ADDR
- 90  ::  342 Sapphire Drive
[ BUILD: 16060051 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Stake property corners for fence? TOM TO DO THIS. Kate to let Drake know and follow up w/Tom
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Order Appliances (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Order Plumbing / Lighting Fixtures (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Set Water Meter (0)      
Fri    Dec 6      Ceiling Fans (0)      
Fri    Dec 6      Blower Door Test (1)      
Mon    Dec 9      Inspection (Final HVAC) (1)      
Tue    Dec 10      Inspection (Final Plumbing) (1)      
Wed    Dec 11      Inspection (Final Electric) (1)      
Thu    Dec 12      Stain Hardwood Stairs (1)      
Fri    Dec 13      Schedule Closing (0)      
Fri    Dec 13      Keys to Settlement Agent (0)      
Fri    Dec 13      Review Settlement Statement (0)      
Fri    Dec 13      Jerry Signs Closing Documents (0)      
Fri    Dec 13      Request Trash Tote From POA Manager (0)      
Fri    Dec 13      Remove Coded Lockbox (0)      
--   --   Charleston Brick, Bone Vinyl, Green Door
--   --   Enlarge deck Yes?
--   --   Mitch- trim hand rai rounded edges on stairs
--   --   Buyer to tag slab
--   --   Mitch- trim hand rai rounded edges on stairs
--   --   Mitch- trim hand rail rounded edges on stairs
--   --   Tom please flag back yard
--   --   Seal grout Osbaldo to do
--   --   Deck Repairs? 7/3- looks to me like some work still needs to be done
--   --   Alert lender (Scott Brown) of when to send appraiser back out
--   --   Install door knobs (for radon test)
--   --   Siding Repair Osbaldo
--   --   Need access panel in master closet
--   --   Need hand railing on stairs
--   --   Paint touch up 7/5
--   --   Reinstall Correct Lighting Harry - Monday morning
--   --   Final Paint Thursday
--   --  
--   --  
--   --  
--   --   Remove and re-hang pantry shelving Osbaldo
--   --   Install missing light fixtures Tuesday
--   --   Repair microwave (dent)
--   --   CODED LOCKBOX --- 6465
--   --  
--   --   Remove post from temporary electric service
-- -- Building Permit (30)       Need to apply first
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       8/29 in process
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)       In process
-- -- Framing III (8) *        9/19 setting stairs and finishing punch out today
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)       9/19 almost complete
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)      
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       2/13 some materials on site
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)       2/13 in process
-- -- Electric Rough In (4)       Will be complete by 3/14
-- -- Exterior Vinyl (0) *        Brick done vinyl needed
-- -- Insulation (2)       3/20 in process
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        In process
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Finish sanding Wednesday afternoon 4/5
-- -- Paint 1 (1)       Thursday morning 4/6
-- -- Garage Door (0)      
-- -- House Numbers (0)       Fire extinguisher only
-- -- Cabinet Installation (2) *        install through Wednesday 5/3
-- -- Granite Installation (1) *        Thu, May 11- (not installed?)
-- -- Interior Trim - Install (3)       Beginning 5/10 (when Mitch is complete with 112) remind Mitch- round edges
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       In process as of 5/11
-- -- Paint 2 (3)       6/6
-- -- Cover Floors (1)       5/26 osbaldo
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       6/26-6/27
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3)       Beginning 6/27-6/30
-- -- HVAC Trim Out (1)       Fri, Jun 30
-- -- Plumbing Trim Out (2)       Fri, Jun 16
-- -- Install Appliances (0) *        Getting date from Amy
-- -- Paint 3 (2) *       
-- -- Carpet (2)       Mon, June 5
-- -- Appraiser Confirms Construction Completion (0)       Tell Scott Brown when to send appraiser back out
-- -- Inspection (Final Building) (2) *        7/5
-- -- Pre Walk Through (0)       Thursday7/6- osbaldo Tom Mindy
-- -- Cleaning (1)       7/7-7/9- Cheryl
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1)       Wednesday
-- -- Payment for Upgrades (0)      
-- -- Closing (1)