ADDR
- 106  ::  2238 Lapis Lane
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Driveway
--   --   Sod
--   --   Curb & Gutter
--   --   Muddy area in backyard
Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Inspection (Concrete Wall) (1)      
Wed    Dec 17      Inspection (Conduit Under Slab) (1)      
Thu    Dec 18      Inspection (Drain Tile) (0)      
Thu    Dec 18      Settlement Agent Confirmed (0)      
Thu    Dec 18      Order Tubs / Showers (0)      
Thu    Dec 18      Framing II (8)      
Tue    Dec 30      Framing III (8) *       
Fri    Jan 9      Verify Window & Roof Structure (0)      
Fri    Jan 9      Install Stairs (0) *       
Fri    Jan 9      House Number and Status in Window (0)      
Fri    Jan 9      Order Appliances (0)      
Fri    Jan 9      Patio (0)      
Fri    Jan 9      Rough In Microwave Vent (0)      
Fri    Jan 9      Inspection (Rough In Plumbing) (1)      
Mon    Jan 12      Inspection (Rough In Electric) (1)      
Tue    Jan 13      Inspection (Framing) (1) *       
Wed    Jan 14      Inspection (Deck Piers) (0)      
Wed    Jan 14      Exterior Stone (0)      
Wed    Jan 14      Set Electric Meter (0) *       
Wed    Jan 14      Inspection (Main Water Line) (0)      
Wed    Jan 14      Loan Approval (0)      
Wed    Jan 14      Deed Preparation (0)      
Wed    Jan 14      Garage Door (0)      
Wed    Jan 14      Mailbox (0)      
Wed    Jan 14      Order Plumbing / Lighting Fixtures (0)      
Wed    Jan 14      Interior Trim - Paint (1)      
Thu    Jan 15      Cover Floors (1)      
Fri    Jan 16      Deliver Plumbing / Lighting Fixtures (0)      
Fri    Jan 16      Shoe Moulding (0)      
Fri    Jan 16      Set Water Meter (0) *       
Fri    Jan 16      Ceiling Fans (0)      
Fri    Jan 16      Blower Door Test (1)      
Mon    Jan 19      Paint 3 (2) *       
Wed    Jan 21      Appraiser Confirms Construction Completion (0)      
Wed    Jan 21      Inspection (Final HVAC) (1)      
Thu    Jan 22      Inspection (Final Plumbing) (1)      
Fri    Jan 23      Inspection (Final Electric) (1)      
Mon    Jan 26      Stain Hardwood Stairs (1) *       
Tue    Jan 27      C.O. to Lender (0)      
Tue    Jan 27      Schedule Closing (0)      
Tue    Jan 27      Payment for Upgrades (0)      
Tue    Jan 27      Keys to Settlement Agent (0)      
Tue    Jan 27      Review Settlement Statement (0)      
Tue    Jan 27      Jerry Signs Closing Documents (0)      
Tue    Jan 27      Request Trash Tote From POA Manager (0)      
Tue    Jan 27      Closing (1)      
Wed    Jan 28      Remove Coded Lockbox (0)      
--   --   Cover floors in kitchen
--   --   Please cover hardwood completely and granite
--   --   Closing by end of June very important
--   --   Cover granite
--   --   Please cover hardwood
--   --   Replace scratched boards by powder bathroom
--   --   Install refrigerator
--   --   Window Screens
--   --   Dimmer Switches / Dimmable light bulbs
--   --   Dimmable light buls
--   --   Dimmable light bulbs
--   --   Broken piece of wood in hall bathroom
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Windows & Doors (0) *       
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *        patio done; front stoop needed
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)       S: Complete except basement bath;
-- -- Electric Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *        K: Almost done
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)       In process
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        B: started (4/18)
-- -- Drywall (Tape, Block, Skim, Sand) (6) *       
-- -- Paint 1 (1)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *       
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3) *        K: in process 5/23
-- -- Luxury Vinyl Plank (3) *        Scott delete?
-- -- Luxury Vinyl Tile (0)       5/26: foyer needs grout;
-- -- Paint 2 (3)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        Friday, June 10
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3) *        Wed/Thurs
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *        Wed/Thurs
-- -- Install Appliances (0) *        K: 6/20 all but fridge
-- -- Carpet (2)       6/14 install
-- -- Inspection (Final Building) (2) *       
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- Buyer Walk Through (1) *