Stake property corners for fence? |
TOM TO DO THIS. Kate to let Drake know and follow up w/Tom |
|
Fri |
Sep 20 |
Ratified Contract? (0)
|
|
|
Fri |
Sep 20 |
$2500 Deposit Received (0)
|
|
|
Fri |
Sep 20 |
Association Packet Requested (0)
|
|
|
Fri |
Sep 20 |
Association Packet Received (0)
|
|
|
Fri |
Sep 20 |
Selections Meeting (0)
|
|
|
Fri |
Sep 20 |
Selections Sheet Signed (0)
|
|
|
Fri |
Sep 20 |
Amendment for Upgrades (B,S,L,T,BCP) (0)
|
|
|
Fri |
Sep 20 |
Deposit For Upgrades Received (0)
|
|
|
Fri |
Sep 20 |
Inspection (Concrete Wall) (1)
|
|
|
Mon |
Sep 23 |
Inspection (Conduit Under Slab) (1)
|
|
|
Tue |
Sep 24 |
Inspection (Drain Tile) (0)
|
|
|
Tue |
Sep 24 |
Settlement Agent Confirmed (0)
|
|
|
Tue |
Sep 24 |
Verify Window & Roof Structure (0)
|
|
|
Tue |
Sep 24 |
Order Appliances (0)
|
|
|
Tue |
Sep 24 |
Patio (0)
|
|
|
Tue |
Sep 24 |
Rough In Microwave Vent (0)
|
|
|
Tue |
Sep 24 |
Inspection (Rough In Plumbing) (1)
|
|
|
Wed |
Sep 25 |
Inspection (Rough In Electric) (1)
|
|
|
Thu |
Sep 26 |
Inspection (Deck Piers) (0)
|
|
|
Thu |
Sep 26 |
Inspection (Framing) (1)
|
|
|
Fri |
Sep 27 |
Exterior Stone (0)
|
|
|
Fri |
Sep 27 |
Set Electric Meter (0)
|
|
|
Fri |
Sep 27 |
Inspection (Main Water Line) (0)
|
|
|
Fri |
Sep 27 |
Loan Approval (0)
|
|
|
Fri |
Sep 27 |
Deed Preparation (0)
|
|
|
Fri |
Sep 27 |
Mailbox (0)
|
|
|
Fri |
Sep 27 |
Order Plumbing / Lighting Fixtures (0)
|
|
|
Fri |
Sep 27 |
Interior Trim - Paint (1)
|
|
|
Mon |
Sep 30 |
Set Water Meter (0)
|
|
|
Mon |
Sep 30 |
Ceiling Fans (0)
|
|
|
Mon |
Sep 30 |
Blower Door Test (1)
|
|
|
Tue |
Oct 1 |
Inspection (Final HVAC) (1)
|
|
|
Wed |
Oct 2 |
Inspection (Final Plumbing) (1)
|
|
|
Thu |
Oct 3 |
Inspection (Final Electric) (1)
|
|
|
Fri |
Oct 4 |
Stain Hardwood Stairs (1)
|
|
|
Mon |
Oct 7 |
Schedule Closing (0)
|
|
|
Mon |
Oct 7 |
Keys to Settlement Agent (0)
|
|
|
Mon |
Oct 7 |
Review Settlement Statement (0)
|
|
|
Mon |
Oct 7 |
Jerry Signs Closing Documents (0)
|
|
|
Mon |
Oct 7 |
Request Trash Tote From POA Manager (0)
|
|
|
Mon |
Oct 7 |
Remove Coded Lockbox (0)
|
|
|
|
-- |
-- |
Charleston Brick, Bone Vinyl, Green Door |
|
|
-- |
-- |
Enlarge deck |
Yes? |
|
-- |
-- |
Mitch- trim hand rai rounded edges on stairs |
|
|
-- |
-- |
Buyer to tag slab |
|
|
-- |
-- |
Mitch- trim hand rai rounded edges on stairs |
|
|
-- |
-- |
Mitch- trim hand rail rounded edges on stairs |
|
|
-- |
-- |
Tom please flag back yard |
|
|
-- |
-- |
Seal grout |
Osbaldo to do |
|
-- |
-- |
Deck Repairs? |
7/3- looks to me like some work still needs to be done |
|
-- |
-- |
Alert lender (Scott Brown) of when to send appraiser back out |
|
|
-- |
-- |
Install door knobs (for radon test) |
|
|
-- |
-- |
Siding Repair |
Osbaldo |
|
-- |
-- |
Need access panel in master closet |
|
|
-- |
-- |
Need hand railing on stairs |
|
|
-- |
-- |
Paint touch up |
7/5 |
|
-- |
-- |
Reinstall Correct Lighting |
Harry - Monday morning |
|
-- |
-- |
Final Paint |
Thursday |
|
-- |
-- |
|
|
|
-- |
-- |
|
|
|
-- |
-- |
|
|
|
-- |
-- |
Remove and re-hang pantry shelving |
Osbaldo |
|
-- |
-- |
Install missing light fixtures |
Tuesday |
|
-- |
-- |
Repair microwave (dent) |
|
|
-- |
-- |
CODED LOCKBOX --- 6465 |
|
|
-- |
-- |
|
|
|
-- |
-- |
Remove post from temporary electric service |
|
|
-- |
-- |
Building Permit (30)
|
Need to apply first |
|
-- |
-- |
