ADDR
- 114  ::  2243 Lapis Lane
[ BUILD: 16020089 ]       [ PLUMB: 16040132 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Missing light bulb in master bathroom
Tue    Apr 29      Ratified Contract? (0)      
Tue    Apr 29      $2500 Deposit Received (0)      
Tue    Apr 29      Association Packet Requested (0)      
Tue    Apr 29      Association Packet Received (0)      
Tue    Apr 29      Selections Meeting (0)      
Tue    Apr 29      Selections Sheet Signed (0)      
Tue    Apr 29      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Apr 29      Deposit For Upgrades Received (0)      
Tue    Apr 29      Inspection (Concrete Wall) (1)      
Wed    Apr 30      Inspection (Conduit Under Slab) (1)      
Thu    May 1      Inspection (Drain Tile) (0)      
Thu    May 1      Settlement Agent Confirmed (0)      
Thu    May 1      Order Tubs / Showers (0)      
Thu    May 1      Verify Window & Roof Structure (0)      
Thu    May 1      Install Stairs (0)      
Thu    May 1      House Number and Status in Window (0)      
Thu    May 1      Order Appliances (0)      
Thu    May 1      Patio (0)      
Thu    May 1      Sod / Seed / Landscaping (0)       Mon/Tues
Thu    May 1      Rough In Microwave Vent (0)      
Thu    May 1      Inspection (Rough In Plumbing) (1)      
Fri    May 2      Inspection (Rough In Electric) (1)      
Mon    May 5      Inspection (Deck Piers) (0)      
Mon    May 5      Inspection (Framing) (1) *       
Tue    May 6      Exterior Stone (0)      
Tue    May 6      Set Electric Meter (0) *       
Tue    May 6      Inspection (Main Water Line) (0)      
Tue    May 6      Loan Approval (0)      
Tue    May 6      Deed Preparation (0)      
Tue    May 6      Garage Door (0) *       
Tue    May 6      House Numbers (0)       JB
Tue    May 6      Mailbox (0)      
Tue    May 6      Order Plumbing / Lighting Fixtures (0)      
Tue    May 6      Interior Trim - Paint (1)      
Wed    May 7      Cover Floors (1)      
Thu    May 8      Deliver Plumbing / Lighting Fixtures (0)      
Thu    May 8      Shoe Moulding (0)      
Thu    May 8      Set Water Meter (0) *       
Thu    May 8      Ceiling Fans (0)      
Thu    May 8      Blower Door Test (1)      
Fri    May 9      Paint 3 (2) *       
Tue    May 13      Appraiser Confirms Construction Completion (0)      
Tue    May 13      Inspection (Final HVAC) (1)      
Wed    May 14      Inspection (Final Plumbing) (1)      
Thu    May 15      Inspection (Final Electric) (1)      
Fri    May 16      Stain Hardwood Stairs (1)      
Mon    May 19      Certificate of Occupancy (1) *       
Tue    May 20      C.O. to Lender (0)      
Tue    May 20      Schedule Closing (0)      
Tue    May 20      Payment for Upgrades (0)      
Tue    May 20      Keys to Settlement Agent (0)      
Tue    May 20      Review Settlement Statement (0)      
Tue    May 20      Jerry Signs Closing Documents (0)      
Tue    May 20      Request Trash Tote From POA Manager (0)      
Tue    May 20      Closing (1)       NEED TO BE IN BY NOV 23
Wed    May 21      Remove Coded Lockbox (0)      
--   --   Portsmouth Brick, Pearl Vinyl, Green Door
--   --   Interior Framing Talk to Darrell and JM this morning
--   --   Nail down sub floor at landing and Laundry Room by pocket door
--   --   Loft window?
--   --   Loft window?
--   --   Discuss handrails from first floor
--   --   Buyer: Plan for patio, steps, landscaping, parking, curb, gutter
--   --   Carpet Wed, Nov 16
--   --   Curb & Gutter Mon, Nov 21
--   --   Water Meter
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *        Monday May 16
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Windows & Doors (0) *       
-- -- Roofing (0) *       
-- -- Order Cabinets (0)       Yes
-- -- Deck (0)      
-- -- Gutters (0)       11/17: Greg is looking into it right away;
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0)      
-- -- HVAC Rough In (4)       Done Sep 6
-- -- Inspection (Rough In HVAC) (1)       Thurs, Sept 15
-- -- Plumbing Rough In (4)       In process
-- -- Electric Rough In (4)       Finished by Sept 14
-- -- Exterior Vinyl (0) *        8/29 brick in process
-- -- Insulation (2) *        9/19
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)       Mon, Nov 14
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        9/23
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        10/3 sanding today
-- -- Paint 1 (1)       Wed, Oct 5
-- -- Cabinet Installation (2) *        Delivery Oct 14, Install Oct 17 - 21
-- -- Granite Installation (1) *        11/1
-- -- Interior Trim - Install (3) *        10/16- end of week
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       In process
-- -- Paint 2 (3)       10/31
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        11/7 installation
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3)       11/14 finishing
-- -- HVAC Trim Out (1)       Tuesday, Nov 15
-- -- Plumbing Trim Out (2)      
-- -- Install Appliances (0) *        Install 11/12
-- -- Carpet (2)       11/15
-- -- Inspection (Final Building) (2) *        Mon, Nov 21
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Wed Nov 16 - Thu Nov 17
-- -- Buyer Walk Through (1)       Mon 11/21