ADDR
- 115  ::  370 Tanzanite Drive
[ BUILD: 17040005 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   CODED LOCKBOX --- 7134
--   --   Remove coded lockbox
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Install Stairs (0)      
Mon    Dec 2      House Number and Status in Window (0)      
Mon    Dec 2      Order Appliances (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Order Plumbing / Lighting Fixtures (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Deliver Plumbing / Lighting Fixtures (0)      
Fri    Dec 6      Shoe Moulding (0)      
Fri    Dec 6      Set Water Meter (0)      
Fri    Dec 6      Ceiling Fans (0)      
Fri    Dec 6      Blower Door Test (1)      
Mon    Dec 9      Inspection (Final HVAC) (1)      
Tue    Dec 10      Inspection (Final Plumbing) (1)      
Wed    Dec 11      Inspection (Final Electric) (1)      
Thu    Dec 12      Stain Hardwood Stairs (1)      
Fri    Dec 13      Schedule Closing (0)      
Fri    Dec 13      Payment for Upgrades (0)      
Fri    Dec 13      Keys to Settlement Agent (0)      
Fri    Dec 13      Review Settlement Statement (0)      
Fri    Dec 13      Jerry Signs Closing Documents (0)      
Fri    Dec 13      Request Trash Tote From POA Manager (0)      
Fri    Dec 13      Remove Coded Lockbox (0)      
--   --   Trimmed entrance in wall under lower stairs for cat entrance Check with Dara at electrical walk through
--   --   Half door at closet under lower stairs Check with Dara at electrical walk through
--   --   Add closet to basement room
--   --   Framing and Electrical Walk Through, Mon 5PM
--   --   Framing and Electrical Walk Through, Mon 5:30 PM
--   --   Tub shower needs to be installed in basement bathroom. Tab is now on site
--   --   Cat door, half door under stairs, outlet under stairs
--   --   A few deck boards to be addressed Osbaldo
--   --   Remove materials from kitchen
--   --   Basement bath tile? 10/10
--   --   Order Mailboxes! Kate?- How many Scott?
--   --   Install cat door from Lowe's on door to storage closet https://goo.gl/mkYVUZ
--   --   Install Light in closet under stairs -NO OUTLET Harry
--   --   Install mailbox Osbaldo will install the mailbox- Saturday or Monday
--   --   Deck boards Osbaldo
--   --   Garage Door Wed, Oct 11
--   --   Connect sewer lines Mindy
--   --   Hoping for final appraisal Monday the 13th
--   --   The really cool fancy brick
--   --   Look at bowed window in dining room Osbaldo will look at it
--   --   Master tile Complete repair and add grout
--   --   Paint touch up under closet
--   --   Door swing going into basement room wrong....???
--   --   Remove trash Osbaldo
--   --   Need shoe around base of cabinet in basement bathroom Jeff
--   --   Paint touch up in closet under stairs
--   --   Install fridge Osbaldo will check
--   --   Paint touch up pantry
--   --   Fill all nail holes from mirrors
--   --   Mailboxes labeled? Keys? Osbaldo?
--   --   Toilet out far from wall in basement bath-can't open door
--   --   Pave driveway
--   --   Push fridge back- take cardboard out from under fridge
--   --   Missing ceiling light- up hallway globe Still waiting on this from Ferguson
--   --   Replace carpet and pad in basement Eagle Carpet
--   --   Paint touch up
--   --   Repair nicks on cabinets Classic Kitchen
--   --   Fill holes in shoe moulding at kitchen cabinets Classic Kitchen
--   --   Adjust patio doors and install screens
--   --   Add landscaping to box in backyard
--   --   Repair nick in living room window Tom will coordinate
--   --   Caulk at base of tubs
--   --   Tighten master bathroom toilet seat Tom
--   --   Adjust cabinet doors in upstairs hall bathroom Classic Kitchen
--   --   Reinstall basement door and remove second door
--   --   Install Street Sign Tuesday (per Mark the street sign guy)
--   --   Needs hot water Mindy
--   --   Install window screens Arriving Monday, Dec 18
--   --   COMCAST
--   --   Install baseboard in basement
--   --   Caulk in master bathroom at tub
--   --   Install missing door knob in basement
--   --   Touch up paint at basement door Isaac
--   --   Where is garage door remote?
--   --   Clean caulk out of bathtub Kelly
--   --   Caulk at master bathroom at tub Isaac
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       6/13
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)       6/26 framing second floor
-- -- Framing III (8) *       
-- -- Windows & Doors (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)       Thurs, Nov 2
-- -- Driveway (0)       Pouring Mon, Nov 20???
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)       Landscaping done in front. Pettit put seed instead of sod and did not seed on side or back
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       Tues, Aug 15
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)       Will be complete today 8/7
-- -- Exterior Vinyl (0) *        Vinyl to start Tue, Oct 10
-- -- Insulation (2)      
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)       HEC to run conduit today
-- -- Inspection (Main Sewer Line) (0)       Meter boxes are set, waiting on connection to meter box
-- -- Order Interior Doors & Trim (0)       9/7: Mitch needs to order this ASAP
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        8/28 beginning today
-- -- Paint 1 (1)       Saturday 9/9
-- -- Garage Door (0)      
-- -- House Numbers (0)       Osbaldo will put it in Mon, Nov 27
-- -- Cabinet Installation (2) *        Delivered Sept 15, Installed Sept 18
-- -- Granite Installation (1) *        Mon, Oct 2
-- -- Interior Trim - Install (3)       Mitch starting 9/11/2017
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Joe was waiting on tile
-- -- Paint 2 (3)       Color on walls today 10/5
-- -- Cover Floors (1)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       waiting on buyer approval of designs
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)       Mindy will request check from Nicolette on Mon, Nov 13
-- -- Electric Trim Out (3)       10/26: Harry is working on it
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       Close as of Oct 30
-- -- Install Appliances (0) *        Installing Tues, Nov 7
-- -- Paint 3 (2) *       
-- -- Carpet (2)       Thu, Oct 26
-- -- Appraiser Confirms Construction Completion (0)       Maybe waiting on driveway
-- -- Inspection (Final Building) (2) *        Thu, Nov 30
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       To Be Completed on Monday and Touch Up after Punch Out
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1)       Monday 12/4 at 10:30- Pre-possession on evening of 12/6
-- -- Closing (1)       Wed, Dec 13 @ 9AM @ WVT