--   --   Leaking Basement Aug 31, 2018
Tue    Apr 29      Ratified Contract? (0)      
Tue    Apr 29      $2500 Deposit Received (0)      
Tue    Apr 29      Association Packet Requested (0)      
Tue    Apr 29      Association Packet Received (0)      
Tue    Apr 29      Selections Meeting (0)      
Tue    Apr 29      Selections Sheet Signed (0)      
Tue    Apr 29      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Apr 29      Deposit For Upgrades Received (0)      
Tue    Apr 29      Inspection (Concrete Wall) (1)      
Wed    Apr 30      Inspection (Conduit Under Slab) (1)      
Thu    May 1      Inspection (Drain Tile) (0)      
Thu    May 1      Settlement Agent Confirmed (0)      
Thu    May 1      Verify Window & Roof Structure (0)      
Thu    May 1      Order Appliances (0)      
Thu    May 1      Patio (0)      
Thu    May 1      Rough In Microwave Vent (0)      
Thu    May 1      Inspection (Rough In Plumbing) (1)      
Fri    May 2      Inspection (Rough In Electric) (1)      
Mon    May 5      Inspection (Deck Piers) (0)      
Mon    May 5      Inspection (Framing) (1) *       
Tue    May 6      Exterior Stone (0)      
Tue    May 6      Set Electric Meter (0) *       
Tue    May 6      Inspection (Main Water Line) (0)      
Tue    May 6      Loan Approval (0)      
Tue    May 6      Deed Preparation (0)      
Tue    May 6      Mailbox (0)      
Tue    May 6      Order Plumbing / Lighting Fixtures (0)      
Tue    May 6      Interior Trim - Paint (1)      
Wed    May 7      Ceiling Fans (0)      
Wed    May 7      Blower Door Test (1)      
Thu    May 8      Inspection (Final HVAC) (1)      
Fri    May 9      Inspection (Final Plumbing) (1)      
Mon    May 12      Inspection (Final Electric) (1)      
Tue    May 13      Stain Hardwood Stairs (1)      
Wed    May 14      Schedule Closing (0)      
Wed    May 14      Keys to Settlement Agent (0)      
Wed    May 14      Review Settlement Statement (0)      
Wed    May 14      Jerry Signs Closing Documents (0)      
Wed    May 14      Request Trash Tote From POA Manager (0)      
Wed    May 14      Remove Coded Lockbox (0)      
--   --   Country Beige Vinyl, Red Door
--   --   Green door
--   --   Tom to move up hall bath vanity to downstairs powder room
--   --   Need vinyl in pantry and under stairs
--   --   Cover floors. Are we using the same stuff we used in heritage 39?
--   --   Install fire extinguisher Osbaldo
--   --   Final paint and stain steps 4/24 last coat of poly
--   --   Trim out laundry and closet under stairs
--   --   Harry, clean up boxes
--   --   Install shoe moulding Osbaldo
--   --   Home Inspection - Apr 25, 9AM
--   --   Radon test results Wed, May 3?
--   --   CODED LOCKBOX = 1488
--   --   Need mailbox keys
--   --   Need extra keys
--   --   Paint edges of doors Isaac
--   --   Touch Up Paint Isaac
--   --   Fence quote-all privacy
--   --   Clean back of patio doors Osbaldo
--   --   Extend drain line in backyard to end of property line and bury it Osbaldo
--   --   Semi frames less shower door install-quote
--   --   Washer install (maybe dryer)
--   --   Left door under sink hinge adjustment Classic - Kate to talk to Gabby, replace hinges
--   --   Is the tile sealed? Osbaldo
--   --   Blinds on 11 windows(waiting on buyer)
--   --   Add seed and straw
--   --   Hardwood repair
--   --   Remove clothes washer
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)       Monday May 16
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       8/7 in process
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *        At least 3 to 4 more weeks according to Donald as of 9/12
-- -- Install Stairs (0)      
-- -- Windows & Doors (0) *        Hopefully Monday 9/26
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       Complete by 12/14-15
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       Tom get with Mitch on supply in trailer
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        1/3 sanding now
-- -- Paint 1 (1)       1/6
-- -- Garage Door (0) *       
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Del Jan 27, Install Jan 30 - Feb 3
-- -- Granite Installation (1) *        Feb 17
-- -- Interior Trim - Install (3) *        Nearly complete
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Some on site- all?
-- -- Paint 2 (3)       3/20 Filling painting trim
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *       
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)       Mon, May 1
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3)       Harry - Thu, April 20
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       Install pedastal sink in powder room
-- -- Install Appliances (0) *        April 10
-- -- Paint 3 (2) *       
-- -- Carpet (2)       April 10th-ish
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Wed, May 3
-- -- Pre Walk Through (0)       Mon, May 1?
-- -- Cleaning (1)       Finishing today 5/1
-- -- Certificate of Occupancy (1) *        Wed, May 3?
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1)       Saturday, May 13 at 11AM;
-- -- Payment for Upgrades (0)      
-- -- Closing (1)       Fri, May 19 @ 3PM, Welby's office