ADDR
- 108  ::  2244 Lapis Lane
[ BUILD: 16040115 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Leaking Basement Aug 31, 2018
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Order Appliances (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Order Plumbing / Lighting Fixtures (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Ceiling Fans (0)      
Fri    Dec 6      Blower Door Test (1)      
Mon    Dec 9      Inspection (Final HVAC) (1)      
Tue    Dec 10      Inspection (Final Plumbing) (1)      
Wed    Dec 11      Inspection (Final Electric) (1)      
Thu    Dec 12      Stain Hardwood Stairs (1)      
Fri    Dec 13      Schedule Closing (0)      
Fri    Dec 13      Keys to Settlement Agent (0)      
Fri    Dec 13      Review Settlement Statement (0)      
Fri    Dec 13      Jerry Signs Closing Documents (0)      
Fri    Dec 13      Request Trash Tote From POA Manager (0)      
Fri    Dec 13      Remove Coded Lockbox (0)      
--   --   Country Beige Vinyl, Red Door
--   --   Green door
--   --   Tom to move up hall bath vanity to downstairs powder room
--   --   Need vinyl in pantry and under stairs
--   --   Cover floors. Are we using the same stuff we used in heritage 39?
--   --   Install fire extinguisher Osbaldo
--   --   Final paint and stain steps 4/24 last coat of poly
--   --   Trim out laundry and closet under stairs
--   --   Harry, clean up boxes
--   --   Install shoe moulding Osbaldo
--   --   Home Inspection - Apr 25, 9AM
--   --   Radon test results Wed, May 3?
--   --   CODED LOCKBOX = 1488
--   --   Need mailbox keys
--   --   Need extra keys
--   --   Paint edges of doors Isaac
--   --   Touch Up Paint Isaac
--   --   Fence quote-all privacy
--   --   Clean back of patio doors Osbaldo
--   --   Extend drain line in backyard to end of property line and bury it Osbaldo
--   --   Semi frames less shower door install-quote
--   --   Washer install (maybe dryer)
--   --   Left door under sink hinge adjustment Classic - Kate to talk to Gabby, replace hinges
--   --   Is the tile sealed? Osbaldo
--   --   Blinds on 11 windows(waiting on buyer)
--   --   Add seed and straw
--   --   Hardwood repair
--   --   Remove clothes washer
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)       Monday May 16
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       8/7 in process
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *        At least 3 to 4 more weeks according to Donald as of 9/12
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)       Hopefully Monday 9/26
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)      
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       Complete by 12/14-15
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2)      
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       Tom get with Mitch on supply in trailer
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        1/3 sanding now
-- -- Paint 1 (1)       1/6
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Del Jan 27, Install Jan 30 - Feb 3
-- -- Granite Installation (1) *        Feb 17
-- -- Interior Trim - Install (3)       Nearly complete
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Some on site- all?
-- -- Paint 2 (3)       3/20 Filling painting trim
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)      
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)       Mon, May 1
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       Harry - Thu, April 20
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       Install pedastal sink in powder room
-- -- Install Appliances (0) *        April 10
-- -- Paint 3 (2) *       
-- -- Carpet (2)       April 10th-ish
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Wed, May 3
-- -- Pre Walk Through (0)       Mon, May 1?
-- -- Cleaning (1)       Finishing today 5/1
-- -- Certificate of Occupancy (1) *        Wed, May 3?
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1)       Saturday, May 13 at 11AM;
-- -- Payment for Upgrades (0)      
-- -- Closing (1)       Fri, May 19 @ 3PM, Welby's office