- 113  ::  2245 Lapis Lane
[ BUILD: 16020090 ]       [ PLUMB: 16040133 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Tenant = Tim Johnson @ 803-760-3497
--   --   Paint at drywall patch on landing Tom will call Isaac
--   --   Hot water side of sink faucet does not work Kate will call Bobby
Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Inspection (Concrete Wall) (1)      
Wed    Dec 17      Inspection (Conduit Under Slab) (1)      
Thu    Dec 18      Inspection (Drain Tile) (0)      
Thu    Dec 18      Settlement Agent Confirmed (0)      
Thu    Dec 18      Verify Window & Roof Structure (0)      
Thu    Dec 18      Patio (0)      
Thu    Dec 18      Rough In Microwave Vent (0)      
Thu    Dec 18      Inspection (Rough In Plumbing) (1)      
Fri    Dec 19      Inspection (Rough In Electric) (1)      
Mon    Dec 22      Inspection (Framing) (1) *       
Tue    Dec 23      Inspection (Deck Piers) (0)      
Tue    Dec 23      Exterior Stone (0)      
Tue    Dec 23      Set Electric Meter (0) *       
Tue    Dec 23      Inspection (Main Water Line) (0)      
Tue    Dec 23      Loan Approval (0)      
Tue    Dec 23      Deed Preparation (0)      
Tue    Dec 23      Mailbox (0)      
Tue    Dec 23      Interior Trim - Paint (1)      
Wed    Dec 24      Ceiling Fans (0)      
Wed    Dec 24      Blower Door Test (1)      
Thu    Dec 25      Inspection (Final HVAC) (1)      
Fri    Dec 26      Inspection (Final Plumbing) (1)      
Mon    Dec 29      Inspection (Final Electric) (1)      
Tue    Dec 30      Stain Hardwood Stairs (1) *       
Wed    Dec 31      Request Trash Tote From POA Manager (0)      
--   --   Bone Vinyl, Red door Need to change door color to yellow
--   --   Potential framing changes in hall bathroom to accommodate for 36 inch vanity
--   --   Finish installing bathroom cabinetry Osbaldo
--   --   Hardware to be installed on cabinetry Osbaldo to check
--   --   Final paint touch up 7/24
--   --   Put ceiling fans inside when they arrive
--   --   Repair main water line Mindy
--   --   Cut in receptacle in Island Harry
--   --   Tom to take remaining lights
--   --   Remove cardboard from floors Osbaldo 7/27
--   --   Clean off front and back siding- very muddy
--   --   Need cord for range
--   --   Shoemold needed at french doors
--   --   Cover on media wires in laundry Harry- 8/3
--   --   Install fridge handles
--   --   Install dishwasher
--   --   Floor creaking through hallway
--   --   Adjust water pressure
--   --   Hall Bath needs seal on spout
--   --   Caulk at master backsplash above wall Osbaldo
--   --   Blend wall paint around trim
--   --   Out back- splash block needed
--   --   Missing several vinyl pieces at bottom of deck
--   --   Hallway squeaks
--   --   CODED LOCKBOX - 6581
--   --   Remove trash can
--   --   Mark parking spot lines Adam
--   --   Paint for all properties
--   --   Wobbly spot on hall tub Mindy? Complete?
--   --   Walk through with Tom creaks in floor- landings Tom
--   --   New panel for panel box lift closet
--   --   Creaks in loft floor ear window Tom
--   --   Touch up floors in kitchen
--   --   Downspout...run away from house Splash block should be sufficient - owner can change later
--   --   Wash paint bottom of trim...outside under French doors
--   --   Box over drain??? Kate handle
--   --   Chip on cement step
--   --   Wobbly spout on hall tub
--   --   Electricity not working in master bedroom
--   --   Ceiling repair from plumbing related water damage Tom will relay to drywaller Happening this week June 18
--   --   REVIEW REPAIR LIST
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *        Monday May 16
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)       Done by Tue, May 2
-- -- Inspection (Rough In HVAC) (1)       Wed, May 3
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *        Thu, May 4
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        5/15- in process- blocked
-- -- Paint 1 (1)       5/19?
-- -- Garage Door (0)      
-- -- House Numbers (0)       Extinguisher - Osbaldo
-- -- Cabinet Installation (2) *        Still working on upstairs bathrooms
-- -- Granite Installation (1) *        July 14
-- -- Interior Trim - Install (3) *        6/26- complete today
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Finishing on Friday 6/23
-- -- Paint 2 (3)       6/12-6/14
-- -- Cover Floors (1)       Osbaldo - Friday afternoon, June 30
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        7/5
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)       Thurs, July 20
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3) *        Finish 7/24
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *       
-- -- Install Appliances (0) *        Were not delivered
-- -- Paint 3 (2) *       
-- -- Carpet (2)       6/30
-- -- Appraiser Confirms Construction Completion (0)       Robbie Miller going August 2
-- -- Inspection (Final Building) (2) *       
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Thursday-Friday
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1) *        Saturday morning 7/29
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)      
-- -- Remove Coded Lockbox (0)