ADDR
- 103  ::  2232 Lapis Lane
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Order Tubs / Showers (0)      
Mon    Dec 2      Framing II (8)      
Thu    Dec 12      Framing III (8) *       
Tue    Dec 24      Verify Window & Roof Structure (0)      
Tue    Dec 24      Install Stairs (0)      
Tue    Dec 24      House Number and Status in Window (0)      
Tue    Dec 24      Order Appliances (0)      
Tue    Dec 24      Patio (0)      
Tue    Dec 24      Rough In Microwave Vent (0)      
Tue    Dec 24      Inspection (Rough In Plumbing) (1)      
Wed    Dec 25      Inspection (Rough In Electric) (1)      
Thu    Dec 26      Inspection (Deck Piers) (0)      
Thu    Dec 26      Inspection (Framing) (1)      
Fri    Dec 27      Exterior Stone (0)      
Fri    Dec 27      Set Electric Meter (0)      
Fri    Dec 27      Inspection (Main Water Line) (0)      
Fri    Dec 27      Loan Approval (0)      
Fri    Dec 27      Deed Preparation (0)      
Fri    Dec 27      Garage Door (0)      
Fri    Dec 27      Mailbox (0)      
Fri    Dec 27      Order Plumbing / Lighting Fixtures (0)      
Fri    Dec 27      Interior Trim - Paint (1)      
Mon    Dec 30      Cover Floors (1)      
Tue    Dec 31      Deliver Plumbing / Lighting Fixtures (0)      
Tue    Dec 31      Shoe Moulding (0)      
Tue    Dec 31      Set Water Meter (0)      
Tue    Dec 31      Ceiling Fans (0)      
Tue    Dec 31      Blower Door Test (1)      
Wed    Jan 1      Paint 3 (2) *       
Fri    Jan 3      Appraiser Confirms Construction Completion (0)      
Fri    Jan 3      Inspection (Final HVAC) (1)      
Mon    Jan 6      Inspection (Final Plumbing) (1)      
Tue    Jan 7      Inspection (Final Electric) (1)      
Wed    Jan 8      Stain Hardwood Stairs (1)      
Thu    Jan 9      C.O. to Lender (0)      
Thu    Jan 9      Schedule Closing (0)      
Thu    Jan 9      Payment for Upgrades (0)      
Thu    Jan 9      Keys to Settlement Agent (0)      
Thu    Jan 9      Review Settlement Statement (0)      
Thu    Jan 9      Jerry Signs Closing Documents (0)      
Thu    Jan 9      Request Trash Tote From POA Manager (0)      
Thu    Jan 9      Closing (1)      
Fri    Jan 10      Remove Coded Lockbox (0)      
--   --   Squeak (give) in floor by powder bath
--   --   Grout?
--   --   Please cover granite
--   --   Driveway
--   --   Sod
--   --   Finish Electrical Trim Out 8/1
--   --   Water stream on hardwood by slider
--   --   Set handrails 8/1
--   --   Kate to put blue tape on floor scratches- TJ to fix?
--   --   Change batteries in alarms
--   --   Cleaning tile
--   --   Finish poly on stairs 8/1
--   --   Need vanity three light for upstairs hall bathroom and missing about 15 bulbs
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Windows & Doors (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)       patio done; front stoop needed
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
-- -- Exterior Vinyl (0) *        K: 6/20 in process
-- -- Insulation (2)      
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *       
-- -- Paint 1 (1)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Setting cabinets Tues, May 24;
-- -- Granite Installation (1) *        June 8
-- -- Interior Trim - Install (3)       K: 7/11- in process-STILL
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       K: finish tile in laundry
-- -- Paint 2 (3)       K: 7/21-24
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       K: 7/25
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3)       K: in process
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       K: finishing 7/25-26
-- -- Install Appliances (0) *        Needs to be installed
-- -- Carpet (2)       Install 7/27
-- -- Inspection (Final Building) (2) *        Friday, July 29
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Sat/Sun July 30/31
-- -- Certificate of Occupancy (1) *       
-- -- Buyer Walk Through (1)       Thursday, August 4