ADDR
- 103  ::  2232 Lapis Lane
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Fri    Sep 20      Ratified Contract? (0)      
Fri    Sep 20      $2500 Deposit Received (0)      
Fri    Sep 20      Association Packet Requested (0)      
Fri    Sep 20      Association Packet Received (0)      
Fri    Sep 20      Selections Meeting (0)      
Fri    Sep 20      Selections Sheet Signed (0)      
Fri    Sep 20      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Fri    Sep 20      Deposit For Upgrades Received (0)      
Fri    Sep 20      Inspection (Concrete Wall) (1)      
Mon    Sep 23      Inspection (Conduit Under Slab) (1)      
Tue    Sep 24      Inspection (Drain Tile) (0)      
Tue    Sep 24      Settlement Agent Confirmed (0)      
Tue    Sep 24      Order Tubs / Showers (0)      
Tue    Sep 24      Framing II (8)      
Fri    Oct 4      Framing III (8)      
Wed    Oct 16      Verify Window & Roof Structure (0)      
Wed    Oct 16      Install Stairs (0)      
Wed    Oct 16      House Number and Status in Window (0)      
Wed    Oct 16      Order Appliances (0)      
Wed    Oct 16      Patio (0)      
Wed    Oct 16      Rough In Microwave Vent (0)      
Wed    Oct 16      Inspection (Rough In Plumbing) (1)      
Thu    Oct 17      Inspection (Rough In Electric) (1)      
Fri    Oct 18      Inspection (Deck Piers) (0)      
Fri    Oct 18      Inspection (Framing) (1)      
Mon    Oct 21      Exterior Stone (0)      
Mon    Oct 21      Set Electric Meter (0)      
Mon    Oct 21      Inspection (Main Water Line) (0)      
Mon    Oct 21      Loan Approval (0)      
Mon    Oct 21      Deed Preparation (0)      
Mon    Oct 21      Garage Door (0)      
Mon    Oct 21      Mailbox (0)      
Mon    Oct 21      Order Plumbing / Lighting Fixtures (0)      
Mon    Oct 21      Interior Trim - Paint (1)      
Tue    Oct 22      Cover Floors (1)      
Wed    Oct 23      Deliver Plumbing / Lighting Fixtures (0)      
Wed    Oct 23      Shoe Moulding (0)      
Wed    Oct 23      Set Water Meter (0)      
Wed    Oct 23      Ceiling Fans (0)      
Wed    Oct 23      Blower Door Test (1)      
Thu    Oct 24      Paint 3 (2)      
Mon    Oct 28      Appraiser Confirms Construction Completion (0)      
Mon    Oct 28      Inspection (Final HVAC) (1)      
Tue    Oct 29      Inspection (Final Plumbing) (1)      
Wed    Oct 30      Inspection (Final Electric) (1)      
Thu    Oct 31      Stain Hardwood Stairs (1)      
Fri    Nov 1      C.O. to Lender (0)      
Fri    Nov 1      Schedule Closing (0)      
Fri    Nov 1      Payment for Upgrades (0)      
Fri    Nov 1      Keys to Settlement Agent (0)      
Fri    Nov 1      Review Settlement Statement (0)      
Fri    Nov 1      Jerry Signs Closing Documents (0)      
Fri    Nov 1      Request Trash Tote From POA Manager (0)      
Fri    Nov 1      Closing (1)      
Mon    Nov 4      Remove Coded Lockbox (0)      
--   --   Squeak (give) in floor by powder bath
--   --   Grout?
--   --   Please cover granite
--   --   Driveway
--   --   Sod
--   --   Finish Electrical Trim Out 8/1
--   --   Water stream on hardwood by slider
--   --   Set handrails 8/1
--   --   Kate to put blue tape on floor scratches- TJ to fix?
--   --   Change batteries in alarms
--   --   Cleaning tile
--   --   Finish poly on stairs 8/1
--   --   Need vanity three light for upstairs hall bathroom and missing about 15 bulbs
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1)      
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Windows & Doors (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)       patio done; front stoop needed
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
-- -- Exterior Vinyl (0)       K: 6/20 in process
-- -- Insulation (2)      
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4)      
-- -- Drywall (Tape, Block, Skim, Sand) (6)      
-- -- Paint 1 (1)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2)       Setting cabinets Tues, May 24;
-- -- Granite Installation (1)       June 8
-- -- Interior Trim - Install (3)       K: 7/11- in process-STILL
-- -- Luxury Vinyl Plank (3)      
-- -- Luxury Vinyl Tile (0)       K: finish tile in laundry
-- -- Paint 2 (3)       K: 7/21-24
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       K: 7/25
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3)       K: in process
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       K: finishing 7/25-26
-- -- Install Appliances (0)       Needs to be installed
-- -- Carpet (2)       Install 7/27
-- -- Inspection (Final Building) (2)       Friday, July 29
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Sat/Sun July 30/31
-- -- Certificate of Occupancy (1)      
-- -- Buyer Walk Through (1)       Thursday, August 4