- 109  ::  2246 Lapis Lane
[ BUILD: 16040116 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Order Tubs / Showers (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Install Stairs (0)      
Mon    Dec 2      House Number and Status in Window (0)      
Mon    Dec 2      Order Appliances (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Garage Door (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Order Plumbing / Lighting Fixtures (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Cover Floors (1)      
Mon    Dec 9      Deliver Plumbing / Lighting Fixtures (0)      
Mon    Dec 9      Shoe Moulding (0)      
Mon    Dec 9      Set Water Meter (0)      
Mon    Dec 9      Ceiling Fans (0)      
Mon    Dec 9      Blower Door Test (1)      
Tue    Dec 10      Paint 3 (2) *       
Thu    Dec 12      Appraiser Confirms Construction Completion (0)      
Thu    Dec 12      Inspection (Final HVAC) (1)      
Fri    Dec 13      Inspection (Final Plumbing) (1)      
Mon    Dec 16      Inspection (Final Electric) (1)      
Tue    Dec 17      Stain Hardwood Stairs (1)      
Wed    Dec 18      C.O. to Lender (0)      
Wed    Dec 18      Schedule Closing (0)      
Wed    Dec 18      Payment for Upgrades (0)      
Wed    Dec 18      Keys to Settlement Agent (0)      
Wed    Dec 18      Review Settlement Statement (0)      
Wed    Dec 18      Jerry Signs Closing Documents (0)      
Wed    Dec 18      Request Trash Tote From POA Manager (0)      
Wed    Dec 18      Remove Coded Lockbox (0)      
--   --   Pearl Vinyl, Gold Door
--   --   Re-install shower in master
--   --   Install hardwood stairs
--   --   Drywall guy finish stair wall.
--   --   Stairs set for carpet...needs to be hardwood Raise up board 3/4- bill today
--   --   1/5 Harry hooking up heat today
--   --   Dip in floor at top of stairs On main level
--   --   Clean out garage
--   --   Please cover hardwood completely
--   --   Hardwood issue in master bedroom
--   --   Hole under sink
--   --   Hardwood uneven at top of stairs
--   --   Propane tank (buyer)
--   --   Connect stove to propane (propane company)
--   --   Schedule drywall repairs for Friday 1/30: Tom will follow up
--   --   Install tank Tom 1/26
--   --   Cleaning
--   --   Window Screens
--   --   Hardwood touch up
--   --   Paint touch up
--   --   Shower head hall bathroom
--   --   Scratch/crack in tub hall bathroom
--   --   Paint touch up in pantry behind corner
--   --   Hole in floor bonus room
--   --   Weathers stripping front door
--   --   Nails at stair threshold at top of stairs
--   --   Trim piece under top stair on first set of steps
--   --   Finish sweeping out garage
--   --   Sewer cap back porch
--   --   Replace drawer in kitchen
--   --   Replace door in kit gen
--   --   Give keys and purse to Scott
--   --   Panel cover in garage
--   --   Flooring touch ups
--   --   Fill hole in cement floor behind garage
--   --   Caulking
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)       Monday May 16
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       K: in process
-- -- Order Steps (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Windows & Doors (0)       Hopefully Monday 9–26
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)      
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       11/29
-- -- Plumbing Rough In (4)       Will be complete 11/1
-- -- Electric Rough In (4)       Beginning Tuesday 11/15
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2)      
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Done by Thu, Dec 15
-- -- Paint 1 (1)       Fri, Dec 16
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Deliver Dec 22, Install Dec 27
-- -- Granite Installation (1) *        1/17 install
-- -- Interior Trim - Install (3)       Mon, Dec 19
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)       Friday
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       Nearly complete
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3)       Just covers left- texted Harry to complete
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       In process- hopefully will be complete today 1/26
-- -- Install Appliances (0) *        Need to set range
-- -- Carpet (2)      
-- -- Inspection (Final Building) (2) *        Tuesday 1/31
-- -- Pre Walk Through (0)       Wednesday 2/1
-- -- Cleaning (1)       Hopefully Sunday-Monday.
-- -- Certificate of Occupancy (1) *       
-- -- Buyer Walk Through (1)      
-- -- Closing (1)