ADDR
- 105  ::  2236 Lapis Lane
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   CODED LOCKBOX = 2432
Fri    Sep 20      Ratified Contract? (0)      
Fri    Sep 20      $2500 Deposit Received (0)      
Fri    Sep 20      Association Packet Requested (0)      
Fri    Sep 20      Association Packet Received (0)      
Fri    Sep 20      Selections Meeting (0)      
Fri    Sep 20      Selections Sheet Signed (0)      
Fri    Sep 20      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Fri    Sep 20      Deposit For Upgrades Received (0)      
Fri    Sep 20      Inspection (Concrete Wall) (1)      
Mon    Sep 23      Inspection (Conduit Under Slab) (1)      
Tue    Sep 24      Inspection (Drain Tile) (0)      
Tue    Sep 24      Settlement Agent Confirmed (0)      
Tue    Sep 24      Order Tubs / Showers (0)      
Tue    Sep 24      Verify Window & Roof Structure (0)      
Tue    Sep 24      Install Stairs (0)      
Tue    Sep 24      House Number and Status in Window (0)      
Tue    Sep 24      Order Appliances (0)      
Tue    Sep 24      Patio (0)      
Tue    Sep 24      Rough In Microwave Vent (0)      
Tue    Sep 24      Inspection (Rough In Plumbing) (1)      
Wed    Sep 25      Inspection (Rough In Electric) (1)      
Thu    Sep 26      Inspection (Deck Piers) (0)      
Thu    Sep 26      Inspection (Framing) (1)      
Fri    Sep 27      Exterior Stone (0)      
Fri    Sep 27      Set Electric Meter (0)      
Fri    Sep 27      Inspection (Main Water Line) (0)      
Fri    Sep 27      Loan Approval (0)      
Fri    Sep 27      Deed Preparation (0)      
Fri    Sep 27      Garage Door (0)      
Fri    Sep 27      Mailbox (0)      
Fri    Sep 27      Order Plumbing / Lighting Fixtures (0)      
Fri    Sep 27      Interior Trim - Paint (1)      
Mon    Sep 30      Deliver Plumbing / Lighting Fixtures (0)      
Mon    Sep 30      Shoe Moulding (0)      
Mon    Sep 30      Set Water Meter (0)      
Mon    Sep 30      Ceiling Fans (0)      
Mon    Sep 30      Blower Door Test (1)      
Tue    Oct 1      Paint 3 (2)      
Thu    Oct 3      Appraiser Confirms Construction Completion (0)      
Thu    Oct 3      Inspection (Final HVAC) (1)      
Fri    Oct 4      Inspection (Final Plumbing) (1)      
Mon    Oct 7      Inspection (Final Electric) (1)      
Tue    Oct 8      Stain Hardwood Stairs (1)      
Wed    Oct 9      C.O. to Lender (0)      
Wed    Oct 9      Schedule Closing (0)      
Wed    Oct 9      Payment for Upgrades (0)      
Wed    Oct 9      Keys to Settlement Agent (0)      
Wed    Oct 9      Review Settlement Statement (0)      
Wed    Oct 9      Jerry Signs Closing Documents (0)      
Wed    Oct 9      Request Trash Tote From POA Manager (0)      
Wed    Oct 9      Closing (1)      
Thu    Oct 10      Remove Coded Lockbox (0)      
--   --   Please cover granite
--   --   Clean garage
--   --   Touch up paint
--   --   Hall bath tile at door?
--   --   Master bath tile?
--   --   Ceiling fans-flip blades to darker side
--   --   Big squeak in floor outside second bedroom at top of stairs
--   --   Trim- consistently held up too high for carpet- discuss with Mitch
--   --   Trim in foyer
--   --   Up bedroom holes in trim to be filled painted
--   --   Install last two light fixtures
--   --   Vent cover in dining room
--   --   Tile/carpet
--   --   2 vent covers in living room
--   --   Eric reattach carpet
--   --   Hole at landing wall- fill and paint
--   --   Washer & Dryer
--   --   Need vinyl under stairs
--   --   Remove furniture
--   --   Paint touch up
--   --   Cleaning
--   --   Final walk through
--   --   Need mailbox keys
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1)      
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Framing II (8)      
-- -- Framing III (8)      
-- -- Windows & Doors (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)       patio done; front stoop needed
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       Tuesday;
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
-- -- Exterior Vinyl (0)      
-- -- Insulation (2)      
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4)      
-- -- Drywall (Tape, Block, Skim, Sand) (6)       K: in process- asked me to order more materials
-- -- Paint 1 (1)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2)       Delivery on 8/12, install 8/15
-- -- Granite Installation (1)       Installed Sept 1
-- -- Interior Trim - Install (3)       Mitch all week
-- -- Luxury Vinyl Plank (3)      
-- -- Luxury Vinyl Tile (0)       8/6: tile in process (Jesse)
-- -- Paint 2 (3)       9/22 finishing paint
-- -- Cover Floors (1)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       Nearly complete
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3)       In process
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)      
-- -- Install Appliances (0)       Sep 28
-- -- Carpet (2)       Sept 30
-- -- Inspection (Final Building) (2)      
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Later this week and next weekend
-- -- Certificate of Occupancy (1)      
-- -- Buyer Walk Through (1)