| -- | -- | Missing light bulb in master bathroom | ||
| Tue | Dec 16 | Ratified Contract? (0) | ||
| Tue | Dec 16 | $2500 Deposit Received (0) | ||
| Tue | Dec 16 | Association Packet Requested (0) | ||
| Tue | Dec 16 | Association Packet Received (0) | ||
| Tue | Dec 16 | Selections Meeting (0) | ||
| Tue | Dec 16 | Selections Sheet Signed (0) | ||
| Tue | Dec 16 | Amendment for Upgrades (B,S,L,T,BCP) (0) | ||
| Tue | Dec 16 | Deposit For Upgrades Received (0) | ||
| Tue | Dec 16 | Inspection (Concrete Wall) (1) | ||
| Wed | Dec 17 | Inspection (Conduit Under Slab) (1) | ||
| Thu | Dec 18 | Inspection (Drain Tile) (0) | ||
| Thu | Dec 18 | Settlement Agent Confirmed (0) | ||
| Thu | Dec 18 | Order Tubs / Showers (0) | ||
| Thu | Dec 18 | Verify Window & Roof Structure (0) | ||
| Thu | Dec 18 | Install Stairs (0) * | ||
| Thu | Dec 18 | House Number and Status in Window (0) | ||
| Thu | Dec 18 | Order Appliances (0) | ||
| Thu | Dec 18 | Patio (0) | ||
| Thu | Dec 18 | Sod / Seed / Landscaping (0) | Mon/Tues | |
| Thu | Dec 18 | Rough In Microwave Vent (0) | ||
| Thu | Dec 18 | Inspection (Rough In Plumbing) (1) | ||
| Fri | Dec 19 | Inspection (Rough In Electric) (1) | ||
| Mon | Dec 22 | Inspection (Framing) (1) * | ||
| Tue | Dec 23 | Inspection (Deck Piers) (0) | ||
| Tue | Dec 23 | Exterior Stone (0) | ||
| Tue | Dec 23 | Set Electric Meter (0) * | ||
| Tue | Dec 23 | Inspection (Main Water Line) (0) | ||
| Tue | Dec 23 | Loan Approval (0) | ||
| Tue | Dec 23 | Deed Preparation (0) | ||
| Tue | Dec 23 | Garage Door (0) | ||
| Tue | Dec 23 | House Numbers (0) | JB | |
| Tue | Dec 23 | Mailbox (0) | ||
| Tue | Dec 23 | Order Plumbing / Lighting Fixtures (0) | ||
| Tue | Dec 23 | Interior Trim - Paint (1) | ||
| Wed | Dec 24 | Cover Floors (1) | ||
| Thu | Dec 25 | Deliver Plumbing / Lighting Fixtures (0) | ||
| Thu | Dec 25 | Shoe Moulding (0) | ||
| Thu | Dec 25 | Set Water Meter (0) * | ||
| Thu | Dec 25 | Ceiling Fans (0) | ||
| Thu | Dec 25 | Blower Door Test (1) | ||
| Fri | Dec 26 | Paint 3 (2) * | ||
| Tue | Dec 30 | Appraiser Confirms Construction Completion (0) | ||
| Tue | Dec 30 | Inspection (Final HVAC) (1) | ||
| Wed | Dec 31 | Inspection (Final Plumbing) (1) | ||
| Thu | Jan 1 | Inspection (Final Electric) (1) | ||
| Fri | Jan 2 | Stain Hardwood Stairs (1) * | ||
| Mon | Jan 5 | Certificate of Occupancy (1) * | ||
| Tue | Jan 6 | C.O. to Lender (0) | ||
| Tue | Jan 6 | Schedule Closing (0) | ||
| Tue | Jan 6 | Payment for Upgrades (0) | ||
| Tue | Jan 6 | Keys to Settlement Agent (0) | ||
| Tue | Jan 6 | Review Settlement Statement (0) | ||
| Tue | Jan 6 | Jerry Signs Closing Documents (0) | ||
| Tue | Jan 6 | Request Trash Tote From POA Manager (0) | ||
| Tue | Jan 6 | Closing (1) | NEED TO BE IN BY NOV 23 | |
| Wed | Jan 7 | Remove Coded Lockbox (0) | ||
| -- | -- | Portsmouth Brick, Pearl Vinyl, Green Door | ||
| -- | -- | Interior Framing | Talk to Darrell and JM this morning | |
