- 108  ::  2244 Lapis Lane
[ BUILD: 16040115 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Leaking Basement Aug 31, 2018
Fri    Sep 20      Ratified Contract? (0)      
Fri    Sep 20      $2500 Deposit Received (0)      
Fri    Sep 20      Association Packet Requested (0)      
Fri    Sep 20      Association Packet Received (0)      
Fri    Sep 20      Selections Meeting (0)      
Fri    Sep 20      Selections Sheet Signed (0)      
Fri    Sep 20      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Fri    Sep 20      Deposit For Upgrades Received (0)      
Fri    Sep 20      Inspection (Concrete Wall) (1)      
Mon    Sep 23      Inspection (Conduit Under Slab) (1)      
Tue    Sep 24      Inspection (Drain Tile) (0)      
Tue    Sep 24      Settlement Agent Confirmed (0)      
Tue    Sep 24      Verify Window & Roof Structure (0)      
Tue    Sep 24      Order Appliances (0)      
Tue    Sep 24      Patio (0)      
Tue    Sep 24      Rough In Microwave Vent (0)      
Tue    Sep 24      Inspection (Rough In Plumbing) (1)      
Wed    Sep 25      Inspection (Rough In Electric) (1)      
Thu    Sep 26      Inspection (Deck Piers) (0)      
Thu    Sep 26      Inspection (Framing) (1)      
Fri    Sep 27      Exterior Stone (0)      
Fri    Sep 27      Set Electric Meter (0)      
Fri    Sep 27      Inspection (Main Water Line) (0)      
Fri    Sep 27      Loan Approval (0)      
Fri    Sep 27      Deed Preparation (0)      
Fri    Sep 27      Mailbox (0)      
Fri    Sep 27      Order Plumbing / Lighting Fixtures (0)      
Fri    Sep 27      Interior Trim - Paint (1)      
Mon    Sep 30      Ceiling Fans (0)      
Mon    Sep 30      Blower Door Test (1)      
Tue    Oct 1      Inspection (Final HVAC) (1)      
Wed    Oct 2      Inspection (Final Plumbing) (1)      
Thu    Oct 3      Inspection (Final Electric) (1)      
Fri    Oct 4      Stain Hardwood Stairs (1)      
Mon    Oct 7      Schedule Closing (0)      
Mon    Oct 7      Keys to Settlement Agent (0)      
Mon    Oct 7      Review Settlement Statement (0)      
Mon    Oct 7      Jerry Signs Closing Documents (0)      
Mon    Oct 7      Request Trash Tote From POA Manager (0)      
Mon    Oct 7      Remove Coded Lockbox (0)      
--   --   Country Beige Vinyl, Red Door
--   --   Green door
--   --   Tom to move up hall bath vanity to downstairs powder room
--   --   Need vinyl in pantry and under stairs
--   --   Cover floors. Are we using the same stuff we used in heritage 39?
--   --   Install fire extinguisher Osbaldo
--   --   Final paint and stain steps 4/24 last coat of poly
--   --   Trim out laundry and closet under stairs
--   --   Harry, clean up boxes
--   --   Install shoe moulding Osbaldo
--   --   Home Inspection - Apr 25, 9AM
--   --   Radon test results Wed, May 3?
--   --   CODED LOCKBOX = 1488
--   --   Need mailbox keys
--   --   Need extra keys
--   --   Paint edges of doors Isaac
--   --   Touch Up Paint Isaac
--   --   Fence quote-all privacy
--   --   Clean back of patio doors Osbaldo
--   --   Extend drain line in backyard to end of property line and bury it Osbaldo
--   --   Semi frames less shower door install-quote
--   --   Washer install (maybe dryer)
--   --   Left door under sink hinge adjustment Classic - Kate to talk to Gabby, replace hinges
--   --   Is the tile sealed? Osbaldo
--   --   Blinds on 11 windows(waiting on buyer)
--   --   Add seed and straw
--   --   Hardwood repair
--   --   Remove clothes washer
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)       Monday May 16
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1)      
-- -- Framing I (9)       8/7 in process
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8)       At least 3 to 4 more weeks according to Donald as of 9/12
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)       Hopefully Monday 9/26
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)      
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       Complete by 12/14-15
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
-- -- Exterior Vinyl (0)      
-- -- Insulation (2)      
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       Tom get with Mitch on supply in trailer
-- -- Drywall (Hang) (4)      
-- -- Drywall (Tape, Block, Skim, Sand) (6)       1/3 sanding now
-- -- Paint 1 (1)       1/6
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2)       Del Jan 27, Install Jan 30 - Feb 3
-- -- Granite Installation (1)       Feb 17
-- -- Interior Trim - Install (3)       Nearly complete
-- -- Luxury Vinyl Plank (3)      
-- -- Luxury Vinyl Tile (0)       Some on site- all?
-- -- Paint 2 (3)       3/20 Filling painting trim
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)      
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)       Mon, May 1
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       Harry - Thu, April 20
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       Install pedastal sink in powder room
-- -- Install Appliances (0)       April 10
-- -- Paint 3 (2)      
-- -- Carpet (2)       April 10th-ish
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2)       Wed, May 3
-- -- Pre Walk Through (0)       Mon, May 1?
-- -- Cleaning (1)       Finishing today 5/1
-- -- Certificate of Occupancy (1)       Wed, May 3?
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1)       Saturday, May 13 at 11AM;
-- -- Payment for Upgrades (0)      
-- -- Closing (1)       Fri, May 19 @ 3PM, Welby's office