ADDR
- 103  ::  2232 Lapis Lane
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Apr 29      Ratified Contract? (0)      
Tue    Apr 29      $2500 Deposit Received (0)      
Tue    Apr 29      Association Packet Requested (0)      
Tue    Apr 29      Association Packet Received (0)      
Tue    Apr 29      Selections Meeting (0)      
Tue    Apr 29      Selections Sheet Signed (0)      
Tue    Apr 29      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Apr 29      Deposit For Upgrades Received (0)      
Tue    Apr 29      Inspection (Concrete Wall) (1)      
Wed    Apr 30      Inspection (Conduit Under Slab) (1)      
Thu    May 1      Inspection (Drain Tile) (0)      
Thu    May 1      Settlement Agent Confirmed (0)      
Thu    May 1      Order Tubs / Showers (0)      
Thu    May 1      Framing II (8)      
Tue    May 13      Framing III (8) *       
Fri    May 23      Verify Window & Roof Structure (0)      
Fri    May 23      Install Stairs (0)      
Fri    May 23      House Number and Status in Window (0)      
Fri    May 23      Order Appliances (0)      
Fri    May 23      Patio (0)      
Fri    May 23      Rough In Microwave Vent (0)      
Fri    May 23      Inspection (Rough In Plumbing) (1)      
Mon    May 26      Inspection (Rough In Electric) (1)      
Tue    May 27      Inspection (Deck Piers) (0)      
Tue    May 27      Inspection (Framing) (1) *       
Wed    May 28      Exterior Stone (0)      
Wed    May 28      Set Electric Meter (0) *       
Wed    May 28      Inspection (Main Water Line) (0)      
Wed    May 28      Loan Approval (0)      
Wed    May 28      Deed Preparation (0)      
Wed    May 28      Garage Door (0) *       
Wed    May 28      Mailbox (0)      
Wed    May 28      Order Plumbing / Lighting Fixtures (0)      
Wed    May 28      Interior Trim - Paint (1)      
Thu    May 29      Cover Floors (1)      
Fri    May 30      Deliver Plumbing / Lighting Fixtures (0)      
Fri    May 30      Shoe Moulding (0)      
Fri    May 30      Set Water Meter (0) *       
Fri    May 30      Ceiling Fans (0)      
Fri    May 30      Blower Door Test (1)      
Mon    Jun 2      Paint 3 (2) *       
Wed    Jun 4      Appraiser Confirms Construction Completion (0)      
Wed    Jun 4      Inspection (Final HVAC) (1)      
Thu    Jun 5      Inspection (Final Plumbing) (1)      
Fri    Jun 6      Inspection (Final Electric) (1)      
Mon    Jun 9      Stain Hardwood Stairs (1)      
Tue    Jun 10      C.O. to Lender (0)      
Tue    Jun 10      Schedule Closing (0)      
Tue    Jun 10      Payment for Upgrades (0)      
Tue    Jun 10      Keys to Settlement Agent (0)      
Tue    Jun 10      Review Settlement Statement (0)      
Tue    Jun 10      Jerry Signs Closing Documents (0)      
Tue    Jun 10      Request Trash Tote From POA Manager (0)      
Tue    Jun 10      Closing (1)      
Wed    Jun 11      Remove Coded Lockbox (0)      
--   --   Squeak (give) in floor by powder bath
--   --   Grout?
--   --   Please cover granite
--   --   Driveway
--   --   Sod
--   --   Finish Electrical Trim Out 8/1
--   --   Water stream on hardwood by slider
--   --   Set handrails 8/1
--   --   Kate to put blue tape on floor scratches- TJ to fix?
--   --   Change batteries in alarms
--   --   Cleaning tile
--   --   Finish poly on stairs 8/1
--   --   Need vanity three light for upstairs hall bathroom and missing about 15 bulbs
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Windows & Doors (0) *       
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *        patio done; front stoop needed
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
-- -- Exterior Vinyl (0) *        K: 6/20 in process
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *       
-- -- Paint 1 (1)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Setting cabinets Tues, May 24;
-- -- Granite Installation (1) *        June 8
-- -- Interior Trim - Install (3) *        K: 7/11- in process-STILL
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       K: finish tile in laundry
-- -- Paint 2 (3)       K: 7/21-24
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        K: 7/25
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3)       K: in process
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       K: finishing 7/25-26
-- -- Install Appliances (0) *        Needs to be installed
-- -- Carpet (2)       Install 7/27
-- -- Inspection (Final Building) (2) *        Friday, July 29
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Sat/Sun July 30/31
-- -- Certificate of Occupancy (1) *       
-- -- Buyer Walk Through (1)       Thursday, August 4