Order Roof & Floor Trusses (1)
|
|
|
-- |
-- |
Order Windows & Doors (0)
|
|
|
-- |
-- |
Stake Out Home (1)
|
|
|
-- |
-- |
Excavate (2)
|
|
|
-- |
-- |
Inspection (Footers) (1)
|
|
|
-- |
-- |
Pour Footers (1)
|
|
|
-- |
-- |
Set Forms (2)
|
|
|
-- |
-- |
Pour Foundation Walls (1)
|
|
|
-- |
-- |
Plumb Slab (2)
|
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1)
|
|
|
-- |
-- |
Prepare Slab (1)
|
|
|
-- |
-- |
Inspection (Slab) (1)
|
|
|
-- |
-- |
Pour Slab (1)
|
|
|
-- |
-- |
Framing I (9)
|
8/29 in process |
|
-- |
-- |
Order Steps (0)
|
|
|
-- |
-- |
Order Tubs / Showers (0)
|
|
|
-- |
-- |
Framing II (8)
|
In process |
|
-- |
-- |
Framing III (8)
|
9/19 setting stairs and finishing punch out today |
|
-- |
-- |
Install Stairs (0)
|
|
|
-- |
-- |
Windows & Doors (0)
|
9/19 almost complete |
|
-- |
-- |
House Number and Status in Window (0)
|
|
|
-- |
-- |
Roofing (0)
|
|
|
-- |
-- |
Order Cabinets (0)
|
|
|
-- |
-- |
Deck (0)
|
|
|
-- |
-- |
Gutters (0)
|
|
|
-- |
-- |
Driveway (0)
|
|
|
-- |
-- |
Privacy Divider / Fence (0)
|
|
|
-- |
-- |
Sod / Seed / Landscaping (0)
|
|
|
-- |
-- |
HVAC Rough In (4)
|
2/13 some materials on site |
|
-- |
-- |
Inspection (Rough In HVAC) (1)
|
|
|
-- |
-- |
Plumbing Rough In (4)
|
2/13 in process |
|
-- |
-- |
Electric Rough In (4)
|
Will be complete by 3/14 |
|
-- |
-- |
Exterior Vinyl (0)
|
Brick done vinyl needed |
|
-- |
-- |
Insulation (2)
|
3/20 in process |
|
-- |
-- |
Inspection (Insulation) (1)
|
|
|
-- |
-- |
Inspection (Electric Service) (0)
|
|
|
-- |
-- |
Inspection (Main Sewer Line) (0)
|
|
|
-- |
-- |
Order Interior Doors & Trim (0)
|
|
|
-- |
-- |
Drywall (Hang) (4)
|
In process |
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6)
|
Finish sanding Wednesday afternoon 4/5 |
|
-- |
-- |
Paint 1 (1)
|
Thursday morning 4/6 |
|
-- |
-- |
Garage Door (0)
|
|
|
-- |
-- |
House Numbers (0)
|
Fire extinguisher only |
|
-- |
-- |
Cabinet Installation (2)
|
install through Wednesday 5/3 |
|
-- |
-- |
Granite Installation (1)
|
Thu, May 11- (not installed?) |
|
-- |
-- |
Interior Trim - Install (3)
|
Beginning 5/10 (when Mitch is complete with 112) remind Mitch- round edges |
|
-- |
-- |
Luxury Vinyl Plank (3)
|
|
|
-- |
-- |
Luxury Vinyl Tile (0)
|
In process as of 5/11 |
|
-- |
-- |
Paint 2 (3)
|
6/6 |
|
-- |
-- |
Cover Floors (1)
|
5/26 osbaldo |
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0)
|
|
|
-- |
-- |
Shoe Moulding (0)
|
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0)
|
6/26-6/27 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0)
|
|
|
-- |
-- |
Pay Water / Sewer Taps (0)
|
|
|
-- |
-- |
Electric Trim Out (3)
|
Beginning 6/27-6/30 |
|
-- |
-- |
HVAC Trim Out (1)
|
Fri, Jun 30 |
|
-- |
-- |
Plumbing Trim Out (2)
|
Fri, Jun 16 |
|
-- |
-- |
Install Appliances (0)
|
Getting date from Amy |
|
-- |
-- |
Paint 3 (2)
|
|
|
-- |
-- |
Carpet (2)
|
Mon, June 5 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0)
|
Tell Scott Brown when to send appraiser back out |
|
-- |
-- |
Inspection (Final Building) (2)
|
7/5 |
|
-- |
-- |
Pre Walk Through (0)
|
Thursday7/6- osbaldo Tom Mindy |
|
-- |
-- |
Cleaning (1)
|
7/7-7/9- Cheryl |
|
-- |
-- |
Certificate of Occupancy (1)
|
|
|
-- |
-- |
C.O. to Lender (0)
|
|
|
-- |
-- |
Buyer Walk Through (1)
|
Wednesday |
|
-- |
-- |
Payment for Upgrades (0)
|
|
|
-- |
-- |
Closing (1)
|
|
|