1)       Set for Fri. 5/8 GWB Issac should have started
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        In process 5/13
    Dalton Gray Bathroom cabinetry  
-- -- Granite Installation (1) *        Friday, May 22
-- -- Interior Trim - Install (3) *        Set to Finish 5/25
-- -- Order Plumbing / Lighting Fixtures (0)       Set to deliver afternoon Wed 5/27
-- -- Luxury Vinyl Plank (3) *        Eric hoped to start week of June 1
    Main Level Luxury Vinyl Plank  
-- -- Luxury Vinyl Tile (0)       install Mon. 5/11 - Grout 5/12 - bare weight Wed 5/13
    Upgraded 12x24 Tile Throughout  
-- -- Paint 2 (3)       In process 5/27
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)       Set to deliver afternoon Wed 5/27
-- -- Shoe Moulding (0)       greg scheduling with issac 6/11
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        Set to finish today 6/17 gwb
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)       paid 6/17 GWB should be set by Friday
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3) *        Bathroom fans 6/21 Patrick to finish today 6/22
-- -- HVAC Trim Out (1) *        Ronnie to install 6/23 GWB
-- -- Plumbing Trim Out (2) *       
-- -- Install Appliances (0) *        CJ Installing 6/19 GWB
    SS Whirlpool Appliances  
-- -- Paint 3 (2) *        Not complete 6/16
-- -- Carpet (2)       Wed, June 10
-- -- Appraiser Confirms Construction Completion (0)       Thursday, July 2
-- -- Inspection (Final Building) (2) *        Only missed 2 small things. Fixing and getting reinspected today 6/25 GWB
-- -- Pre Walk Through (0)       Set for Friday 6/19 gwb
-- -- Cleaning (1)       Cleaning Started 6/21 set to finish by Friday morning 6/26 GWB
-- -- Certificate of Occupancy (1) *        Still have not received as of 7/6 SPR
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)       Kate contacting Matt
-- -- Buyer Walk Through (1) *        Set for Friday 6/26 at 4pm GWB per Matt
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       Friday, July 17 at 4PM
-- -- Remove Coded Lockbox (0)