ADDR
- 114  ::  2243 Lapis Lane
[ BUILD: 16020089 ]       [ PLUMB: 16040132 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Missing light bulb in master bathroom
Fri    Sep 20      Ratified Contract? (0)      
Fri    Sep 20      $2500 Deposit Received (0)      
Fri    Sep 20      Association Packet Requested (0)      
Fri    Sep 20      Association Packet Received (0)      
Fri    Sep 20      Selections Meeting (0)      
Fri    Sep 20      Selections Sheet Signed (0)      
Fri    Sep 20      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Fri    Sep 20      Deposit For Upgrades Received (0)      
Fri    Sep 20      Inspection (Concrete Wall) (1)      
Mon    Sep 23      Inspection (Conduit Under Slab) (1)      
Tue    Sep 24      Inspection (Drain Tile) (0)      
Tue    Sep 24      Settlement Agent Confirmed (0)      
Tue    Sep 24      Order Tubs / Showers (0)      
Tue    Sep 24      Verify Window & Roof Structure (0)      
Tue    Sep 24      Install Stairs (0)      
Tue    Sep 24      House Number and Status in Window (0)      
Tue    Sep 24      Order Appliances (0)      
Tue    Sep 24      Patio (0)      
Tue    Sep 24      Sod / Seed / Landscaping (0)       Mon/Tues
Tue    Sep 24      Rough In Microwave Vent (0)      
Tue    Sep 24      Inspection (Rough In Plumbing) (1)      
Wed    Sep 25      Inspection (Rough In Electric) (1)      
Thu    Sep 26      Inspection (Deck Piers) (0)      
Thu    Sep 26      Inspection (Framing) (1)      
Fri    Sep 27      Exterior Stone (0)      
Fri    Sep 27      Set Electric Meter (0)      
Fri    Sep 27      Inspection (Main Water Line) (0)      
Fri    Sep 27      Loan Approval (0)      
Fri    Sep 27      Deed Preparation (0)      
Fri    Sep 27      Garage Door (0)      
Fri    Sep 27      House Numbers (0)       JB
Fri    Sep 27      Mailbox (0)      
Fri    Sep 27      Order Plumbing / Lighting Fixtures (0)      
Fri    Sep 27      Interior Trim - Paint (1)      
Mon    Sep 30      Cover Floors (1)      
Tue    Oct 1      Deliver Plumbing / Lighting Fixtures (0)      
Tue    Oct 1      Shoe Moulding (0)      
Tue    Oct 1      Set Water Meter (0)      
Tue    Oct 1      Ceiling Fans (0)      
Tue    Oct 1      Blower Door Test (1)      
Wed    Oct 2      Paint 3 (2)      
Fri    Oct 4      Appraiser Confirms Construction Completion (0)      
Fri    Oct 4      Inspection (Final HVAC) (1)      
Mon    Oct 7      Inspection (Final Plumbing) (1)      
Tue    Oct 8      Inspection (Final Electric) (1)      
Wed    Oct 9      Stain Hardwood Stairs (1)      
Thu    Oct 10      Certificate of Occupancy (1)      
Fri    Oct 11      C.O. to Lender (0)      
Fri    Oct 11      Schedule Closing (0)      
Fri    Oct 11      Payment for Upgrades (0)      
Fri    Oct 11      Keys to Settlement Agent (0)      
Fri    Oct 11      Review Settlement Statement (0)      
Fri    Oct 11      Jerry Signs Closing Documents (0)      
Fri    Oct 11      Request Trash Tote From POA Manager (0)      
Fri    Oct 11      Closing (1)       NEED TO BE IN BY NOV 23
Mon    Oct 14      Remove Coded Lockbox (0)      
--   --   Portsmouth Brick, Pearl Vinyl, Green Door
--   --   Interior Framing Talk to Darrell and JM this morning
--   --   Nail down sub floor at landing and Laundry Room by pocket door
--   --   Loft window?
--   --   Loft window?
--   --   Discuss handrails from first floor
--   --   Buyer: Plan for patio, steps, landscaping, parking, curb, gutter
--   --   Carpet Wed, Nov 16
--   --   Curb & Gutter Mon, Nov 21
--   --   Water Meter
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1)       Monday May 16
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Framing II (8)      
-- -- Framing III (8)      
-- -- Windows & Doors (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)       Yes
-- -- Deck (0)      
-- -- Gutters (0)       11/17: Greg is looking into it right away;
-- -- Driveway (0)      
-- -- Privacy Divider / Fence (0)      
-- -- HVAC Rough In (4)       Done Sep 6
-- -- Inspection (Rough In HVAC) (1)       Thurs, Sept 15
-- -- Plumbing Rough In (4)       In process
-- -- Electric Rough In (4)       Finished by Sept 14
-- -- Exterior Vinyl (0)       8/29 brick in process
-- -- Insulation (2)       9/19
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)       Mon, Nov 14
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4)       9/23
-- -- Drywall (Tape, Block, Skim, Sand) (6)       10/3 sanding today
-- -- Paint 1 (1)       Wed, Oct 5
-- -- Cabinet Installation (2)       Delivery Oct 14, Install Oct 17 - 21
-- -- Granite Installation (1)       11/1
-- -- Interior Trim - Install (3)       10/16- end of week
-- -- Luxury Vinyl Plank (3)      
-- -- Luxury Vinyl Tile (0)       In process
-- -- Paint 2 (3)       10/31
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       11/7 installation
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3)       11/14 finishing
-- -- HVAC Trim Out (1)       Tuesday, Nov 15
-- -- Plumbing Trim Out (2)      
-- -- Install Appliances (0)       Install 11/12
-- -- Carpet (2)       11/15
-- -- Inspection (Final Building) (2)       Mon, Nov 21
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Wed Nov 16 - Thu Nov 17
-- -- Buyer Walk Through (1)       Mon 11/21