Driveway |
|
|
-- |
-- |
Sod |
|
|
-- |
-- |
Curb & Gutter |
|
|
-- |
-- |
Muddy area in backyard |
|
|
Thu |
Nov 28 |
Ratified Contract? (0) |
|
|
Thu |
Nov 28 |
$2500 Deposit Received (0) |
|
|
Thu |
Nov 28 |
Association Packet Requested (0) |
|
|
Thu |
Nov 28 |
Association Packet Received (0) |
|
|
Thu |
Nov 28 |
Selections Meeting (0) |
|
|
Thu |
Nov 28 |
Selections Sheet Signed (0) |
|
|
Thu |
Nov 28 |
Amendment for Upgrades (B,S,L,T,BCP) (0) |
|
|
Thu |
Nov 28 |
Deposit For Upgrades Received (0) |
|
|
Thu |
Nov 28 |
Inspection (Concrete Wall) (1) |
|
|
Fri |
Nov 29 |
Inspection (Conduit Under Slab) (1) |
|
|
Mon |
Dec 2 |
Inspection (Drain Tile) (0) |
|
|
Mon |
Dec 2 |
Settlement Agent Confirmed (0) |
|
|
Mon |
Dec 2 |
Order Tubs / Showers (0) |
|
|
Mon |
Dec 2 |
Framing II (8) |
|
|
Thu |
Dec 12 |
Framing III (8) * |
|
|
Tue |
Dec 24 |
Verify Window & Roof Structure (0) |
|
|
Tue |
Dec 24 |
Install Stairs (0) |
|
|
Tue |
Dec 24 |
House Number and Status in Window (0) |
|
|
Tue |
Dec 24 |
Order Appliances (0) |
|
|
Tue |
Dec 24 |
Patio (0) |
|
|
Tue |
Dec 24 |
Rough In Microwave Vent (0) |
|
|
Tue |
Dec 24 |
Inspection (Rough In Plumbing) (1) |
|
|
Wed |
Dec 25 |
Inspection (Rough In Electric) (1) |
|
|
Thu |
Dec 26 |
Inspection (Deck Piers) (0) |
|
|
Thu |
Dec 26 |
Inspection (Framing) (1) |
|
|
Fri |
Dec 27 |
Exterior Stone (0) |
|
|
Fri |
Dec 27 |
Set Electric Meter (0) |
|
|
Fri |
Dec 27 |
Inspection (Main Water Line) (0) |
|
|
Fri |
Dec 27 |
Loan Approval (0) |
|
|
Fri |
Dec 27 |
Deed Preparation (0) |
|
|
Fri |
Dec 27 |
Garage Door (0) |
|
|
Fri |
Dec 27 |
Mailbox (0) |
|
|
Fri |
Dec 27 |
Order Plumbing / Lighting Fixtures (0) |
|
|
Fri |
Dec 27 |
Interior Trim - Paint (1) |
|
|
Mon |
Dec 30 |
Cover Floors (1) |
|
|
Tue |
Dec 31 |
Deliver Plumbing / Lighting Fixtures (0) |
|
|
Tue |
Dec 31 |
Shoe Moulding (0) |
|
|
Tue |
Dec 31 |
Set Water Meter (0) |
|
|
Tue |
Dec 31 |
Ceiling Fans (0) |
|
|
Tue |
Dec 31 |
Blower Door Test (1) |
|
|
Wed |
Jan 1 |
Paint 3 (2) * |
|
|
Fri |
Jan 3 |
Appraiser Confirms Construction Completion (0) |
|
|
Fri |
Jan 3 |
Inspection (Final HVAC) (1) |
|
|
Mon |
Jan 6 |
Inspection (Final Plumbing) (1) |
|
|
Tue |
Jan 7 |
Inspection (Final Electric) (1) |
|
|
Wed |
Jan 8 |
Stain Hardwood Stairs (1) |
|
|
Thu |
Jan 9 |
C.O. to Lender (0) |
|
|
Thu |
Jan 9 |
Schedule Closing (0) |
|
|
Thu |
Jan 9 |
Payment for Upgrades (0) |
|
|
Thu |
Jan 9 |
Keys to Settlement Agent (0) |
|
|
Thu |
Jan 9 |
Review Settlement Statement (0) |
|
|
Thu |
Jan 9 |
Jerry Signs Closing Documents (0) |
|
|
Thu |
Jan 9 |
Request Trash Tote From POA Manager (0) |
|
|
Thu |
Jan 9 |
Closing (1) |
|
|
Fri |
Jan 10 |
Remove Coded Lockbox (0) |
|
|
|
-- |
-- |
Cover floors in kitchen |
|
|
-- |
-- |
Please cover hardwood completely and granite |
|
|
-- |
-- |
