Need Certificate of Occupancy by June 14 |
Hopefully by Friday 6/16 |
|
-- |
-- |
CLOSING TUES JUN 20 @ 2PM |
|
|
-- |
-- |
Drywall patch in basement |
|
|
-- |
-- |
Sweep out basement room |
|
|
-- |
-- |
Need cover for communication box |
|
|
-- |
-- |
Acess for wTer panel |
|
|
Fri |
Sep 20 |
Ratified Contract? (0)
|
|
|
Fri |
Sep 20 |
$2500 Deposit Received (0)
|
|
|
Fri |
Sep 20 |
Association Packet Requested (0)
|
|
|
Fri |
Sep 20 |
Association Packet Received (0)
|
|
|
Fri |
Sep 20 |
Selections Meeting (0)
|
|
|
Fri |
Sep 20 |
Selections Sheet Signed (0)
|
|
|
Fri |
Sep 20 |
Amendment for Upgrades (B,S,L,T,BCP) (0)
|
|
|
Fri |
Sep 20 |
Deposit For Upgrades Received (0)
|
|
|
Fri |
Sep 20 |
Inspection (Concrete Wall) (1)
|
|
|
Mon |
Sep 23 |
Inspection (Conduit Under Slab) (1)
|
|
|
Tue |
Sep 24 |
Inspection (Drain Tile) (0)
|
|
|
Tue |
Sep 24 |
Settlement Agent Confirmed (0)
|
|
|
Tue |
Sep 24 |
Order Tubs / Showers (0)
|
|
|
Tue |
Sep 24 |
Verify Window & Roof Structure (0)
|
|
|
Tue |
Sep 24 |
Install Stairs (0)
|
|
|
Tue |
Sep 24 |
House Number and Status in Window (0)
|
|
|
Tue |
Sep 24 |
Order Appliances (0)
|
|
|
Tue |
Sep 24 |
Patio (0)
|
|
|
Tue |
Sep 24 |
Rough In Microwave Vent (0)
|
|
|
Tue |
Sep 24 |
Inspection (Rough In Plumbing) (1)
|
|
|
Wed |
Sep 25 |
Inspection (Rough In Electric) (1)
|
|
|
Thu |
Sep 26 |
Inspection (Deck Piers) (0)
|
|
|
Thu |
Sep 26 |
Inspection (Framing) (1)
|
|
|
Fri |
Sep 27 |
Exterior Stone (0)
|
|
|
Fri |
Sep 27 |
Set Electric Meter (0)
|
|
|
Fri |
Sep 27 |
Inspection (Main Water Line) (0)
|
|
|
Fri |
Sep 27 |
Loan Approval (0)
|
|
|
Fri |
Sep 27 |
Deed Preparation (0)
|
|
|
Fri |
Sep 27 |
Garage Door (0)
|
|
|
Fri |
Sep 27 |
Mailbox (0)
|
|
|
Fri |
Sep 27 |
Order Plumbing / Lighting Fixtures (0)
|
|
|
Fri |
Sep 27 |
Interior Trim - Paint (1)
|
|
|
Mon |
Sep 30 |
Deliver Plumbing / Lighting Fixtures (0)
|
|
|
Mon |
Sep 30 |
Shoe Moulding (0)
|
|
|
Mon |
Sep 30 |
Shelving, Door Knobs, Fire Extinguisher (0)
|
Finishing 6/15 |
|
Mon |
Sep 30 |
Set Water Meter (0)
|
|
|
Mon |
Sep 30 |
Ceiling Fans (0)
|
|
|
Mon |
Sep 30 |
Blower Door Test (1)
|
|
|
Tue |
Oct 1 |
Paint 3 (2)
|
|
|
Thu |
Oct 3 |
Appraiser Confirms Construction Completion (0)
|
|
|
Thu |
Oct 3 |
Inspection (Final HVAC) (1)
|
|
|
Fri |
Oct 4 |
Inspection (Final Plumbing) (1)
|
|
|
Mon |
Oct 7 |
Inspection (Final Electric) (1)
|
|
|
Tue |
Oct 8 |
Stain Hardwood Stairs (1)
|
|
|
Wed |
Oct 9 |
Cleaning (1)
|
Sunday 6/18-29 |
|
Thu |
Oct 10 |
Certificate of Occupancy (1)
|
|
|
Fri |
Oct 11 |
C.O. to Lender (0)
|
|
|
Fri |
Oct 11 |
Schedule Closing (0)
|
|
|
Fri |
Oct 11 |
Buyer Walk Through (1)
|
|
|
Mon |
Oct 14 |
Payment for Upgrades (0)
|
|
|
Mon |
Oct 14 |
Keys to Settlement Agent (0)
|
|
|
Mon |
Oct 14 |
Review Settlement Statement (0)
|
|
|
Mon |
Oct 14 |
Jerry Signs Closing Documents (0)
|
|
|
Mon |
Oct 14 |
Request Trash Tote From POA Manager (0)
|
|
|
Mon |
Oct 14 |
Closing (1)
|
|
|
Tue |
Oct 15 |
Remove Coded Lockbox (0)
|
|
|
|
-- |
-- |
