ADDR
- 105  ::  2236 Lapis Lane
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   CODED LOCKBOX = 2432
Tue    Apr 29      Ratified Contract? (0)      
Tue    Apr 29      $2500 Deposit Received (0)      
Tue    Apr 29      Association Packet Requested (0)      
Tue    Apr 29      Association Packet Received (0)      
Tue    Apr 29      Selections Meeting (0)      
Tue    Apr 29      Selections Sheet Signed (0)      
Tue    Apr 29      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Apr 29      Deposit For Upgrades Received (0)      
Tue    Apr 29      Inspection (Concrete Wall) (1)      
Wed    Apr 30      Inspection (Conduit Under Slab) (1)      
Thu    May 1      Inspection (Drain Tile) (0)      
Thu    May 1      Settlement Agent Confirmed (0)      
Thu    May 1      Order Tubs / Showers (0)      
Thu    May 1      Verify Window & Roof Structure (0)      
Thu    May 1      Install Stairs (0)      
Thu    May 1      House Number and Status in Window (0)      
Thu    May 1      Order Appliances (0)      
Thu    May 1      Patio (0)      
Thu    May 1      Rough In Microwave Vent (0)      
Thu    May 1      Inspection (Rough In Plumbing) (1)      
Fri    May 2      Inspection (Rough In Electric) (1)      
Mon    May 5      Inspection (Deck Piers) (0)      
Mon    May 5      Inspection (Framing) (1) *       
Tue    May 6      Exterior Stone (0)      
Tue    May 6      Set Electric Meter (0) *       
Tue    May 6      Inspection (Main Water Line) (0)      
Tue    May 6      Loan Approval (0)      
Tue    May 6      Deed Preparation (0)      
Tue    May 6      Garage Door (0) *       
Tue    May 6      Mailbox (0)      
Tue    May 6      Order Plumbing / Lighting Fixtures (0)      
Tue    May 6      Interior Trim - Paint (1)      
Wed    May 7      Deliver Plumbing / Lighting Fixtures (0)      
Wed    May 7      Shoe Moulding (0)      
Wed    May 7      Set Water Meter (0) *       
Wed    May 7      Ceiling Fans (0)      
Wed    May 7      Blower Door Test (1)      
Thu    May 8      Paint 3 (2) *       
Mon    May 12      Appraiser Confirms Construction Completion (0)      
Mon    May 12      Inspection (Final HVAC) (1)      
Tue    May 13      Inspection (Final Plumbing) (1)      
Wed    May 14      Inspection (Final Electric) (1)      
Thu    May 15      Stain Hardwood Stairs (1)      
Fri    May 16      C.O. to Lender (0)      
Fri    May 16      Schedule Closing (0)      
Fri    May 16      Payment for Upgrades (0)      
Fri    May 16      Keys to Settlement Agent (0)      
Fri    May 16      Review Settlement Statement (0)      
Fri    May 16      Jerry Signs Closing Documents (0)      
Fri    May 16      Request Trash Tote From POA Manager (0)      
Fri    May 16      Closing (1)      
Mon    May 19      Remove Coded Lockbox (0)      
--   --   Please cover granite
--   --   Clean garage
--   --   Touch up paint
--   --   Hall bath tile at door?
--   --   Master bath tile?
--   --   Ceiling fans-flip blades to darker side
--   --   Big squeak in floor outside second bedroom at top of stairs
--   --   Trim- consistently held up too high for carpet- discuss with Mitch
--   --   Trim in foyer
--   --   Up bedroom holes in trim to be filled painted
--   --   Install last two light fixtures
--   --   Vent cover in dining room
--   --   Tile/carpet
--   --   2 vent covers in living room
--   --   Eric reattach carpet
--   --   Hole at landing wall- fill and paint
--   --   Washer & Dryer
--   --   Need vinyl under stairs
--   --   Remove furniture
--   --   Paint touch up
--   --   Cleaning
--   --   Final walk through
--   --   Need mailbox keys
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Windows & Doors (0) *       
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *        patio done; front stoop needed
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       Tuesday;
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        K: in process- asked me to order more materials
-- -- Paint 1 (1)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Delivery on 8/12, install 8/15
-- -- Granite Installation (1) *        Installed Sept 1
-- -- Interior Trim - Install (3) *        Mitch all week
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       8/6: tile in process (Jesse)
-- -- Paint 2 (3)       9/22 finishing paint
-- -- Cover Floors (1)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        Nearly complete
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3)       In process
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)      
-- -- Install Appliances (0) *        Sep 28
-- -- Carpet (2)       Sept 30
-- -- Inspection (Final Building) (2) *       
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Later this week and next weekend
-- -- Certificate of Occupancy (1) *       
-- -- Buyer Walk Through (1)