Closing by end of June very important |
|
|
-- |
-- |
Cover granite |
|
|
-- |
-- |
Please cover hardwood |
|
|
-- |
-- |
Replace scratched boards by powder bathroom |
|
|
-- |
-- |
Install refrigerator |
|
|
-- |
-- |
Window Screens |
|
|
-- |
-- |
Dimmer Switches / Dimmable light bulbs |
|
|
-- |
-- |
Dimmable light buls |
|
|
-- |
-- |
Dimmable light bulbs |
|
|
-- |
-- |
Broken piece of wood in hall bathroom |
|
|
-- |
-- |
Building Permit (30) |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) |
|
|
-- |
-- |
Order Windows & Doors (0) |
|
|
-- |
-- |
Stake Out Home (1) |
|
|
-- |
-- |
Excavate (2) |
|
|
-- |
-- |
Inspection (Footers) (1) |
|
|
-- |
-- |
Pour Footers (1) |
|
|
-- |
-- |
Set Forms (2) |
|
|
-- |
-- |
Pour Foundation Walls (1) |
|
|
-- |
-- |
Plumb Slab (2) |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
-- |
-- |
Prepare Slab (1) |
|
|
-- |
-- |
Inspection (Slab) (1) |
|
|
-- |
-- |
Pour Slab (1) * |
|
|
-- |
-- |
Framing I (9) |
|
|
-- |
-- |
Order Steps (0) |
|
|
-- |
-- |
Windows & Doors (0) |
|
|
-- |
-- |
Roofing (0) |
|
|
-- |
-- |
Order Cabinets (0) |
|
|
-- |
-- |
Deck (0) |
|
|
-- |
-- |
Gutters (0) |
|
|
-- |
-- |
Driveway (0) |
patio done; front stoop needed |
|
-- |
-- |
Privacy Divider / Fence (0) |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) |
|
|
-- |
-- |
HVAC Rough In (4) |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) |
|
|
-- |
-- |
Plumbing Rough In (4) |
S: Complete except basement bath; |
|
-- |
-- |
Electric Rough In (4) |
|
|
-- |
-- |
Exterior Vinyl (0) * |
K: Almost done |
|
-- |
-- |
Insulation (2) |
|
|
-- |
-- |
Inspection (Insulation) (1) |
|
|
-- |
-- |
Inspection (Electric Service) (0) |
In process |
|
-- |
-- |
Inspection (Main Sewer Line) (0) |
|
|
-- |
-- |
Order Interior Doors & Trim (0) |
|
|
-- |
-- |
Drywall (Hang) (4) * |
B: started (4/18) |
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
|
|
-- |
-- |
Paint 1 (1) |
|
|
-- |
-- |
House Numbers (0) |
|
|
-- |
-- |
Cabinet Installation (2) * |
|
|
-- |
-- |
Granite Installation (1) * |
|
|
-- |
-- |
Interior Trim - Install (3) |
K: in process 5/23 |
|
-- |
-- |
Luxury Vinyl Plank (3) * |
Scott delete? |
|
-- |
-- |
Luxury Vinyl Tile (0) |
5/26: foyer needs grout; |
|
-- |
-- |
Paint 2 (3) |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) |
Friday, June 10 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) |
|
|
-- |
-- |
Electric Trim Out (3) |
Wed/Thurs |
|
-- |
-- |
HVAC Trim Out (1) |
|
|
-- |
-- |
Plumbing Trim Out (2) |
Wed/Thurs |
|
-- |
-- |
Install Appliances (0) * |
K: 6/20 all but fridge |
|
-- |
-- |
Carpet (2) |
6/14 install |
|
-- |
-- |
Inspection (Final Building) (2) * |
|
|
-- |
-- |
Pre Walk Through (0) |
|
|
-- |
-- |
Cleaning (1) |
|
|
-- |
-- |
Certificate of Occupancy (1) * |
|
|
-- |
-- |
Buyer Walk Through (1) |
|
|