| Tue | Dec 16 | Ratified Contract? (0) | ||
| Tue | Dec 16 | $2500 Deposit Received (0) | ||
| Tue | Dec 16 | Association Packet Requested (0) | ||
| Tue | Dec 16 | Association Packet Received (0) | ||
| Tue | Dec 16 | Selections Meeting (0) | ||
| Tue | Dec 16 | Selections Sheet Signed (0) | ||
| Tue | Dec 16 | Amendment for Upgrades (B,S,L,T,BCP) (0) | ||
| Tue | Dec 16 | Deposit For Upgrades Received (0) | ||
| Tue | Dec 16 | Inspection (Concrete Wall) (1) | ||
| Wed | Dec 17 | Inspection (Conduit Under Slab) (1) | ||
| Thu | Dec 18 | Inspection (Drain Tile) (0) | ||
| Thu | Dec 18 | Settlement Agent Confirmed (0) | ||
| Thu | Dec 18 | Order Tubs / Showers (0) | ||
| Thu | Dec 18 | Verify Window & Roof Structure (0) | ||
| Thu | Dec 18 | Install Stairs (0) * | ||
| Thu | Dec 18 | House Number and Status in Window (0) | ||
| Thu | Dec 18 | Order Appliances (0) | ||
| Thu | Dec 18 | Patio (0) | ||
| Thu | Dec 18 | Rough In Microwave Vent (0) | ||
| Thu | Dec 18 | Inspection (Rough In Plumbing) (1) | ||
| Fri | Dec 19 | Inspection (Rough In Electric) (1) | ||
| Mon | Dec 22 | Inspection (Framing) (1) * | ||
| Tue | Dec 23 | Inspection (Deck Piers) (0) | ||
| Tue | Dec 23 | Exterior Stone (0) | ||
| Tue | Dec 23 | Set Electric Meter (0) * | ||
| Tue | Dec 23 | Inspection (Main Water Line) (0) | ||
| Tue | Dec 23 | Loan Approval (0) | ||
| Tue | Dec 23 | Deed Preparation (0) | ||
| Tue | Dec 23 | Garage Door (0) | ||
| Tue | Dec 23 | Mailbox (0) | ||
| Tue | Dec 23 | Order Plumbing / Lighting Fixtures (0) | ||
| Tue | Dec 23 | Interior Trim - Paint (1) | ||
| Wed | Dec 24 | Cover Floors (1) | ||
| Thu | Dec 25 | Deliver Plumbing / Lighting Fixtures (0) | ||
| Thu | Dec 25 | Shoe Moulding (0) | ||
| Thu | Dec 25 | Set Water Meter (0) * | ||
| Thu | Dec 25 | Ceiling Fans (0) | ||
| Thu | Dec 25 | Blower Door Test (1) | ||
| Fri | Dec 26 | Paint 3 (2) * | ||
| Tue | Dec 30 | Appraiser Confirms Construction Completion (0) | ||
| Tue | Dec 30 | Inspection (Final HVAC) (1) | ||
| Wed | Dec 31 | Inspection (Final Plumbing) (1) | ||
| Thu | Jan 1 | Inspection (Final Electric) (1) | ||
| Fri | Jan 2 | Stain Hardwood Stairs (1) * | ||
| Mon | Jan 5 | C.O. to Lender (0) | ||
| Mon | Jan 5 | Schedule Closing (0) | ||
| Mon | Jan 5 | Payment for Upgrades (0) | ||
| Mon | Jan 5 | Keys to Settlement Agent (0) | ||
| Mon | Jan 5 | Review Settlement Statement (0) | ||
| Mon | Jan 5 | Jerry Signs Closing Documents (0) | ||
| Mon | Jan 5 | Request Trash Tote From POA Manager (0) | ||
| Mon | Jan 5 | Remove Coded Lockbox (0) | ||
| -- | -- | Pearl Vinyl, Gold Door | ||
| -- | -- | Re-install shower in master | ||
| -- | -- | Install hardwood stairs | ||
| -- | -- | Drywall guy finish stair wall. | ||
| -- | -- | Stairs set for carpet...needs to be hardwood | Raise up board 3/4- bill today | |
| -- | -- | 1/5 Harry hooking up heat today | ||
| -- | -- | Dip in floor at top of stairs | On main level | |
| -- | -- | Clean out garage | ||
| -- | -- | Please cover hardwood completely | ||
| -- | -- | Hardwood issue in master bedroom | ||
| -- | -- | Hole under sink | ||
| -- | -- | Hardwood uneven at top of stairs | ||
| -- | -- | Propane tank (buyer) | ||
| -- | -- | Connect stove to propane (propane company) | ||
| -- | -- | Schedule drywall repairs for Friday | 1/30: Tom will follow up | |
| -- | -- | Install tank | Tom 1/26 | |
| -- | -- | Cleaning | ||
| -- | -- | Window Screens | ||
| -- | -- | Hardwood touch up | ||
| -- | -- | Paint touch up | ||
