| -- | -- | Need Certificate of Occupancy by June 14 | Hopefully by Friday 6/16 | |
| -- | -- | CLOSING TUES JUN 20 @ 2PM | ||
| -- | -- | Drywall patch in basement | ||
| -- | -- | Sweep out basement room | ||
| -- | -- | Need cover for communication box | ||
| -- | -- | Acess for wTer panel | ||
| Tue | Dec 16 | Ratified Contract? (0) | ||
| Tue | Dec 16 | $2500 Deposit Received (0) | ||
| Tue | Dec 16 | Association Packet Requested (0) | ||
| Tue | Dec 16 | Association Packet Received (0) | ||
| Tue | Dec 16 | Selections Meeting (0) | ||
| Tue | Dec 16 | Selections Sheet Signed (0) | ||
| Tue | Dec 16 | Amendment for Upgrades (B,S,L,T,BCP) (0) | ||
| Tue | Dec 16 | Deposit For Upgrades Received (0) | ||
| Tue | Dec 16 | Inspection (Concrete Wall) (1) | ||
| Wed | Dec 17 | Inspection (Conduit Under Slab) (1) | ||
| Thu | Dec 18 | Inspection (Drain Tile) (0) | ||
| Thu | Dec 18 | Settlement Agent Confirmed (0) | ||
| Thu | Dec 18 | Order Tubs / Showers (0) | ||
| Thu | Dec 18 | Verify Window & Roof Structure (0) | ||
| Thu | Dec 18 | Install Stairs (0) * | ||
| Thu | Dec 18 | House Number and Status in Window (0) | ||
| Thu | Dec 18 | Order Appliances (0) | ||
| Thu | Dec 18 | Patio (0) | ||
| Thu | Dec 18 | Rough In Microwave Vent (0) | ||
| Thu | Dec 18 | Inspection (Rough In Plumbing) (1) | ||
| Fri | Dec 19 | Inspection (Rough In Electric) (1) | ||
| Mon | Dec 22 | Inspection (Framing) (1) * | ||
| Tue | Dec 23 | Inspection (Deck Piers) (0) | ||
| Tue | Dec 23 | Exterior Stone (0) | ||
| Tue | Dec 23 | Set Electric Meter (0) * | ||
| Tue | Dec 23 | Inspection (Main Water Line) (0) | ||
| Tue | Dec 23 | Loan Approval (0) | ||
| Tue | Dec 23 | Deed Preparation (0) | ||
| Tue | Dec 23 | Garage Door (0) | ||
| Tue | Dec 23 | Mailbox (0) | ||
| Tue | Dec 23 | Order Plumbing / Lighting Fixtures (0) | ||
| Tue | Dec 23 | Interior Trim - Paint (1) | ||
| Wed | Dec 24 | Deliver Plumbing / Lighting Fixtures (0) | ||
| Wed | Dec 24 | Shoe Moulding (0) | ||
| Wed | Dec 24 | Shelving, Door Knobs, Fire Extinguisher (0) * | Finishing 6/15 | |
| Wed | Dec 24 | Set Water Meter (0) * | ||
| Wed | Dec 24 | Ceiling Fans (0) | ||
| Wed | Dec 24 | Blower Door Test (1) | ||
| Thu | Dec 25 | Paint 3 (2) * | ||
| Mon | Dec 29 | Appraiser Confirms Construction Completion (0) | ||
| Mon | Dec 29 | Inspection (Final HVAC) (1) | ||
| Tue | Dec 30 | Inspection (Final Plumbing) (1) | ||
| Wed | Dec 31 | Inspection (Final Electric) (1) | ||
| Thu | Jan 1 | Stain Hardwood Stairs (1) * | ||
| Fri | Jan 2 | Cleaning (1) | Sunday 6/18-29 | |
| Mon | Jan 5 | Certificate of Occupancy (1) * | ||
| Tue | Jan 6 | C.O. to Lender (0) | ||
| Tue | Jan 6 | Schedule Closing (0) | ||
| Tue | Jan 6 | Buyer Walk Through (1) * | ||
| Wed | Jan 7 | Payment for Upgrades (0) | ||
| Wed | Jan 7 | Keys to Settlement Agent (0) | ||
| Wed | Jan 7 | Review Settlement Statement (0) | ||
| Wed | Jan 7 | Jerry Signs Closing Documents (0) | ||
| Wed | Jan 7 | Request Trash Tote From POA Manager (0) | ||
| Wed | Jan 7 | Closing (1) | ||
| Thu | Jan 8 | Remove Coded Lockbox (0) | ||
| -- | -- | Portsmouth Brick, Country Beige Vinyl, Green Door | Paint front door | |
