- 105  ::  2236 Lapis Lane
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   CODED LOCKBOX = 2432
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Order Tubs / Showers (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Install Stairs (0)      
Mon    Dec 2      House Number and Status in Window (0)      
Mon    Dec 2      Order Appliances (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Garage Door (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Order Plumbing / Lighting Fixtures (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Deliver Plumbing / Lighting Fixtures (0)      
Fri    Dec 6      Shoe Moulding (0)      
Fri    Dec 6      Set Water Meter (0)      
Fri    Dec 6      Ceiling Fans (0)      
Fri    Dec 6      Blower Door Test (1)      
Mon    Dec 9      Paint 3 (2) *       
Wed    Dec 11      Appraiser Confirms Construction Completion (0)      
Wed    Dec 11      Inspection (Final HVAC) (1)      
Thu    Dec 12      Inspection (Final Plumbing) (1)      
Fri    Dec 13      Inspection (Final Electric) (1)      
Mon    Dec 16      Stain Hardwood Stairs (1)      
Tue    Dec 17      C.O. to Lender (0)      
Tue    Dec 17      Schedule Closing (0)      
Tue    Dec 17      Payment for Upgrades (0)      
Tue    Dec 17      Keys to Settlement Agent (0)      
Tue    Dec 17      Review Settlement Statement (0)      
Tue    Dec 17      Jerry Signs Closing Documents (0)      
Tue    Dec 17      Request Trash Tote From POA Manager (0)      
Tue    Dec 17      Closing (1)      
Wed    Dec 18      Remove Coded Lockbox (0)      
--   --   Please cover granite
--   --   Clean garage
--   --   Touch up paint
--   --   Hall bath tile at door?
--   --   Master bath tile?
--   --   Ceiling fans-flip blades to darker side
--   --   Big squeak in floor outside second bedroom at top of stairs
--   --   Trim- consistently held up too high for carpet- discuss with Mitch
--   --   Trim in foyer
--   --   Up bedroom holes in trim to be filled painted
--   --   Install last two light fixtures
--   --   Vent cover in dining room
--   --   Tile/carpet
--   --   2 vent covers in living room
--   --   Eric reattach carpet
--   --   Hole at landing wall- fill and paint
--   --   Washer & Dryer
--   --   Need vinyl under stairs
--   --   Remove furniture
--   --   Paint touch up
--   --   Cleaning
--   --   Final walk through
--   --   Need mailbox keys
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Windows & Doors (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)       patio done; front stoop needed
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       Tuesday;
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2)      
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        K: in process- asked me to order more materials
-- -- Paint 1 (1)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Delivery on 8/12, install 8/15
-- -- Granite Installation (1) *        Installed Sept 1
-- -- Interior Trim - Install (3)       Mitch all week
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       8/6: tile in process (Jesse)
-- -- Paint 2 (3)       9/22 finishing paint
-- -- Cover Floors (1)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       Nearly complete
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3)       In process
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)      
-- -- Install Appliances (0) *        Sep 28
-- -- Carpet (2)       Sept 30
-- -- Inspection (Final Building) (2) *       
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Later this week and next weekend
-- -- Certificate of Occupancy (1) *       
-- -- Buyer Walk Through (1)