--   --   Stake property corners for fence? TOM TO DO THIS. Kate to let Drake know and follow up w/Tom
Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Inspection (Concrete Wall) (1)      
Wed    Dec 17      Inspection (Conduit Under Slab) (1)      
Thu    Dec 18      Inspection (Drain Tile) (0)      
Thu    Dec 18      Settlement Agent Confirmed (0)      
Thu    Dec 18      Verify Window & Roof Structure (0)      
Thu    Dec 18      Order Appliances (0)      
Thu    Dec 18      Patio (0)      
Thu    Dec 18      Rough In Microwave Vent (0)      
Thu    Dec 18      Inspection (Rough In Plumbing) (1)      
Fri    Dec 19      Inspection (Rough In Electric) (1)      
Mon    Dec 22      Inspection (Framing) (1) *       
Tue    Dec 23      Inspection (Deck Piers) (0)      
Tue    Dec 23      Exterior Stone (0)      
Tue    Dec 23      Set Electric Meter (0) *       
Tue    Dec 23      Inspection (Main Water Line) (0)      
Tue    Dec 23      Loan Approval (0)      
Tue    Dec 23      Deed Preparation (0)      
Tue    Dec 23      Mailbox (0)      
Tue    Dec 23      Order Plumbing / Lighting Fixtures (0)      
Tue    Dec 23      Interior Trim - Paint (1)      
Wed    Dec 24      Set Water Meter (0) *       
Wed    Dec 24      Ceiling Fans (0)      
Wed    Dec 24      Blower Door Test (1)      
Thu    Dec 25      Inspection (Final HVAC) (1)      
Fri    Dec 26      Inspection (Final Plumbing) (1)      
Mon    Dec 29      Inspection (Final Electric) (1)      
Tue    Dec 30      Stain Hardwood Stairs (1) *       
Wed    Dec 31      Schedule Closing (0)      
Wed    Dec 31      Keys to Settlement Agent (0)      
Wed    Dec 31      Review Settlement Statement (0)      
Wed    Dec 31      Jerry Signs Closing Documents (0)      
Wed    Dec 31      Request Trash Tote From POA Manager (0)      
Wed    Dec 31      Remove Coded Lockbox (0)      
--   --   Charleston Brick, Bone Vinyl, Green Door
--   --   Enlarge deck Yes?
--   --   Mitch- trim hand rai rounded edges on stairs
--   --   Buyer to tag slab
--   --   Mitch- trim hand rai rounded edges on stairs
--   --   Mitch- trim hand rail rounded edges on stairs
--   --   Tom please flag back yard
--   --   Seal grout Osbaldo to do
--   --   Deck Repairs? 7/3- looks to me like some work still needs to be done
--   --   Alert lender (Scott Brown) of when to send appraiser back out
--   --   Install door knobs (for radon test)
--   --   Siding Repair Osbaldo
--   --   Need access panel in master closet
--   --   Need hand railing on stairs
--   --   Paint touch up 7/5
--   --   Reinstall Correct Lighting Harry - Monday morning
--   --   Final Paint Thursday
--   --  
--   --  
--   --  
--   --   Remove and re-hang pantry shelving Osbaldo
--   --   Install missing light fixtures Tuesday
--   --   Repair microwave (dent)
--   --   CODED LOCKBOX --- 6465
--   --  
--   --   Remove post from temporary electric service
-- -- Building Permit (30) *        Need to apply first
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       8/29 in process
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)       In process
-- -- Framing III (8) *        9/19 setting stairs and finishing punch out today
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *        9/19 almost complete
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       2/13 some materials on site
-- -- Plumbing Rough In (4)       2/13 in process
-- -- Electric Rough In (4)       Will be complete by 3/14
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *        Brick done vinyl needed
-- -- Insulation (2) *        3/20 in process
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        In process
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Finish sanding Wednesday afternoon 4/5
-- -- Paint 1 (1)       Thursday morning 4/6
-- -- Garage Door (0)      
-- -- House Numbers (0)       Fire extinguisher only
-- -- Cabinet Installation (2) *        install through Wednesday 5/3
-- -- Granite Installation (1) *        Thu, May 11- (not installed?)
-- -- Interior Trim - Install (3) *        Beginning 5/10 (when Mitch is complete with 112) remind Mitch- round edges
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       In process as of 5/11
-- -- Paint 2 (3)       6/6
-- -- Cover Floors (1)       5/26 osbaldo
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        6/26-6/27
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3) *        Beginning 6/27-6/30
-- -- HVAC Trim Out (1) *        Fri, Jun 30
-- -- Plumbing Trim Out (2) *        Fri, Jun 16
-- -- Install Appliances (0) *        Getting date from Amy
-- -- Paint 3 (2) *       
-- -- Carpet (2)       Mon, June 5
-- -- Appraiser Confirms Construction Completion (0)       Tell Scott Brown when to send appraiser back out
-- -- Inspection (Final Building) (2) *        7/5
-- -- Pre Walk Through (0)       Thursday7/6- osbaldo Tom Mindy
-- -- Cleaning (1)       7/7-7/9- Cheryl
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1) *        Wednesday
-- -- Payment for Upgrades (0)      
-- -- Closing (1)