Glue off of transition strip in pantry |
Kelly |
|
-- |
-- |
Put plugs in patio door |
Isaac |
|
-- |
-- |
Small Nick in hall bath shower tub repair |
Mindy |
|
-- |
-- |
Access panel in loft walk in |
Osbaldo |
|
-- |
-- |
Need new weather stripping at front door |
Osbaldo - Friday (and back door) |
|
-- |
-- |
Sidewalk hole? |
Tom |
|
-- |
-- |
CODED LOCKBOX = 7134 |
|
|
-- |
-- |
Seal around duct in furnace room at ceiling |
Osbaldo |
|
-- |
-- |
House and Mailbox Keys? |
|
|
Thu |
Nov 28 |
Ratified Contract? (0) |
|
|
Thu |
Nov 28 |
$2500 Deposit Received (0) |
|
|
Thu |
Nov 28 |
Association Packet Requested (0) |
|
|
Thu |
Nov 28 |
Association Packet Received (0) |
|
|
Thu |
Nov 28 |
Selections Meeting (0) |
|
|
Thu |
Nov 28 |
Selections Sheet Signed (0) |
|
|
Thu |
Nov 28 |
Amendment for Upgrades (B,S,L,T,BCP) (0) |
|
|
Thu |
Nov 28 |
Deposit For Upgrades Received (0) |
|
|
Thu |
Nov 28 |
Inspection (Concrete Wall) (1) |
|
|
Fri |
Nov 29 |
Inspection (Conduit Under Slab) (1) |
|
|
Mon |
Dec 2 |
Inspection (Drain Tile) (0) |
|
|
Mon |
Dec 2 |
Settlement Agent Confirmed (0) |
|
|
Mon |
Dec 2 |
Order Tubs / Showers (0) |
|
|
Mon |
Dec 2 |
Verify Window & Roof Structure (0) |
|
|
Mon |
Dec 2 |
Install Stairs (0) |
|
|
Mon |
Dec 2 |
House Number and Status in Window (0) |
|
|
Mon |
Dec 2 |
Order Appliances (0) |
|
|
Mon |
Dec 2 |
Patio (0) |
|
|
Mon |
Dec 2 |
Rough In Microwave Vent (0) |
|
|
Mon |
Dec 2 |
Inspection (Rough In Plumbing) (1) |
|
|
Tue |
Dec 3 |
Inspection (Rough In Electric) (1) |
|
|
Wed |
Dec 4 |
Inspection (Deck Piers) (0) |
|
|
Wed |
Dec 4 |
Inspection (Framing) (1) |
|
|
Thu |
Dec 5 |
Exterior Stone (0) |
|
|
Thu |
Dec 5 |
Set Electric Meter (0) |
|
|
Thu |
Dec 5 |
Inspection (Main Water Line) (0) |
|
|
Thu |
Dec 5 |
Loan Approval (0) |
|
|
Thu |
Dec 5 |
Deed Preparation (0) |
|
|
Thu |
Dec 5 |
Garage Door (0) |
|
|
Thu |
Dec 5 |
Mailbox (0) |
|
|
Thu |
Dec 5 |
Order Plumbing / Lighting Fixtures (0) |
|
|
Thu |
Dec 5 |
Interior Trim - Paint (1) |
|
|
Fri |
Dec 6 |
Deliver Plumbing / Lighting Fixtures (0) |
|
|
Fri |
Dec 6 |
Shoe Moulding (0) |
|
|
Fri |
Dec 6 |
Set Water Meter (0) |
|
|
Fri |
Dec 6 |
Ceiling Fans (0) |
|
|
Fri |
Dec 6 |
Blower Door Test (1) |
|
|
Mon |
Dec 9 |
Paint 3 (2) * |
|
|
Wed |
Dec 11 |
Appraiser Confirms Construction Completion (0) |
|
|
Wed |
Dec 11 |
Inspection (Final HVAC) (1) |
|
|
Thu |
Dec 12 |
Inspection (Final Plumbing) (1) |
|
|
Fri |
Dec 13 |
Inspection (Final Electric) (1) |
|
|
Mon |
Dec 16 |
Stain Hardwood Stairs (1) |
|
|
Tue |
Dec 17 |
Cleaning (1) |
Sat/Sun |
|
Wed |
Dec 18 |
C.O. to Lender (0) |
|
|
Wed |
Dec 18 |
Schedule Closing (0) |
|
|
Wed |
Dec 18 |
Payment for Upgrades (0) |
