CODED LOCKBOX --- 7134 |
|
|
-- |
-- |
Remove coded lockbox |
|
|
Thu |
Nov 28 |
Ratified Contract? (0) |
|
|
Thu |
Nov 28 |
$2500 Deposit Received (0) |
|
|
Thu |
Nov 28 |
Association Packet Requested (0) |
|
|
Thu |
Nov 28 |
Association Packet Received (0) |
|
|
Thu |
Nov 28 |
Selections Meeting (0) |
|
|
Thu |
Nov 28 |
Selections Sheet Signed (0) |
|
|
Thu |
Nov 28 |
Amendment for Upgrades (B,S,L,T,BCP) (0) |
|
|
Thu |
Nov 28 |
Deposit For Upgrades Received (0) |
|
|
Thu |
Nov 28 |
Inspection (Concrete Wall) (1) |
|
|
Fri |
Nov 29 |
Inspection (Conduit Under Slab) (1) |
|
|
Mon |
Dec 2 |
Inspection (Drain Tile) (0) |
|
|
Mon |
Dec 2 |
Settlement Agent Confirmed (0) |
|
|
Mon |
Dec 2 |
Verify Window & Roof Structure (0) |
|
|
Mon |
Dec 2 |
Install Stairs (0) |
|
|
Mon |
Dec 2 |
House Number and Status in Window (0) |
|
|
Mon |
Dec 2 |
Order Appliances (0) |
|
|
Mon |
Dec 2 |
Patio (0) |
|
|
Mon |
Dec 2 |
Rough In Microwave Vent (0) |
|
|
Mon |
Dec 2 |
Inspection (Rough In Plumbing) (1) |
|
|
Tue |
Dec 3 |
Inspection (Rough In Electric) (1) |
|
|
Wed |
Dec 4 |
Inspection (Deck Piers) (0) |
|
|
Wed |
Dec 4 |
Inspection (Framing) (1) |
|
|
Thu |
Dec 5 |
Exterior Stone (0) |
|
|
Thu |
Dec 5 |
Set Electric Meter (0) |
|
|
Thu |
Dec 5 |
Inspection (Main Water Line) (0) |
|
|
Thu |
Dec 5 |
Loan Approval (0) |
|
|
Thu |
Dec 5 |
Deed Preparation (0) |
|
|
Thu |
Dec 5 |
Mailbox (0) |
|
|
Thu |
Dec 5 |
Order Plumbing / Lighting Fixtures (0) |
|
|
Thu |
Dec 5 |
Interior Trim - Paint (1) |
|
|
Fri |
Dec 6 |
Deliver Plumbing / Lighting Fixtures (0) |
|
|
Fri |
Dec 6 |
Shoe Moulding (0) |
|
|
Fri |
Dec 6 |
Set Water Meter (0) |
|
|
Fri |
Dec 6 |
Ceiling Fans (0) |
|
|
Fri |
Dec 6 |
Blower Door Test (1) |
|
|
Mon |
Dec 9 |
Inspection (Final HVAC) (1) |
|
|
Tue |
Dec 10 |
Inspection (Final Plumbing) (1) |
|
|
Wed |
Dec 11 |
Inspection (Final Electric) (1) |
|
|
Thu |
Dec 12 |
Stain Hardwood Stairs (1) |
|
|
Fri |
Dec 13 |
Schedule Closing (0) |
|
|
Fri |
Dec 13 |
Payment for Upgrades (0) |
|
|
Fri |
Dec 13 |
Keys to Settlement Agent (0) |
|
|
Fri |
Dec 13 |
Review Settlement Statement (0) |
|
|
Fri |
Dec 13 |
Jerry Signs Closing Documents (0) |
|
|
Fri |
Dec 13 |
Request Trash Tote From POA Manager (0) |
|
|
Fri |
Dec 13 |
Remove Coded Lockbox (0) |
|
|
|
-- |
-- |
Trimmed entrance in wall under lower stairs for cat entrance |
Check with Dara at electrical walk through |
|
-- |
-- |
Half door at closet under lower stairs |
Check with Dara at electrical walk through |
|
-- |
-- |
Add closet to basement room |
|
|
-- |
-- |
Framing and Electrical Walk Through, Mon 5PM |
|
|
-- |
-- |
Framing and Electrical Walk Through, Mon 5:30 PM |
|
|
-- |
-- |
Tub shower needs to be installed in basement bathroom. Tab is now on site |
|
|
-- |
-- |
Cat door, half door under stairs, outlet under stairs |
|
|
-- |
-- |
A few deck boards to be addressed |
Osbaldo |
|
-- |
-- |
Remove materials from kitchen |
|
|
-- |
-- |
Basement bath tile? |
10/10 |
|
-- |
