ADDR
- 112  ::  2247 Lapis Lane
[ BUILD: 16090091 ]       [ PLUMB: 16040134 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Glue off of transition strip in pantry Kelly
--   --   Put plugs in patio door Isaac
--   --   Small Nick in hall bath shower tub repair Mindy
--   --   Access panel in loft walk in Osbaldo
--   --   Need new weather stripping at front door Osbaldo - Friday (and back door)
--   --   Sidewalk hole? Tom
--   --   CODED LOCKBOX = 7134
--   --   Seal around duct in furnace room at ceiling Osbaldo
--   --   House and Mailbox Keys?
Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Inspection (Concrete Wall) (1)      
Wed    Dec 17      Inspection (Conduit Under Slab) (1)      
Thu    Dec 18      Inspection (Drain Tile) (0)      
Thu    Dec 18      Settlement Agent Confirmed (0)      
Thu    Dec 18      Order Tubs / Showers (0)      
Thu    Dec 18      Verify Window & Roof Structure (0)      
Thu    Dec 18      Install Stairs (0) *       
Thu    Dec 18      House Number and Status in Window (0)      
Thu    Dec 18      Order Appliances (0)      
Thu    Dec 18      Patio (0)      
Thu    Dec 18      Rough In Microwave Vent (0)      
Thu    Dec 18      Inspection (Rough In Plumbing) (1)      
Fri    Dec 19      Inspection (Rough In Electric) (1)      
Mon    Dec 22      Inspection (Framing) (1) *       
Tue    Dec 23      Inspection (Deck Piers) (0)      
Tue    Dec 23      Exterior Stone (0)      
Tue    Dec 23      Set Electric Meter (0) *       
Tue    Dec 23      Inspection (Main Water Line) (0)      
Tue    Dec 23      Loan Approval (0)      
Tue    Dec 23      Deed Preparation (0)      
Tue    Dec 23      Garage Door (0)      
Tue    Dec 23      Mailbox (0)      
Tue    Dec 23      Order Plumbing / Lighting Fixtures (0)      
Tue    Dec 23      Interior Trim - Paint (1)      
Wed    Dec 24      Deliver Plumbing / Lighting Fixtures (0)      
Wed    Dec 24      Shoe Moulding (0)      
Wed    Dec 24      Set Water Meter (0) *       
Wed    Dec 24      Ceiling Fans (0)      
Wed    Dec 24      Blower Door Test (1)      
Thu    Dec 25      Paint 3 (2) *       
Mon    Dec 29      Appraiser Confirms Construction Completion (0)      
Mon    Dec 29      Inspection (Final HVAC) (1)      
Tue    Dec 30      Inspection (Final Plumbing) (1)      
Wed    Dec 31      Inspection (Final Electric) (1)      
Thu    Jan 1      Stain Hardwood Stairs (1) *       
Fri    Jan 2      Cleaning (1)       Sat/Sun
Mon    Jan 5      C.O. to Lender (0)      
Mon    Jan 5      Schedule Closing (0)      
Mon    Jan 5      Payment for Upgrades (0)      
Mon    Jan 5      Keys to Settlement Agent (0)      
Mon    Jan 5      Review Settlement Statement (0)      
Mon    Jan 5      Jerry Signs Closing Documents (0)      
Mon    Jan 5      Request Trash Tote From POA Manager (0)      
Mon    Jan 5      Closing (1)       TUESDAY, MAY 23, 2017
Tue    Jan 6      Remove Coded Lockbox (0)      
--   --   Country Beige Vinyl, Green Door
--   --   Follow up with realtor on hall shower decision
--   --   Buyer wants access panel in closet Left note on site after door had been changed
--   --   Install shower through patio door Tuesday, February 14
--   --   Add 2 additional lengths of fence on right side to match 111 Week of 5/8- Tom please confirm with Premier
--   --   Caulk side splash in hall bathroom
--   --   Need to scrape and sweep the floors and get out all drywall materials so Mitch can begin trim
--   --   Cranberry red front door
--   --   Would like to close on May 12, 2017
--   --   Key stuck in front door
--   --   Laminate countertop against wall in dining room?
--   --   Drywall needed in pantry
--   --   Drywall needed upstairs???
--   --   Interior Trim in Bathrooms
--   --   Shoemold over weekend or Monday 8th Thu, May 11
--   --   Paint final coat 5/6-5/7
--   --   Paint 3- 5/9-5/10
--   --   Transition strip needed between kitchen tile and pantry vinyl Mindy to call Eric
--   --   Final paint Fri, May 12
--   --   Hoping to close by Friday 5/19...or Monday 5/21???
--   --   Cypress Trees Osbaldo
--   --   Fire extinguisher Osbaldo
--   --   HVAC - grill covers, condensate line
--   --   Push button locks
--   --   Storm Door Osbaldo - Friday
--   --   Appraiser Re-Visit Sandy Martin -- likely Wed, May 17
--   --   Insulate door to attic Osbaldo
--   --   Install screens and screen on patio door Kelly
--   --   Install storm door
--   --   Install electronic deadbolt Osbaldo
--   --   Shelving in pantry Ron Thursday morning
--   --   Install. Sanity
--   --   Install vanity Mindy
--   --   Light bulbs in dining chandelier Osbaldo - Friday
--   --   Missing bulbs in master bath Osbaldo - Friday
--   --   Cut hole in toe kick of loft kitchen Osbaldo - Friday
--   --   Washer drain
--   --   Receptacle on inside of closetall Harry
--   --   Snap light in pantry instead of flush mont Amy, Harry
--   --   Leave closing booklet Mindy
--   --   Front door seal top left corner Osbaldo - Friday
--   --   Closing Tuesday at 10AM
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *        Monday May 16
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Windows & Doors (0) *       
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *        Extend fence by two lengths
-- -- Sod / Seed / Landscaping (0)       Seed backyard and provide new landscape hedge
-- -- HVAC Rough In (4)       2/13 in process
-- -- Plumbing Rough In (4)       2/13 in process-waiting on hall shower
-- -- Electric Rough In (4)       2/20 - Harry in process
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Complete by 3/14
-- -- Paint 1 (1)       3/15
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Delivered Thurs, Mar 23, Installed Mon, Mar 27
-- -- Granite Installation (1) *        4/10
-- -- Interior Trim - Install (3) *        Done except for bathrooms- waiting on grout will finish 4/25
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       4/24 all needs to be grouted
-- -- Paint 2 (3)       Thursday 4/27
-- -- Cover Floors (1)       TODAY 5/3
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        Week of May 1
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3) *        By 5/12
-- -- HVAC Trim Out (1) *        By Thu, Apr 27
-- -- Plumbing Trim Out (2) *        5/9 in process
-- -- Install Appliances (0) *        5/11- confirm with Amy
-- -- Carpet (2)       5/8
-- -- Inspection (Final Building) (2) *        Wed, May 17
-- -- Pre Walk Through (0)       5/11 @10:30
-- -- Certificate of Occupancy (1) *       
-- -- Buyer Walk Through (1) *        Wednesday 5/17?