| -- | -- | Shower head hall bathroom | ||
| -- | -- | Scratch/crack in tub hall bathroom | ||
| -- | -- | Paint touch up in pantry behind corner | ||
| -- | -- | Hole in floor bonus room | ||
| -- | -- | Weathers stripping front door | ||
| -- | -- | Nails at stair threshold at top of stairs | ||
| -- | -- | Trim piece under top stair on first set of steps | ||
| -- | -- | Finish sweeping out garage | ||
| -- | -- | Sewer cap back porch | ||
| -- | -- | Replace drawer in kitchen | ||
| -- | -- | Replace door in kit gen | ||
| -- | -- | Give keys and purse to Scott | ||
| -- | -- | Panel cover in garage | ||
| -- | -- | Flooring touch ups | ||
| -- | -- | Fill hole in cement floor behind garage | ||
| -- | -- | Caulking | ||
| -- | -- | Building Permit (30) * | ||
| -- | -- | Order Roof & Floor Trusses (1) | ||
| -- | -- | Order Windows & Doors (0) | ||
| -- | -- | Stake Out Home (1) | ||
| -- | -- | Excavate (2) | Monday May 16 | |
| -- | -- | Inspection (Footers) (1) | ||
| -- | -- | Pour Footers (1) * | ||
| -- | -- | Set Forms (2) | ||
| -- | -- | Pour Foundation Walls (1) | ||
| -- | -- | Plumb Slab (2) | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) | ||
| -- | -- | Prepare Slab (1) | ||
| -- | -- | Inspection (Slab) (1) | ||
| -- | -- | Pour Slab (1) * | ||
| -- | -- | Framing I (9) | K: in process | |
| -- | -- | Order Steps (0) | ||
| -- | -- | Framing II (8) | ||
| -- | -- | Framing III (8) * | ||
| -- | -- | Windows & Doors (0) * | Hopefully Monday 9–26 | |
| -- | -- | Roofing (0) * | ||
| -- | -- | Order Cabinets (0) | ||
| -- | -- | Deck (0) | ||
| -- | -- | Gutters (0) | ||
| -- | -- | Driveway (0) * | ||
| -- | -- | Privacy Divider / Fence (0) * | ||
| -- | -- | Sod / Seed / Landscaping (0) | ||
| -- | -- | HVAC Rough In (4) | ||
| -- | -- | Plumbing Rough In (4) | Will be complete 11/1 | |
| -- | -- | Electric Rough In (4) | Beginning Tuesday 11/15 | |
| -- | -- | Inspection (Rough In HVAC) (1) | 11/29 | |
| -- | -- | Exterior Vinyl (0) * | ||
| -- | -- | Insulation (2) * | ||
| -- | -- | Inspection (Insulation) (1) | ||
| -- | -- | Inspection (Electric Service) (0) | ||
| -- | -- | Inspection (Main Sewer Line) (0) | ||
| -- | -- | Order Interior Doors & Trim (0) | ||
| -- | -- | Drywall (Hang) (4) * | ||
| -- | -- | Drywall (Tape, Block, Skim, Sand) (6) * | Done by Thu, Dec 15 | |
| -- | -- | Paint 1 (1) | Fri, Dec 16 | |
| -- | -- | House Numbers (0) | ||
| -- | -- | Cabinet Installation (2) * | Deliver Dec 22, Install Dec 27 | |
| -- | -- | Granite Installation (1) * | 1/17 install | |
| -- | -- | Interior Trim - Install (3) * | Mon, Dec 19 | |
| -- | -- | Luxury Vinyl Plank (3) * | ||
| -- | -- | Luxury Vinyl Tile (0) | ||
| -- | -- | Paint 2 (3) | Friday | |
| -- | -- | Shelving, Door Knobs, Fire Extinguisher (0) * | Nearly complete | |
| -- | -- | Install Coded Lockbox (add extra keys) (0) | ||
| -- | -- | Pay Water / Sewer Taps (0) | ||
| -- | -- | Electric Trim Out (3) * | Just covers left- texted Harry to complete | |
| -- | -- | HVAC Trim Out (1) * | ||
| -- | -- | Plumbing Trim Out (2) * | In process- hopefully will be complete today 1/26 | |
| -- | -- | Install Appliances (0) * | Need to set range | |
| -- | -- | Carpet (2) | ||
| -- | -- | Inspection (Final Building) (2) * | Tuesday 1/31 | |
| -- | -- | Pre Walk Through (0) | Wednesday 2/1 | |
| -- | -- | Cleaning (1) | Hopefully Sunday-Monday. | |
| -- | -- | Certificate of Occupancy (1) * | ||
| -- | -- | Buyer Walk Through (1) * | ||
| -- | -- | Closing (1) | ||