- 90  ::  342 Sapphire Drive
[ BUILD: 16060051 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Stake property corners for fence? TOM TO DO THIS. Kate to let Drake know and follow up w/Tom
Tue    Apr 29      Ratified Contract? (0)      
Tue    Apr 29      $2500 Deposit Received (0)      
Tue    Apr 29      Association Packet Requested (0)      
Tue    Apr 29      Association Packet Received (0)      
Tue    Apr 29      Selections Meeting (0)      
Tue    Apr 29      Selections Sheet Signed (0)      
Tue    Apr 29      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Apr 29      Deposit For Upgrades Received (0)      
Tue    Apr 29      Inspection (Concrete Wall) (1)      
Wed    Apr 30      Inspection (Conduit Under Slab) (1)      
Thu    May 1      Inspection (Drain Tile) (0)      
Thu    May 1      Settlement Agent Confirmed (0)      
Thu    May 1      Verify Window & Roof Structure (0)      
Thu    May 1      Order Appliances (0)      
Thu    May 1      Patio (0)      
Thu    May 1      Rough In Microwave Vent (0)      
Thu    May 1      Inspection (Rough In Plumbing) (1)      
Fri    May 2      Inspection (Rough In Electric) (1)      
Mon    May 5      Inspection (Deck Piers) (0)      
Mon    May 5      Inspection (Framing) (1) *       
Tue    May 6      Exterior Stone (0)      
Tue    May 6      Set Electric Meter (0) *       
Tue    May 6      Inspection (Main Water Line) (0)      
Tue    May 6      Loan Approval (0)      
Tue    May 6      Deed Preparation (0)      
Tue    May 6      Mailbox (0)      
Tue    May 6      Order Plumbing / Lighting Fixtures (0)      
Tue    May 6      Interior Trim - Paint (1)      
Wed    May 7      Set Water Meter (0) *       
Wed    May 7      Ceiling Fans (0)      
Wed    May 7      Blower Door Test (1)      
Thu    May 8      Inspection (Final HVAC) (1)      
Fri    May 9      Inspection (Final Plumbing) (1)      
Mon    May 12      Inspection (Final Electric) (1)      
Tue    May 13      Stain Hardwood Stairs (1)      
Wed    May 14      Schedule Closing (0)      
Wed    May 14      Keys to Settlement Agent (0)      
Wed    May 14      Review Settlement Statement (0)      
Wed    May 14      Jerry Signs Closing Documents (0)      
Wed    May 14      Request Trash Tote From POA Manager (0)      
Wed    May 14      Remove Coded Lockbox (0)      
--   --   Charleston Brick, Bone Vinyl, Green Door
--   --   Enlarge deck Yes?
--   --   Mitch- trim hand rai rounded edges on stairs
--   --   Buyer to tag slab
--   --   Mitch- trim hand rai rounded edges on stairs
--   --   Mitch- trim hand rail rounded edges on stairs
--   --   Tom please flag back yard
--   --   Seal grout Osbaldo to do
--   --   Deck Repairs? 7/3- looks to me like some work still needs to be done
--   --   Alert lender (Scott Brown) of when to send appraiser back out
--   --   Install door knobs (for radon test)
--   --   Siding Repair Osbaldo
--   --   Need access panel in master closet
--   --   Need hand railing on stairs
--   --   Paint touch up 7/5
--   --   Reinstall Correct Lighting Harry - Monday morning
--   --   Final Paint Thursday
--   --  
--   --  
--   --  
--   --   Remove and re-hang pantry shelving Osbaldo
--   --   Install missing light fixtures Tuesday
--   --   Repair microwave (dent)
--   --   CODED LOCKBOX --- 6465
--   --  
--   --   Remove post from temporary electric service
-- -- Building Permit (30)       Need to apply first
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       8/29 in process
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)       In process
-- -- Framing III (8) *        9/19 setting stairs and finishing punch out today
-- -- Install Stairs (0)      
-- -- Windows & Doors (0) *        9/19 almost complete
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       2/13 some materials on site
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)       2/13 in process
-- -- Electric Rough In (4)       Will be complete by 3/14
-- -- Exterior Vinyl (0) *        Brick done vinyl needed
-- -- Insulation (2) *        3/20 in process
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        In process
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Finish sanding Wednesday afternoon 4/5
-- -- Paint 1 (1)       Thursday morning 4/6
-- -- Garage Door (0) *       
-- -- House Numbers (0)       Fire extinguisher only
-- -- Cabinet Installation (2) *        install through Wednesday 5/3
-- -- Granite Installation (1) *        Thu, May 11- (not installed?)
-- -- Interior Trim - Install (3) *        Beginning 5/10 (when Mitch is complete with 112) remind Mitch- round edges
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       In process as of 5/11
-- -- Paint 2 (3)       6/6
-- -- Cover Floors (1)       5/26 osbaldo
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        6/26-6/27
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3)       Beginning 6/27-6/30
-- -- HVAC Trim Out (1)       Fri, Jun 30
-- -- Plumbing Trim Out (2)       Fri, Jun 16
-- -- Install Appliances (0) *        Getting date from Amy
-- -- Paint 3 (2) *       
-- -- Carpet (2)       Mon, June 5
-- -- Appraiser Confirms Construction Completion (0)       Tell Scott Brown when to send appraiser back out
-- -- Inspection (Final Building) (2) *        7/5
-- -- Pre Walk Through (0)       Thursday7/6- osbaldo Tom Mindy
-- -- Cleaning (1)       7/7-7/9- Cheryl
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1)       Wednesday
-- -- Payment for Upgrades (0)      
-- -- Closing (1)