- 116  ::  372 Tanzanite Drive
[ BUILD: 17040009 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Order Plumbing / Lighting Fixtures (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Ceiling Fans (0)      
Fri    Dec 6      Blower Door Test (1)      
Mon    Dec 9      Inspection (Final HVAC) (1)      
Tue    Dec 10      Inspection (Final Plumbing) (1)      
Wed    Dec 11      Inspection (Final Electric) (1)      
Thu    Dec 12      Stain Hardwood Stairs (1)      
--   --   Twin Dormers (not needed)
--   --   Install shoe moulding
--   --   Suzanne wants to know when to order final appraisal Lease ends Nov 30
--   --   Install last few light fixtures
--   --   Floor scratches foyer Eric will check it out- 12/1
--   --   Paint Puch up
--   --   Paint touch up
--   --   CODED LOCKBOX --- 2062
--   --   Pave driveway
--   --   We need keys!
--   --   Install Washer & Dryer Tom - Mon, Dec 4
--   --   Install missing light bulbs master fan, hall bath vanity, dining light, garage
--   --   Caulk at base of tubs Mindy
--   --   Clean tubs and vanities Kelly
--   --   Install screens Tom will pick up and install
--   --   Tighten escutchens at shower heads Mindy - gap at shower head in upstairs hall bathroom
--   --   Install hall sconce light at stairs
--   --   Sand and paint banister top cap in living room
--   --   Install missing shoe moulding in hall closet
--   --   Clean front of island Kelly
--   --   Install weather stripping at french doors and adjust screen door Tom
--   --   Repair or replace wood interior trim at french door Tom
--   --   Install mailbox and provide keys
--   --   Adjust garage door lock
--   --   COMCAST
--   --   Repair threshold to bonus room behind garage Tom will tell Eric
--   --   Remove coded lockbox
--   --   Repair fence where damaged by pallet Tom
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       Meet on site with buyers to discuss framing of laundry/ bathroom
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)       Leave 2nd floor laundry bathroom unframed...meet with buyers
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)      
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)  09.07.2021    
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)       Mon, Nov 20
-- -- Privacy Divider / Fence (0)       Tom will check
-- -- Sod / Seed / Landscaping (0)       Landscaping complete. Seededd and straw out front not back should've been sod
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       All inspections Friday, Aug 18
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)       In process- complete Thursday 8/18
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2)      
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)       Finished Thurs, Nov 9 - Inspected Fri, Nov 10
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        8/28- beginning today
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process, complete by Monday 18th
-- -- Paint 1 (1)       Tuesday 19th
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        10/9 installation in process
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3)       10/9 waiting on shoe
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Nearly complete as of Mon, Sep 25
-- -- Paint 2 (3)       Tuesday 10/17
-- -- Cover Floors (1)       Osbaldo to cover on Thurs / Fri
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       Designs approved
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)       Mindy to pay on Thurs, Nov 9
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       completing today
-- -- HVAC Trim Out (1)       Need heat pump
-- -- Plumbing Trim Out (2)       Thu, Nov 2
-- -- Install Appliances (0) *        Delivering Friday 11/3
-- -- Paint 3 (2) *       
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)       Tues, Dec 5 at 8:00 AM
-- -- Inspection (Final Building) (2) *        Thu, Nov 30
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       In process...waiting on water
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)  09.07.2021    
-- -- Buyer Walk Through (1)       Mon, Nov 13
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)  09.07.2021    
-- -- Review Settlement Statement (0)  09.07.2021    
-- -- Jerry Signs Closing Documents (0)  09.07.2021    
-- -- Request Trash Tote From POA Manager (0)  09.07.2021    
-- -- Closing (1)      
-- -- Remove Coded Lockbox (0)  09.07.2021