| -- | -- | Adjust door framing in the basement | ||
| -- | -- | Install fence? | ||
| -- | -- | Plant leiland cypress trees? | ||
| -- | -- | Appraiser Re-Visit | When Complete, 10 Days Prior to Closing | |
| -- | -- | Mitch shoemold today 5/25 | ||
| -- | -- | Appraiser needs to verify completion by June 10 | ||
| -- | -- | Install Basement Carpet | Thursday 6/15 | |
| -- | -- | Install kitchen shoemold | Friday 6/16 | |
| -- | -- | Final paint | Saturday 6/17 | |
| -- | -- | Building Permit (30) * | ||
| -- | -- | Order Roof & Floor Trusses (1) | ||
| -- | -- | Order Windows & Doors (0) | ||
| -- | -- | Stake Out Home (1) | ||
| -- | -- | Excavate (2) | ||
| -- | -- | Inspection (Footers) (1) | ||
| -- | -- | Pour Footers (1) * | ||
| -- | -- | Set Forms (2) | ||
| -- | -- | Pour Foundation Walls (1) | ||
| -- | -- | Plumb Slab (2) | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) | ||
| -- | -- | Prepare Slab (1) | ||
| -- | -- | Inspection (Slab) (1) | ||
| -- | -- | Pour Slab (1) * | ||
| -- | -- | Framing I (9) | In process | |
| -- | -- | Order Steps (0) | ||
| -- | -- | Framing II (8) | In process | |
| -- | -- | Framing III (8) * | 9/19 settings stairs and punch out today | |
| -- | -- | Windows & Doors (0) * | 9/19 nearly complete | |
| -- | -- | Roofing (0) * | ||
| -- | -- | Order Cabinets (0) | ||
| -- | -- | Deck (0) | ||
| -- | -- | Gutters (0) | ||
| -- | -- | Driveway (0) * | ||
| -- | -- | Privacy Divider / Fence (0) * | ||
| -- | -- | Sod / Seed / Landscaping (0) | ||
| -- | -- | HVAC Rough In (4) | ||
| -- | -- | Plumbing Rough In (4) | 10/24 done with all but tubs | |
| -- | -- | Electric Rough In (4) | 11/29 | |
| -- | -- | Inspection (Rough In HVAC) (1) | ||
| -- | -- | Exterior Vinyl (0) * | Brick done vinyl needed | |
| -- | -- | Insulation (2) * | 2/13 in process | |
| -- | -- | Inspection (Insulation) (1) | ||
| -- | -- | Inspection (Electric Service) (0) | ||
| -- | -- | Inspection (Main Sewer Line) (0) | ||
| -- | -- | Order Interior Doors & Trim (0) | ||
| -- | -- | Drywall (Hang) (4) * | ||
| -- | -- | Drywall (Tape, Block, Skim, Sand) (6) * | Finishing | |
| -- | -- | Paint 1 (1) | 3/6: Isaac coming soon; | |
| -- | -- | House Numbers (0) | ||
| -- | -- | Cabinet Installation (2) * | Del Mar 14, Install Mar 15 | |
| -- | -- | Granite Installation (1) * | ||
| -- | -- | Interior Trim - Install (3) * | Complete Monday 5/8 | |
| -- | -- | Luxury Vinyl Plank (3) * | ||
| -- | -- | Luxury Vinyl Tile (0) | Thursday 5/4 | |
| -- | -- | Paint 2 (3) | Friday 5/11 in process | |
| -- | -- | Cover Floors (1) | ||
| -- | -- | Install Coded Lockbox (add extra keys) (0) | ||
| -- | -- | Pay Water / Sewer Taps (0) | Mindy will get check; | |
| -- | -- | Electric Trim Out (3) * | 6/15 complete the morning | |
| -- | -- | HVAC Trim Out (1) * | June 12-13 | |
| -- | -- | Plumbing Trim Out (2) * | Ready now 6/12 | |
| -- | -- | Install Appliances (0) * | ||
| -- | -- | Carpet (2) | ||
| -- | -- | Inspection (Final Building) (2) * | Thurs, June 15 | |
| -- | -- | Pre Walk Through (0) | Today Thursday 6/15 | |