| -- | -- | Nail down sub floor at landing and Laundry Room by pocket door | ||
| -- | -- | Loft window? | ||
| -- | -- | Loft window? | ||
| -- | -- | Discuss handrails from first floor | ||
| -- | -- | Buyer: Plan for patio, steps, landscaping, parking, curb, gutter | ||
| -- | -- | Carpet | Wed, Nov 16 | |
| -- | -- | Curb & Gutter | Mon, Nov 21 | |
| -- | -- | Water Meter | ||
| -- | -- | Building Permit (30) * | ||
| -- | -- | Order Roof & Floor Trusses (1) | ||
| -- | -- | Order Windows & Doors (0) | ||
| -- | -- | Stake Out Home (1) | ||
| -- | -- | Excavate (2) | ||
| -- | -- | Inspection (Footers) (1) | ||
| -- | -- | Pour Footers (1) * | ||
| -- | -- | Set Forms (2) | ||
| -- | -- | Pour Foundation Walls (1) | ||
| -- | -- | Plumb Slab (2) | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) | ||
| -- | -- | Prepare Slab (1) | ||
| -- | -- | Inspection (Slab) (1) | ||
| -- | -- | Pour Slab (1) * | Monday May 16 | |
| -- | -- | Framing I (9) | ||
| -- | -- | Order Steps (0) | ||
| -- | -- | Framing II (8) | ||
| -- | -- | Framing III (8) * | ||
| -- | -- | Windows & Doors (0) * | ||
| -- | -- | Roofing (0) * | ||
| -- | -- | Order Cabinets (0) | Yes | |
| -- | -- | Deck (0) | ||
| -- | -- | Gutters (0) | 11/17: Greg is looking into it right away; | |
| -- | -- | Driveway (0) * | ||
| -- | -- | Privacy Divider / Fence (0) * | ||
| -- | -- | HVAC Rough In (4) | Done Sep 6 | |
| -- | -- | Plumbing Rough In (4) | In process | |
| -- | -- | Electric Rough In (4) | Finished by Sept 14 | |
| -- | -- | Inspection (Rough In HVAC) (1) | Thurs, Sept 15 | |
| -- | -- | Exterior Vinyl (0) * | 8/29 brick in process | |
| -- | -- | Insulation (2) * | 9/19 | |
| -- | -- | Inspection (Insulation) (1) | ||
| -- | -- | Inspection (Electric Service) (0) | Mon, Nov 14 | |
| -- | -- | Inspection (Main Sewer Line) (0) | ||
| -- | -- | Order Interior Doors & Trim (0) | ||
| -- | -- | Drywall (Hang) (4) * | 9/23 | |
| -- | -- | Drywall (Tape, Block, Skim, Sand) (6) * | 10/3 sanding today | |
| -- | -- | Paint 1 (1) | Wed, Oct 5 | |
| -- | -- | Cabinet Installation (2) * | Delivery Oct 14, Install Oct 17 - 21 | |
| -- | -- | Granite Installation (1) * | 11/1 | |
| -- | -- | Interior Trim - Install (3) * | 10/16- end of week | |
| -- | -- | Luxury Vinyl Plank (3) * | ||
| -- | -- | Luxury Vinyl Tile (0) | In process | |
| -- | -- | Paint 2 (3) | 10/31 | |
| -- | -- | Shelving, Door Knobs, Fire Extinguisher (0) * | 11/7 installation | |
| -- | -- | Install Coded Lockbox (add extra keys) (0) | ||
| -- | -- | Pay Water / Sewer Taps (0) | ||
| -- | -- | Electric Trim Out (3) * | 11/14 finishing | |
| -- | -- | HVAC Trim Out (1) * | Tuesday, Nov 15 | |
| -- | -- | Plumbing Trim Out (2) * | ||
| -- | -- | Install Appliances (0) * | Install 11/12 | |
| -- | -- | Carpet (2) | 11/15 | |
| -- | -- | Inspection (Final Building) (2) * | Mon, Nov 21 | |
| -- | -- | Pre Walk Through (0) | ||
| -- | -- | Cleaning (1) | Wed Nov 16 - Thu Nov 17 | |
| -- | -- | Buyer Walk Through (1) * | Mon 11/21 | |