|
|
Wed |
Dec 18 |
Keys to Settlement Agent (0) |
|
|
Wed |
Dec 18 |
Review Settlement Statement (0) |
|
|
Wed |
Dec 18 |
Jerry Signs Closing Documents (0) |
|
|
Wed |
Dec 18 |
Request Trash Tote From POA Manager (0) |
|
|
Wed |
Dec 18 |
Closing (1) |
TUESDAY, MAY 23, 2017 |
|
Thu |
Dec 19 |
Remove Coded Lockbox (0) |
|
|
|
-- |
-- |
Country Beige Vinyl, Green Door |
|
|
-- |
-- |
Follow up with realtor on hall shower decision |
|
|
-- |
-- |
Buyer wants access panel in closet |
Left note on site after door had been changed |
|
-- |
-- |
Install shower through patio door |
Tuesday, February 14 |
|
-- |
-- |
Add 2 additional lengths of fence on right side to match 111 |
Week of 5/8- Tom please confirm with Premier |
|
-- |
-- |
Caulk side splash in hall bathroom |
|
|
-- |
-- |
Need to scrape and sweep the floors and get out all drywall materials so Mitch can begin trim |
|
|
-- |
-- |
Cranberry red front door |
|
|
-- |
-- |
Would like to close on May 12, 2017 |
|
|
-- |
-- |
Key stuck in front door |
|
|
-- |
-- |
Laminate countertop against wall in dining room? |
|
|
-- |
-- |
Drywall needed in pantry |
|
|
-- |
-- |
Drywall needed upstairs??? |
|
|
-- |
-- |
Interior Trim in Bathrooms |
|
|
-- |
-- |
Shoemold over weekend or Monday 8th |
Thu, May 11 |
|
-- |
-- |
Paint final coat 5/6-5/7 |
|
|
-- |
-- |
Paint 3- 5/9-5/10 |
|
|
-- |
-- |
Transition strip needed between kitchen tile and pantry vinyl |
Mindy to call Eric |
|
-- |
-- |
Final paint |
Fri, May 12 |
|
-- |
-- |
Hoping to close by Friday 5/19...or Monday 5/21??? |
|
|
-- |
-- |
Cypress Trees |
Osbaldo |
|
-- |
-- |
Fire extinguisher |
Osbaldo |
|
-- |
-- |
HVAC - grill covers, condensate line |
|
|
-- |
-- |
Push button locks |
|
|
-- |
-- |
Storm Door |
Osbaldo - Friday |
|
-- |
-- |
Appraiser Re-Visit |
Sandy Martin -- likely Wed, May 17 |
|
-- |
-- |
Insulate door to attic |
Osbaldo |
|
-- |
-- |
Install screens and screen on patio door |
Kelly |
|
-- |
-- |
Install storm door |
|
|
-- |
-- |
Install electronic deadbolt |
Osbaldo |
|
-- |
-- |
Shelving in pantry |
Ron Thursday morning |
|
-- |
-- |
Install. Sanity |
|
|
-- |
-- |
Install vanity |
Mindy |
|
-- |
-- |
Light bulbs in dining chandelier |
Osbaldo - Friday |
|
-- |
-- |
Missing bulbs in master bath |
Osbaldo - Friday |
|
-- |
-- |
Cut hole in toe kick of loft kitchen |
Osbaldo - Friday |
|
-- |
-- |
Washer drain |
|
|
-- |
-- |
Receptacle on inside of closetall |
Harry |
|
-- |
-- |
Snap light in pantry instead of flush mont |
Amy, Harry |
|
-- |
-- |
Leave closing booklet Mindy |
|
|
-- |
-- |
Front door seal top left corner |
Osbaldo - Friday |
|
-- |
-- |
Closing Tuesday at 10AM |
|
|
-- |
-- |