-- |
Order Mailboxes! |
Kate?- How many Scott? |
|
-- |
-- |
Install cat door from Lowe's on door to storage closet |
https://goo.gl/mkYVUZ |
|
-- |
-- |
Install Light in closet under stairs -NO OUTLET |
Harry |
|
-- |
-- |
Install mailbox |
Osbaldo will install the mailbox- Saturday or Monday |
|
-- |
-- |
Deck boards |
Osbaldo |
|
-- |
-- |
Garage Door |
Wed, Oct 11 |
|
-- |
-- |
Connect sewer lines |
Mindy |
|
-- |
-- |
Hoping for final appraisal Monday the 13th |
|
|
-- |
-- |
The really cool fancy brick |
|
|
-- |
-- |
Look at bowed window in dining room |
Osbaldo will look at it |
|
-- |
-- |
Master tile |
Complete repair and add grout |
|
-- |
-- |
Paint touch up under closet |
|
|
-- |
-- |
Door swing going into basement room wrong....??? |
|
|
-- |
-- |
Remove trash |
Osbaldo |
|
-- |
-- |
Need shoe around base of cabinet in basement bathroom |
Jeff |
|
-- |
-- |
Paint touch up in closet under stairs |
|
|
-- |
-- |
Install fridge |
Osbaldo will check |
|
-- |
-- |
Paint touch up pantry |
|
|
-- |
-- |
Fill all nail holes from mirrors |
|
|
-- |
-- |
Mailboxes labeled? Keys? |
Osbaldo? |
|
-- |
-- |
Toilet out far from wall in basement bath-can't open door |
|
|
-- |
-- |
Pave driveway |
|
|
-- |
-- |
Push fridge back- take cardboard out from under fridge |
|
|
-- |
-- |
Missing ceiling light- up hallway globe |
Still waiting on this from Ferguson |
|
-- |
-- |
Replace carpet and pad in basement |
Eagle Carpet |
|
-- |
-- |
Paint touch up |
|
|
-- |
-- |
Repair nicks on cabinets |
Classic Kitchen |
|
-- |
-- |
Fill holes in shoe moulding at kitchen cabinets |
Classic Kitchen |
|
-- |
-- |
Adjust patio doors and install screens |
|
|
-- |
-- |
Add landscaping to box in backyard |
|
|
-- |
-- |
Repair nick in living room window |
Tom will coordinate |
|
-- |
-- |
Caulk at base of tubs |
|
|
-- |
-- |
Tighten master bathroom toilet seat |
Tom |
|
-- |
-- |
Adjust cabinet doors in upstairs hall bathroom |
Classic Kitchen |
|
-- |
-- |
Reinstall basement door and remove second door |
|
|
-- |
-- |
Install Street Sign |
Tuesday (per Mark the street sign guy) |
|
-- |
-- |
Needs hot water |
Mindy |
|
-- |
-- |
Install window screens |
Arriving Monday, Dec 18 |
|
-- |
-- |
COMCAST |
|
|
-- |
-- |
Install baseboard in basement |
|
|
-- |
-- |
Caulk in master bathroom at tub |
|
|
-- |
-- |
Install missing door knob in basement |
|
|
-- |
-- |
Touch up paint at basement door |
Isaac |
|
-- |
-- |
Where is garage door remote? |
|
|
-- |
-- |
Clean caulk out of bathtub |
Kelly |
|
-- |
-- |
Caulk at master bathroom at tub |
Isaac |
|
-- |
-- |
Building Permit (30) |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) |
|
|
-- |
-- |
Order Windows & Doors (0) |
|
|
-- |
-- |
Stake Out Home (1) |
|
|
-- |
-- |
Excavate (2) |
|
|
-- |
-- |
Inspection (Footers) (1) |
|
|
-- |
-- |
Pour Footers (1) |
|
|
-- |
-- |
Set Forms (2) |
|
|
-- |
-- |
Pour Foundation Walls (1) |
|
|
-- |
-- |
Plumb Slab (2) |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
