-- |
-- |
Driveway |
|
|
-- |
-- |
Sod |
|
|
-- |
-- |
Curb & Gutter |
|
|
-- |
-- |
Muddy area in backyard |
|
|
Fri |
Sep 20 |
Ratified Contract? (0)
|
|
|
Fri |
Sep 20 |
$2500 Deposit Received (0)
|
|
|
Fri |
Sep 20 |
Association Packet Requested (0)
|
|
|
Fri |
Sep 20 |
Association Packet Received (0)
|
|
|
Fri |
Sep 20 |
Selections Meeting (0)
|
|
|
Fri |
Sep 20 |
Selections Sheet Signed (0)
|
|
|
Fri |
Sep 20 |
Amendment for Upgrades (B,S,L,T,BCP) (0)
|
|
|
Fri |
Sep 20 |
Deposit For Upgrades Received (0)
|
|
|
Fri |
Sep 20 |
Inspection (Concrete Wall) (1)
|
|
|
Mon |
Sep 23 |
Inspection (Conduit Under Slab) (1)
|
|
|
Tue |
Sep 24 |
Inspection (Drain Tile) (0)
|
|
|
Tue |
Sep 24 |
Settlement Agent Confirmed (0)
|
|
|
Tue |
Sep 24 |
Order Tubs / Showers (0)
|
|
|
Tue |
Sep 24 |
Framing II (8)
|
|
|
Fri |
Oct 4 |
Framing III (8)
|
|
|
Wed |
Oct 16 |
Verify Window & Roof Structure (0)
|
|
|
Wed |
Oct 16 |
Install Stairs (0)
|
|
|
Wed |
Oct 16 |
House Number and Status in Window (0)
|
|
|
Wed |
Oct 16 |
Order Appliances (0)
|
|
|
Wed |
Oct 16 |
Patio (0)
|
|
|
Wed |
Oct 16 |
Rough In Microwave Vent (0)
|
|
|
Wed |
Oct 16 |
Inspection (Rough In Plumbing) (1)
|
|
|
Thu |
Oct 17 |
Inspection (Rough In Electric) (1)
|
|
|
Fri |
Oct 18 |
Inspection (Deck Piers) (0)
|
|
|
Fri |
Oct 18 |
Inspection (Framing) (1)
|
|
|
Mon |
Oct 21 |
Exterior Stone (0)
|
|
|
Mon |
Oct 21 |
Set Electric Meter (0)
|
|
|
Mon |
Oct 21 |
Inspection (Main Water Line) (0)
|
|
|
Mon |
Oct 21 |
Loan Approval (0)
|
|
|
Mon |
Oct 21 |
Deed Preparation (0)
|
|
|
Mon |
Oct 21 |
Garage Door (0)
|
|
|
Mon |
Oct 21 |
Mailbox (0)
|
|
|
Mon |
Oct 21 |
Order Plumbing / Lighting Fixtures (0)
|
|
|
Mon |
Oct 21 |
Interior Trim - Paint (1)
|
|
|
Tue |
Oct 22 |
Cover Floors (1)
|
|
|
Wed |
Oct 23 |
Deliver Plumbing / Lighting Fixtures (0)
|
|
|
Wed |
Oct 23 |
Shoe Moulding (0)
|
|
|
Wed |
Oct 23 |
Set Water Meter (0)
|
|
|
Wed |
Oct 23 |
Ceiling Fans (0)
|
|
|
Wed |
Oct 23 |
Blower Door Test (1)
|
|
|
Thu |
Oct 24 |
Paint 3 (2)
|
|
|
Mon |
Oct 28 |
Appraiser Confirms Construction Completion (0)
|
|
|
Mon |
Oct 28 |
Inspection (Final HVAC) (1)
|
|
|
Tue |
Oct 29 |
Inspection (Final Plumbing) (1)
|
|
|
Wed |
Oct 30 |
Inspection (Final Electric) (1)
|
|
|
Thu |
Oct 31 |
Stain Hardwood Stairs (1)
|
|
|
Fri |
Nov 1 |
C.O. to Lender (0)
|
|
|
Fri |
Nov 1 |
Schedule Closing (0)
|
|
|
Fri |
Nov 1 |
Payment for Upgrades (0)
|
|
|
Fri |
Nov 1 |
Keys to Settlement Agent (0)
|
|
|
Fri |
Nov 1 |
Review Settlement Statement (0)
|
|
|
Fri |
Nov 1 |
Jerry Signs Closing Documents (0)
|
|
|
Fri |
Nov 1 |
Request Trash Tote From POA Manager (0)
|
|
|
Fri |
Nov 1 |
Closing (1)
|
|
|
Mon |
Nov 4 |
Remove Coded Lockbox (0)
|
|
|
|
-- |
-- |
Cover floors in kitchen |
|
|
-- |
-- |
Please cover hardwood completely and granite |
|
|
-- |
-- |