Building Permit (30) |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) |
|
|
-- |
-- |
Order Windows & Doors (0) |
|
|
-- |
-- |
Stake Out Home (1) |
|
|
-- |
-- |
Excavate (2) |
|
|
-- |
-- |
Inspection (Footers) (1) |
|
|
-- |
-- |
Pour Footers (1) |
|
|
-- |
-- |
Set Forms (2) |
|
|
-- |
-- |
Pour Foundation Walls (1) |
|
|
-- |
-- |
Plumb Slab (2) |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
-- |
-- |
Prepare Slab (1) |
|
|
-- |
-- |
Inspection (Slab) (1) |
|
|
-- |
-- |
Pour Slab (1) * |
Monday May 16 |
|
-- |
-- |
Framing I (9) |
|
|
-- |
-- |
Order Steps (0) |
|
|
-- |
-- |
Framing II (8) |
|
|
-- |
-- |
Framing III (8) * |
|
|
-- |
-- |
Windows & Doors (0) |
|
|
-- |
-- |
Roofing (0) |
|
|
-- |
-- |
Order Cabinets (0) |
|
|
-- |
-- |
Deck (0) |
|
|
-- |
-- |
Gutters (0) |
|
|
-- |
-- |
Driveway (0) |
|
|
-- |
-- |
Privacy Divider / Fence (0) |
Extend fence by two lengths |
|
-- |
-- |
Sod / Seed / Landscaping (0) |
Seed backyard and provide new landscape hedge |
|
-- |
-- |
HVAC Rough In (4) |
2/13 in process |
|
-- |
-- |
Inspection (Rough In HVAC) (1) |
|
|
-- |
-- |
Plumbing Rough In (4) |
2/13 in process-waiting on hall shower |
|
-- |
-- |
Electric Rough In (4) |
2/20 - Harry in process |
|
-- |
-- |
Exterior Vinyl (0) * |
|
|
-- |
-- |
Insulation (2) |
|
|
-- |
-- |
Inspection (Insulation) (1) |
|
|
-- |
-- |
Inspection (Electric Service) (0) |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) |
|
|
-- |
-- |
Order Interior Doors & Trim (0) |
|
|
-- |
-- |
Drywall (Hang) (4) * |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
Complete by 3/14 |
|
-- |
-- |
Paint 1 (1) |
3/15 |
|
-- |
-- |
House Numbers (0) |
|
|
-- |
-- |
Cabinet Installation (2) * |
Delivered Thurs, Mar 23, Installed Mon, Mar 27 |
|
-- |
-- |
Granite Installation (1) * |
4/10 |
|
-- |
-- |
Interior Trim - Install (3) |
Done except for bathrooms- waiting on grout will finish 4/25 |
|
-- |
-- |
Luxury Vinyl Plank (3) * |
|
|
-- |
-- |
Luxury Vinyl Tile (0) |
4/24 all needs to be grouted |
|
-- |
-- |
Paint 2 (3) |
Thursday 4/27 |
|
-- |
-- |
Cover Floors (1) |
TODAY 5/3 |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) |
Week of May 1 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) |
|
|
-- |
-- |
Electric Trim Out (3) |
By 5/12 |
|
-- |
-- |
HVAC Trim Out (1) |
By Thu, Apr 27 |
|
-- |
-- |
Plumbing Trim Out (2) |
5/9 in process |
|
-- |
-- |
Install Appliances (0) * |
5/11- confirm with Amy |
|
-- |
-- |
Carpet (2) |
5/8 |
|
-- |
-- |
Inspection (Final Building) (2) * |
Wed, May 17 |
|
-- |
-- |
Pre Walk Through (0) |
5/11 @10:30 |
|
-- |
-- |
Certificate of Occupancy (1) * |
|
|
-- |
-- |
Buyer Walk Through (1) |
Wednesday 5/17? |
|