ADDR
- 114  ::  2243 Lapis Lane
[ BUILD: 16020089 ]       [ PLUMB: 16040132 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Missing light bulb in master bathroom
Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Inspection (Concrete Wall) (1)      
Wed    Dec 17      Inspection (Conduit Under Slab) (1)      
Thu    Dec 18      Inspection (Drain Tile) (0)      
Thu    Dec 18      Settlement Agent Confirmed (0)      
Thu    Dec 18      Order Tubs / Showers (0)      
Thu    Dec 18      Verify Window & Roof Structure (0)      
Thu    Dec 18      Install Stairs (0) *       
Thu    Dec 18      House Number and Status in Window (0)      
Thu    Dec 18      Order Appliances (0)      
Thu    Dec 18      Patio (0)      
Thu    Dec 18      Sod / Seed / Landscaping (0)       Mon/Tues
Thu    Dec 18      Rough In Microwave Vent (0)      
Thu    Dec 18      Inspection (Rough In Plumbing) (1)      
Fri    Dec 19      Inspection (Rough In Electric) (1)      
Mon    Dec 22      Inspection (Framing) (1) *       
Tue    Dec 23      Inspection (Deck Piers) (0)      
Tue    Dec 23      Exterior Stone (0)      
Tue    Dec 23      Set Electric Meter (0) *       
Tue    Dec 23      Inspection (Main Water Line) (0)      
Tue    Dec 23      Loan Approval (0)      
Tue    Dec 23      Deed Preparation (0)      
Tue    Dec 23      Garage Door (0)      
Tue    Dec 23      House Numbers (0)       JB
Tue    Dec 23      Mailbox (0)      
Tue    Dec 23      Order Plumbing / Lighting Fixtures (0)      
Tue    Dec 23      Interior Trim - Paint (1)      
Wed    Dec 24      Cover Floors (1)      
Thu    Dec 25      Deliver Plumbing / Lighting Fixtures (0)      
Thu    Dec 25      Shoe Moulding (0)      
Thu    Dec 25      Set Water Meter (0) *       
Thu    Dec 25      Ceiling Fans (0)      
Thu    Dec 25      Blower Door Test (1)      
Fri    Dec 26      Paint 3 (2) *       
Tue    Dec 30      Appraiser Confirms Construction Completion (0)      
Tue    Dec 30      Inspection (Final HVAC) (1)      
Wed    Dec 31      Inspection (Final Plumbing) (1)      
Thu    Jan 1      Inspection (Final Electric) (1)      
Fri    Jan 2      Stain Hardwood Stairs (1) *       
Mon    Jan 5      Certificate of Occupancy (1) *       
Tue    Jan 6      C.O. to Lender (0)      
Tue    Jan 6      Schedule Closing (0)      
Tue    Jan 6      Payment for Upgrades (0)      
Tue    Jan 6      Keys to Settlement Agent (0)      
Tue    Jan 6      Review Settlement Statement (0)      
Tue    Jan 6      Jerry Signs Closing Documents (0)      
Tue    Jan 6      Request Trash Tote From POA Manager (0)      
Tue    Jan 6      Closing (1)       NEED TO BE IN BY NOV 23
Wed    Jan 7      Remove Coded Lockbox (0)      
--   --   Portsmouth Brick, Pearl Vinyl, Green Door
--   --   Interior Framing Talk to Darrell and JM this morning
--   --   Nail down sub floor at landing and Laundry Room by pocket door
--   --   Loft window?
--   --   Loft window?
--   --   Discuss handrails from first floor
--   --   Buyer: Plan for patio, steps, landscaping, parking, curb, gutter
--   --   Carpet Wed, Nov 16
--   --   Curb & Gutter Mon, Nov 21
--   --   Water Meter
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *        Monday May 16
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Windows & Doors (0) *       
-- -- Roofing (0) *       
-- -- Order Cabinets (0)       Yes
-- -- Deck (0)      
-- -- Gutters (0)       11/17: Greg is looking into it right away;
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *       
-- -- HVAC Rough In (4)       Done Sep 6
-- -- Plumbing Rough In (4)       In process
-- -- Electric Rough In (4)       Finished by Sept 14
-- -- Inspection (Rough In HVAC) (1)       Thurs, Sept 15
-- -- Exterior Vinyl (0) *        8/29 brick in process
-- -- Insulation (2) *        9/19
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)       Mon, Nov 14
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        9/23
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        10/3 sanding today
-- -- Paint 1 (1)       Wed, Oct 5
-- -- Cabinet Installation (2) *        Delivery Oct 14, Install Oct 17 - 21
-- -- Granite Installation (1) *        11/1
-- -- Interior Trim - Install (3) *        10/16- end of week
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       In process
-- -- Paint 2 (3)       10/31
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        11/7 installation
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3) *        11/14 finishing
-- -- HVAC Trim Out (1) *        Tuesday, Nov 15
-- -- Plumbing Trim Out (2) *       
-- -- Install Appliances (0) *        Install 11/12
-- -- Carpet (2)       11/15
-- -- Inspection (Final Building) (2) *        Mon, Nov 21
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Wed Nov 16 - Thu Nov 17
-- -- Buyer Walk Through (1) *        Mon 11/21