ADDR
- 109  ::  2246 Lapis Lane
[ BUILD: 16040116 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Inspection (Concrete Wall) (1)      
Wed    Dec 17      Inspection (Conduit Under Slab) (1)      
Thu    Dec 18      Inspection (Drain Tile) (0)      
Thu    Dec 18      Settlement Agent Confirmed (0)      
Thu    Dec 18      Order Tubs / Showers (0)      
Thu    Dec 18      Verify Window & Roof Structure (0)      
Thu    Dec 18      Install Stairs (0) *       
Thu    Dec 18      House Number and Status in Window (0)      
Thu    Dec 18      Order Appliances (0)      
Thu    Dec 18      Patio (0)      
Thu    Dec 18      Rough In Microwave Vent (0)      
Thu    Dec 18      Inspection (Rough In Plumbing) (1)      
Fri    Dec 19      Inspection (Rough In Electric) (1)      
Mon    Dec 22      Inspection (Framing) (1) *       
Tue    Dec 23      Inspection (Deck Piers) (0)      
Tue    Dec 23      Exterior Stone (0)      
Tue    Dec 23      Set Electric Meter (0) *       
Tue    Dec 23      Inspection (Main Water Line) (0)      
Tue    Dec 23      Loan Approval (0)      
Tue    Dec 23      Deed Preparation (0)      
Tue    Dec 23      Garage Door (0)      
Tue    Dec 23      Mailbox (0)      
Tue    Dec 23      Order Plumbing / Lighting Fixtures (0)      
Tue    Dec 23      Interior Trim - Paint (1)      
Wed    Dec 24      Cover Floors (1)      
Thu    Dec 25      Deliver Plumbing / Lighting Fixtures (0)      
Thu    Dec 25      Shoe Moulding (0)      
Thu    Dec 25      Set Water Meter (0) *       
Thu    Dec 25      Ceiling Fans (0)      
Thu    Dec 25      Blower Door Test (1)      
Fri    Dec 26      Paint 3 (2) *       
Tue    Dec 30      Appraiser Confirms Construction Completion (0)      
Tue    Dec 30      Inspection (Final HVAC) (1)      
Wed    Dec 31      Inspection (Final Plumbing) (1)      
Thu    Jan 1      Inspection (Final Electric) (1)      
Fri    Jan 2      Stain Hardwood Stairs (1) *       
Mon    Jan 5      C.O. to Lender (0)      
Mon    Jan 5      Schedule Closing (0)      
Mon    Jan 5      Payment for Upgrades (0)      
Mon    Jan 5      Keys to Settlement Agent (0)      
Mon    Jan 5      Review Settlement Statement (0)      
Mon    Jan 5      Jerry Signs Closing Documents (0)      
Mon    Jan 5      Request Trash Tote From POA Manager (0)      
Mon    Jan 5      Remove Coded Lockbox (0)      
--   --   Pearl Vinyl, Gold Door
--   --   Re-install shower in master
--   --   Install hardwood stairs
--   --   Drywall guy finish stair wall.
--   --   Stairs set for carpet...needs to be hardwood Raise up board 3/4- bill today
--   --   1/5 Harry hooking up heat today
--   --   Dip in floor at top of stairs On main level
--   --   Clean out garage
--   --   Please cover hardwood completely
--   --   Hardwood issue in master bedroom
--   --   Hole under sink
--   --   Hardwood uneven at top of stairs
--   --   Propane tank (buyer)
--   --   Connect stove to propane (propane company)
--   --   Schedule drywall repairs for Friday 1/30: Tom will follow up
--   --   Install tank Tom 1/26
--   --   Cleaning
--   --   Window Screens
--   --   Hardwood touch up
--   --   Paint touch up
--   --   Shower head hall bathroom
--   --   Scratch/crack in tub hall bathroom
--   --   Paint touch up in pantry behind corner
--   --   Hole in floor bonus room
--   --   Weathers stripping front door
--   --   Nails at stair threshold at top of stairs
--   --   Trim piece under top stair on first set of steps
--   --   Finish sweeping out garage
--   --   Sewer cap back porch
--   --   Replace drawer in kitchen
--   --   Replace door in kit gen
--   --   Give keys and purse to Scott
--   --   Panel cover in garage
--   --   Flooring touch ups
--   --   Fill hole in cement floor behind garage
--   --   Caulking
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)       Monday May 16
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       K: in process
-- -- Order Steps (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Windows & Doors (0) *        Hopefully Monday 9–26
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)       Will be complete 11/1
-- -- Electric Rough In (4)       Beginning Tuesday 11/15
-- -- Inspection (Rough In HVAC) (1)       11/29
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Done by Thu, Dec 15
-- -- Paint 1 (1)       Fri, Dec 16
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Deliver Dec 22, Install Dec 27
-- -- Granite Installation (1) *        1/17 install
-- -- Interior Trim - Install (3) *        Mon, Dec 19
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)       Friday
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        Nearly complete
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3) *        Just covers left- texted Harry to complete
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *        In process- hopefully will be complete today 1/26
-- -- Install Appliances (0) *        Need to set range
-- -- Carpet (2)      
-- -- Inspection (Final Building) (2) *        Tuesday 1/31
-- -- Pre Walk Through (0)       Wednesday 2/1
-- -- Cleaning (1)       Hopefully Sunday-Monday.
-- -- Certificate of Occupancy (1) *       
-- -- Buyer Walk Through (1) *       
-- -- Closing (1)