--   --   Clean Exterior by back patio
--   --   Dishwasher repair
--   --   Grass seed
--   --   Repaint front door
Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Inspection (Concrete Wall) (1)      
Wed    Dec 17      Inspection (Conduit Under Slab) (1)      
Thu    Dec 18      Inspection (Drain Tile) (0)      
Thu    Dec 18      Settlement Agent Confirmed (0)      
Thu    Dec 18      Order Tubs / Showers (0)      
Thu    Dec 18      Verify Window & Roof Structure (0)      
Thu    Dec 18      Install Stairs (0) *       
Thu    Dec 18      House Number and Status in Window (0)      
Thu    Dec 18      Order Appliances (0)      
Thu    Dec 18      Patio (0)      
Thu    Dec 18      Rough In Microwave Vent (0)      
Thu    Dec 18      Inspection (Rough In Plumbing) (1)      
Fri    Dec 19      Inspection (Rough In Electric) (1)      
Mon    Dec 22      Inspection (Framing) (1) *       
Tue    Dec 23      Inspection (Deck Piers) (0)      
Tue    Dec 23      Exterior Stone (0)      
Tue    Dec 23      Set Electric Meter (0) *       
Tue    Dec 23      Inspection (Main Water Line) (0)      
Tue    Dec 23      Loan Approval (0)      
Tue    Dec 23      Deed Preparation (0)      
Tue    Dec 23      Garage Door (0)      
Tue    Dec 23      Mailbox (0)      
Tue    Dec 23      Order Plumbing / Lighting Fixtures (0)      
Tue    Dec 23      Interior Trim - Paint (1)      
Wed    Dec 24      Cover Floors (1)      
Thu    Dec 25      Deliver Plumbing / Lighting Fixtures (0)      
Thu    Dec 25      Shoe Moulding (0)      
Thu    Dec 25      Set Water Meter (0) *       
Thu    Dec 25      Ceiling Fans (0)      
Thu    Dec 25      Blower Door Test (1)      
Fri    Dec 26      Paint 3 (2) *       
Tue    Dec 30      Appraiser Confirms Construction Completion (0)      
Tue    Dec 30      Inspection (Final HVAC) (1)      
Wed    Dec 31      Inspection (Final Plumbing) (1)      
Thu    Jan 1      Inspection (Final Electric) (1)      
Fri    Jan 2      Stain Hardwood Stairs (1) *       
Mon    Jan 5      C.O. to Lender (0)      
Mon    Jan 5      Schedule Closing (0)      
Mon    Jan 5      Payment for Upgrades (0)      
Mon    Jan 5      Keys to Settlement Agent (0)      
Mon    Jan 5      Review Settlement Statement (0)      
Mon    Jan 5      Jerry Signs Closing Documents (0)      
Mon    Jan 5      Request Trash Tote From POA Manager (0)      
Mon    Jan 5      Closing (1)      
Tue    Jan 6      Remove Coded Lockbox (0)      
--   --   Carter's Grove Brick, Bone Vinyl, Green Door
--   --   Beginning meter pack on 107-110 today
--   --   Repair damaged stairs
--   --   Need bathroom trim
--   --   Tom did you call HEC?
--   --   Tom did you call for heat?
--   --   12/8 gash on third step needs to be fixed
--   --   Need vinyl under stairs and in basement room closet
--   --   Patch concrete in basement room
--   --   Nosing piece for s
--   --   Nosing piece for top of stairs 12/19 installed today
--   --   Replace damaged stair tread
--   --   Shower Door Install Between 28-30
--   --   1/3 finishing paint now
--   --   Privacy Fence Divider
--   --   1/5 paint touch up today
--   --   Flooring touch up
--   --   1/5 Harry punch out
--   --   Replace master closet fluorescent light cover
--   --   Replace master closet fluorescent light cover
--   --   Chips in garage floor- Tom to seal when it warms up
--   --   Carpet Repair
--   --  
--   --  
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)       Monday May 16
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       8/7 in process
-- -- Order Steps (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Windows & Doors (0) *        Hopefully Monday 9/26
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)       In progress
-- -- Driveway (0) *        Concrete patios being Poured Wednesday or Thursday of this week
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       Sept 20?
-- -- Plumbing Rough In (4)       Done by Friday 10/14
-- -- Electric Rough In (4)       Nearly done
-- -- Inspection (Rough In HVAC) (1)       Friday, Oct 14
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *        Mon, Oct 17
-- -- Inspection (Insulation) (1)       Tue, Oct 18
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        In process
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        10/27 tape/block, 10/28 skim, done by Wed 11/2
-- -- Paint 1 (1)       11/7
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        11/14: install starting
-- -- Granite Installation (1) *        Thursday 12/1
-- -- Interior Trim - Install (3) *        11/14: In progress
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       will be complete by 11/12 (Marcus)
-- -- Paint 2 (3)       11/29
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        In processing
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3) *        12/21 will be complete by
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *        12/21 In process
-- -- Install Appliances (0) *        Installed Dec 14;
-- -- Carpet (2)      
-- -- Inspection (Final Building) (2) *        Thurs, Dec 22
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Frid, Dec 23 - Monday December 26 or 27
-- -- Certificate of Occupancy (1) *       
-- -- Buyer Walk Through (1) *        1/4