-- |
-- |
Prepare Slab (1) |
|
|
-- |
-- |
Inspection (Slab) (1) |
|
|
-- |
-- |
Pour Slab (1) * |
|
|
-- |
-- |
Framing I (9) |
6/13 |
|
-- |
-- |
Order Steps (0) |
|
|
-- |
-- |
Order Tubs / Showers (0) |
|
|
-- |
-- |
Framing II (8) |
6/26 framing second floor |
|
-- |
-- |
Framing III (8) * |
|
|
-- |
-- |
Windows & Doors (0) |
|
|
-- |
-- |
Roofing (0) |
|
|
-- |
-- |
Order Cabinets (0) |
|
|
-- |
-- |
Deck (0) |
|
|
-- |
-- |
Gutters (0) |
Thurs, Nov 2 |
|
-- |
-- |
Driveway (0) |
Pouring Mon, Nov 20??? |
|
-- |
-- |
Privacy Divider / Fence (0) |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) |
Landscaping done in front. Pettit put seed instead of sod and did not seed on side or back |
|
-- |
-- |
HVAC Rough In (4) |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) |
Tues, Aug 15 |
|
-- |
-- |
Plumbing Rough In (4) |
|
|
-- |
-- |
Electric Rough In (4) |
Will be complete today 8/7 |
|
-- |
-- |
Exterior Vinyl (0) * |
Vinyl to start Tue, Oct 10 |
|
-- |
-- |
Insulation (2) |
|
|
-- |
-- |
Inspection (Insulation) (1) |
|
|
-- |
-- |
Inspection (Electric Service) (0) |
HEC to run conduit today |
|
-- |
-- |
Inspection (Main Sewer Line) (0) |
Meter boxes are set, waiting on connection to meter box |
|
-- |
-- |
Order Interior Doors & Trim (0) |
9/7: Mitch needs to order this ASAP |
|
-- |
-- |
Drywall (Hang) (4) * |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
8/28 beginning today |
|
-- |
-- |
Paint 1 (1) |
Saturday 9/9 |
|
-- |
-- |
Garage Door (0) |
|
|
-- |
-- |
House Numbers (0) |
Osbaldo will put it in Mon, Nov 27 |
|
-- |
-- |
Cabinet Installation (2) * |
Delivered Sept 15, Installed Sept 18 |
|
-- |
-- |
Granite Installation (1) * |
Mon, Oct 2 |
|
-- |
-- |
Interior Trim - Install (3) |
Mitch starting 9/11/2017 |
|
-- |
-- |
Luxury Vinyl Plank (3) * |
|
|
-- |
-- |
Luxury Vinyl Tile (0) |
Joe was waiting on tile |
|
-- |
-- |
Paint 2 (3) |
Color on walls today 10/5 |
|
-- |
-- |
Cover Floors (1) |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) |
waiting on buyer approval of designs |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) |
Mindy will request check from Nicolette on Mon, Nov 13 |
|
-- |
-- |
Electric Trim Out (3) |
10/26: Harry is working on it |
|
-- |
-- |
HVAC Trim Out (1) |
|
|
-- |
-- |
Plumbing Trim Out (2) |
Close as of Oct 30 |
|
-- |
-- |
Install Appliances (0) * |
Installing Tues, Nov 7 |
|
-- |
-- |
Paint 3 (2) * |
|
|
-- |
-- |
Carpet (2) |
Thu, Oct 26 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0) |
Maybe waiting on driveway |
|
-- |
-- |
Inspection (Final Building) (2) * |
Thu, Nov 30 |
|
-- |
-- |
Pre Walk Through (0) |
|
|
-- |
-- |
Cleaning (1) |
To Be Completed on Monday and Touch Up after Punch Out |
|
-- |
-- |
Certificate of Occupancy (1) * |
|
|
-- |
-- |
C.O. to Lender (0) |
|
|
-- |
-- |
Buyer Walk Through (1) |
Monday 12/4 at 10:30- Pre-possession on evening of 12/6 |
|
-- |
-- |
Closing (1) |
Wed, Dec 13 @ 9AM @ WVT |
|