Portsmouth Brick, Country Beige Vinyl, Green Door |
Paint front door |
|
-- |
-- |
Adjust door framing in the basement |
|
|
-- |
-- |
Install fence? |
|
|
-- |
-- |
Plant leiland cypress trees? |
|
|
-- |
-- |
Appraiser Re-Visit |
When Complete, 10 Days Prior to Closing |
|
-- |
-- |
Mitch shoemold today 5/25 |
|
|
-- |
-- |
Appraiser needs to verify completion by June 10 |
|
|
-- |
-- |
Install Basement Carpet |
Thursday 6/15 |
|
-- |
-- |
Install kitchen shoemold |
Friday 6/16 |
|
-- |
-- |
Final paint |
Saturday 6/17 |
|
-- |
-- |
Building Permit (30)
|
|
|
-- |
-- |
Order Roof & Floor Trusses (1)
|
|
|
-- |
-- |
Order Windows & Doors (0)
|
|
|
-- |
-- |
Stake Out Home (1)
|
|
|
-- |
-- |
Excavate (2)
|
|
|
-- |
-- |
Inspection (Footers) (1)
|
|
|
-- |
-- |
Pour Footers (1)
|
|
|
-- |
-- |
Set Forms (2)
|
|
|
-- |
-- |
Pour Foundation Walls (1)
|
|
|
-- |
-- |
Plumb Slab (2)
|
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1)
|
|
|
-- |
-- |
Prepare Slab (1)
|
|
|
-- |
-- |
Inspection (Slab) (1)
|
|
|
-- |
-- |
Pour Slab (1)
|
|
|
-- |
-- |
Framing I (9)
|
In process |
|
-- |
-- |
Order Steps (0)
|
|
|
-- |
-- |
Framing II (8)
|
In process |
|
-- |
-- |
Framing III (8)
|
9/19 settings stairs and punch out today |
|
-- |
-- |
Windows & Doors (0)
|
9/19 nearly complete |
|
-- |
-- |
Roofing (0)
|
|
|
-- |
-- |
Order Cabinets (0)
|
|
|
-- |
-- |
Deck (0)
|
|
|
-- |
-- |
Gutters (0)
|
|
|
-- |
-- |
Driveway (0)
|
|
|
-- |
-- |
Privacy Divider / Fence (0)
|
|
|
-- |
-- |
Sod / Seed / Landscaping (0)
|
|
|
-- |
-- |
HVAC Rough In (4)
|
|
|
-- |
-- |
Inspection (Rough In HVAC) (1)
|
|
|
-- |
-- |
Plumbing Rough In (4)
|
10/24 done with all but tubs |
|
-- |
-- |
Electric Rough In (4)
|
11/29 |
|
-- |
-- |
Exterior Vinyl (0)
|
Brick done vinyl needed |
|
-- |
-- |
Insulation (2)
|
2/13 in process |
|
-- |
-- |
Inspection (Insulation) (1)
|
|
|
-- |
-- |
Inspection (Electric Service) (0)
|
|
|
-- |
-- |
Inspection (Main Sewer Line) (0)
|
|
|
-- |
-- |
Order Interior Doors & Trim (0)
|
|
|
-- |
-- |
Drywall (Hang) (4)
|
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6)
|
Finishing |
|
-- |
-- |
Paint 1 (1)
|
3/6: Isaac coming soon; |
|
-- |
-- |
House Numbers (0)
|
|
|
-- |
-- |
Cabinet Installation (2)
|
Del Mar 14, Install Mar 15 |
|
-- |
-- |
Granite Installation (1)
|
|
|
-- |
-- |
Interior Trim - Install (3)
|
Complete Monday 5/8 |
|
-- |
-- |
Luxury Vinyl Plank (3)
|
|
|
-- |
-- |
Luxury Vinyl Tile (0)
|
Thursday 5/4 |
|
-- |
-- |
Paint 2 (3)
|
Friday 5/11 in process |
|
-- |
-- |
Cover Floors (1)
|
|
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0)
|
|
|
-- |
-- |
Pay Water / Sewer Taps (0)
|
Mindy will get check; |
|
-- |
-- |
Electric Trim Out (3)
|
6/15 complete the morning |
|
-- |
-- |
HVAC Trim Out (1)
|
June 12-13 |
|
-- |
-- |
Plumbing Trim Out (2)
|
Ready now 6/12 |
|
-- |
-- |
Install Appliances (0)
|
|
|
-- |
-- |
Carpet (2)
|
|
|
-- |
-- |
Inspection (Final Building) (2)
|
Thurs, June 15 |
|
-- |
-- |
Pre Walk Through (0)
|
Today Thursday 6/15 |
|