ADDR
- 115  ::  370 Tanzanite Drive
[ BUILD: 17040005 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   CODED LOCKBOX --- 7134
--   --   Remove coded lockbox
Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Inspection (Concrete Wall) (1)      
Wed    Dec 17      Inspection (Conduit Under Slab) (1)      
Thu    Dec 18      Inspection (Drain Tile) (0)      
Thu    Dec 18      Settlement Agent Confirmed (0)      
Thu    Dec 18      Verify Window & Roof Structure (0)      
Thu    Dec 18      Install Stairs (0) *       
Thu    Dec 18      House Number and Status in Window (0)      
Thu    Dec 18      Order Appliances (0)      
Thu    Dec 18      Patio (0)      
Thu    Dec 18      Rough In Microwave Vent (0)      
Thu    Dec 18      Inspection (Rough In Plumbing) (1)      
Fri    Dec 19      Inspection (Rough In Electric) (1)      
Mon    Dec 22      Inspection (Framing) (1) *       
Tue    Dec 23      Inspection (Deck Piers) (0)      
Tue    Dec 23      Exterior Stone (0)      
Tue    Dec 23      Set Electric Meter (0) *       
Tue    Dec 23      Inspection (Main Water Line) (0)      
Tue    Dec 23      Loan Approval (0)      
Tue    Dec 23      Deed Preparation (0)      
Tue    Dec 23      Mailbox (0)      
Tue    Dec 23      Order Plumbing / Lighting Fixtures (0)      
Tue    Dec 23      Interior Trim - Paint (1)      
Wed    Dec 24      Deliver Plumbing / Lighting Fixtures (0)      
Wed    Dec 24      Shoe Moulding (0)      
Wed    Dec 24      Set Water Meter (0) *       
Wed    Dec 24      Ceiling Fans (0)      
Wed    Dec 24      Blower Door Test (1)      
Thu    Dec 25      Inspection (Final HVAC) (1)      
Fri    Dec 26      Inspection (Final Plumbing) (1)      
Mon    Dec 29      Inspection (Final Electric) (1)      
Tue    Dec 30      Stain Hardwood Stairs (1) *       
Wed    Dec 31      Schedule Closing (0)      
Wed    Dec 31      Payment for Upgrades (0)      
Wed    Dec 31      Keys to Settlement Agent (0)      
Wed    Dec 31      Review Settlement Statement (0)      
Wed    Dec 31      Jerry Signs Closing Documents (0)      
Wed    Dec 31      Request Trash Tote From POA Manager (0)      
Wed    Dec 31      Remove Coded Lockbox (0)      
--   --   Trimmed entrance in wall under lower stairs for cat entrance Check with Dara at electrical walk through
--   --   Half door at closet under lower stairs Check with Dara at electrical walk through
--   --   Add closet to basement room
--   --   Framing and Electrical Walk Through, Mon 5PM
--   --   Framing and Electrical Walk Through, Mon 5:30 PM
--   --   Tub shower needs to be installed in basement bathroom. Tab is now on site
--   --   Cat door, half door under stairs, outlet under stairs
--   --   A few deck boards to be addressed Osbaldo
--   --   Remove materials from kitchen
--   --   Basement bath tile? 10/10
--   --   Order Mailboxes! Kate?- How many Scott?
--   --   Install cat door from Lowe's on door to storage closet https://goo.gl/mkYVUZ
--   --   Install Light in closet under stairs -NO OUTLET Harry
--   --   Install mailbox Osbaldo will install the mailbox- Saturday or Monday
--   --   Deck boards Osbaldo
--   --   Garage Door Wed, Oct 11
--   --   Connect sewer lines Mindy
--   --   Hoping for final appraisal Monday the 13th
--   --   The really cool fancy brick
--   --   Look at bowed window in dining room Osbaldo will look at it
--   --   Master tile Complete repair and add grout
--   --   Paint touch up under closet
--   --   Door swing going into basement room wrong....???
--   --   Remove trash Osbaldo
--   --   Need shoe around base of cabinet in basement bathroom Jeff
--   --   Paint touch up in closet under stairs
--   --   Install fridge Osbaldo will check
--   --   Paint touch up pantry
--   --   Fill all nail holes from mirrors
--   --   Mailboxes labeled? Keys? Osbaldo?
--   --   Toilet out far from wall in basement bath-can't open door
--   --   Pave driveway
--   --   Push fridge back- take cardboard out from under fridge
--   --   Missing ceiling light- up hallway globe Still waiting on this from Ferguson
--   --   Replace carpet and pad in basement Eagle Carpet
--   --   Paint touch up
--   --   Repair nicks on cabinets Classic Kitchen
--   --   Fill holes in shoe moulding at kitchen cabinets Classic Kitchen
--   --   Adjust patio doors and install screens
--   --   Add landscaping to box in backyard
--   --   Repair nick in living room window Tom will coordinate
--   --   Caulk at base of tubs
--   --   Tighten master bathroom toilet seat Tom
--   --   Adjust cabinet doors in upstairs hall bathroom Classic Kitchen
--   --   Reinstall basement door and remove second door
--   --   Install Street Sign Tuesday (per Mark the street sign guy)
--   --   Needs hot water Mindy
--   --   Install window screens Arriving Monday, Dec 18
--   --   COMCAST
--   --   Install baseboard in basement
--   --   Caulk in master bathroom at tub
--   --   Install missing door knob in basement
--   --   Touch up paint at basement door Isaac
--   --   Where is garage door remote?
--   --   Clean caulk out of bathtub Kelly
--   --   Caulk at master bathroom at tub Isaac
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       6/13
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)       6/26 framing second floor
-- -- Framing III (8) *       
-- -- Windows & Doors (0) *       
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)       Thurs, Nov 2
-- -- Driveway (0) *        Pouring Mon, Nov 20???
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)       Landscaping done in front. Pettit put seed instead of sod and did not seed on side or back
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)       Will be complete today 8/7
-- -- Inspection (Rough In HVAC) (1)       Tues, Aug 15
-- -- Exterior Vinyl (0) *        Vinyl to start Tue, Oct 10
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)       HEC to run conduit today
-- -- Inspection (Main Sewer Line) (0)       Meter boxes are set, waiting on connection to meter box
-- -- Order Interior Doors & Trim (0)       9/7: Mitch needs to order this ASAP
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        8/28 beginning today
-- -- Paint 1 (1)       Saturday 9/9
-- -- Garage Door (0)      
-- -- House Numbers (0)       Osbaldo will put it in Mon, Nov 27
-- -- Cabinet Installation (2) *        Delivered Sept 15, Installed Sept 18
-- -- Granite Installation (1) *        Mon, Oct 2
-- -- Interior Trim - Install (3) *        Mitch starting 9/11/2017
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Joe was waiting on tile
-- -- Paint 2 (3)       Color on walls today 10/5
-- -- Cover Floors (1)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        waiting on buyer approval of designs
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)       Mindy will request check from Nicolette on Mon, Nov 13
-- -- Electric Trim Out (3) *        10/26: Harry is working on it
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *        Close as of Oct 30
-- -- Install Appliances (0) *        Installing Tues, Nov 7
-- -- Paint 3 (2) *       
-- -- Carpet (2)       Thu, Oct 26
-- -- Appraiser Confirms Construction Completion (0)       Maybe waiting on driveway
-- -- Inspection (Final Building) (2) *        Thu, Nov 30
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       To Be Completed on Monday and Touch Up after Punch Out
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1) *        Monday 12/4 at 10:30- Pre-possession on evening of 12/6
-- -- Closing (1)       Wed, Dec 13 @ 9AM @ WVT