Closing by end of June very important |
|
|
-- |
-- |
Cover granite |
|
|
-- |
-- |
Please cover hardwood |
|
|
-- |
-- |
Replace scratched boards by powder bathroom |
|
|
-- |
-- |
Install refrigerator |
|
|
-- |
-- |
Window Screens |
|
|
-- |
-- |
Dimmer Switches / Dimmable light bulbs |
|
|
-- |
-- |
Dimmable light buls |
|
|
-- |
-- |
Dimmable light bulbs |
|
|
-- |
-- |
Broken piece of wood in hall bathroom |
|
|
-- |
-- |
Building Permit (30)
|
|
|
-- |
-- |
Order Roof & Floor Trusses (1)
|
|
|
-- |
-- |
Order Windows & Doors (0)
|
|
|
-- |
-- |
Stake Out Home (1)
|
|
|
-- |
-- |
Excavate (2)
|
|
|
-- |
-- |
Inspection (Footers) (1)
|
|
|
-- |
-- |
Pour Footers (1)
|
|
|
-- |
-- |
Set Forms (2)
|
|
|
-- |
-- |
Pour Foundation Walls (1)
|
|
|
-- |
-- |
Plumb Slab (2)
|
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1)
|
|
|
-- |
-- |
Prepare Slab (1)
|
|
|
-- |
-- |
Inspection (Slab) (1)
|
|
|
-- |
-- |
Pour Slab (1)
|
|
|
-- |
-- |
Framing I (9)
|
|
|
-- |
-- |
Order Steps (0)
|
|
|
-- |
-- |
Windows & Doors (0)
|
|
|
-- |
-- |
Roofing (0)
|
|
|
-- |
-- |
Order Cabinets (0)
|
|
|
-- |
-- |
Deck (0)
|
|
|
-- |
-- |
Gutters (0)
|
|
|
-- |
-- |
Driveway (0)
|
patio done; front stoop needed |
|
-- |
-- |
Privacy Divider / Fence (0)
|
|
|
-- |
-- |
Sod / Seed / Landscaping (0)
|
|
|
-- |
-- |
HVAC Rough In (4)
|
|
|
-- |
-- |
Inspection (Rough In HVAC) (1)
|
|
|
-- |
-- |
Plumbing Rough In (4)
|
S: Complete except basement bath; |
|
-- |
-- |
Electric Rough In (4)
|
|
|
-- |
-- |
Exterior Vinyl (0)
|
K: Almost done |
|
-- |
-- |
Insulation (2)
|
|
|
-- |
-- |
Inspection (Insulation) (1)
|
|
|
-- |
-- |
Inspection (Electric Service) (0)
|
In process |
|
-- |
-- |
Inspection (Main Sewer Line) (0)
|
|
|
-- |
-- |
Order Interior Doors & Trim (0)
|
|
|
-- |
-- |
Drywall (Hang) (4)
|
B: started (4/18) |
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6)
|
|
|
-- |
-- |
Paint 1 (1)
|
|
|
-- |
-- |
House Numbers (0)
|
|
|
-- |
-- |
Cabinet Installation (2)
|
|
|
-- |
-- |
Granite Installation (1)
|
|
|
-- |
-- |
Interior Trim - Install (3)
|
K: in process 5/23 |
|
-- |
-- |
Luxury Vinyl Plank (3)
|
Scott delete? |
|
-- |
-- |
Luxury Vinyl Tile (0)
|
5/26: foyer needs grout; |
|
-- |
-- |
Paint 2 (3)
|
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0)
|
Friday, June 10 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0)
|
|
|
-- |
-- |
Pay Water / Sewer Taps (0)
|
|
|
-- |
-- |
Electric Trim Out (3)
|
Wed/Thurs |
|
-- |
-- |
HVAC Trim Out (1)
|
|
|
-- |
-- |
Plumbing Trim Out (2)
|
Wed/Thurs |
|
-- |
-- |
Install Appliances (0)
|
K: 6/20 all but fridge |
|
-- |
-- |
Carpet (2)
|
6/14 install |
|
-- |
-- |
Inspection (Final Building) (2)
|
|
|
-- |
-- |
Pre Walk Through (0)
|
|
|
-- |
-- |
Cleaning (1)
|
|
|
-- |
-- |
Certificate of Occupancy (1)
|
|
|
-- |
-- |
Buyer Walk Through (1)
|
|
|