| Tue | Dec 16 | Ratified Contract? (0) | ||
| Tue | Dec 16 | $2500 Deposit Received (0) | ||
| Tue | Dec 16 | Association Packet Requested (0) | ||
| Tue | Dec 16 | Association Packet Received (0) | ||
| Tue | Dec 16 | Selections Meeting (0) | ||
| Tue | Dec 16 | Selections Sheet Signed (0) | ||
| Tue | Dec 16 | Amendment for Upgrades (B,S,L,T,BCP) (0) | ||
| Tue | Dec 16 | Deposit For Upgrades Received (0) | ||
| Tue | Dec 16 | Inspection (Concrete Wall) (1) | ||
| Wed | Dec 17 | Inspection (Conduit Under Slab) (1) | ||
| Thu | Dec 18 | Inspection (Drain Tile) (0) | ||
| Thu | Dec 18 | Settlement Agent Confirmed (0) | ||
| Thu | Dec 18 | Verify Window & Roof Structure (0) | ||
| Thu | Dec 18 | Order Appliances (0) | ||
| Thu | Dec 18 | Patio (0) | ||
| Thu | Dec 18 | Rough In Microwave Vent (0) | ||
| Thu | Dec 18 | Inspection (Rough In Plumbing) (1) | ||
| Fri | Dec 19 | Inspection (Rough In Electric) (1) | ||
| Mon | Dec 22 | Inspection (Framing) (1) * | ||
| Tue | Dec 23 | Inspection (Deck Piers) (0) | ||
| Tue | Dec 23 | Exterior Stone (0) | ||
| Tue | Dec 23 | Set Electric Meter (0) * | ||
| Tue | Dec 23 | Inspection (Main Water Line) (0) | ||
| Tue | Dec 23 | Loan Approval (0) | ||
| Tue | Dec 23 | Deed Preparation (0) | ||
| Tue | Dec 23 | Mailbox (0) | ||
| Tue | Dec 23 | Interior Trim - Paint (1) | ||
| Wed | Dec 24 | Ceiling Fans (0) | ||
| Wed | Dec 24 | Blower Door Test (1) | ||
| Thu | Dec 25 | Inspection (Final HVAC) (1) | ||
| Fri | Dec 26 | Inspection (Final Plumbing) (1) | ||
| Mon | Dec 29 | Inspection (Final Electric) (1) | ||
| Tue | Dec 30 | Stain Hardwood Stairs (1) * | ||
| Wed | Dec 31 | Request Trash Tote From POA Manager (0) | ||
| -- | -- | Missing Twin Dormers | ||
| -- | -- | Repair damaged tub | Mindy - waiting on water and electricity | |
| -- | -- | Adjust sewer stub is too close too the firewall | Mindy | |
| -- | -- | Garage door | ||
| -- | -- | Powder bath, change door swing | Kate will tell Mitch | |
| -- | -- | Pave driveway | ||
| -- | -- | Remove debris on Thursday for cleaners | Tom | |
| -- | -- | CODED LOCKBOX --- 3438 | ||
| -- | -- | Where are extra keys? | ||
| -- | -- | COMCAST | ||
| -- | -- | Install weather stripping | ||
| -- | -- | Creaks in floor in 2nd and 3rd bedroom | ||
| -- | -- | Adjust laundry room door which is difficult to close | ||
| -- | -- | Upper level newel post needs sanding | ||
| -- | -- | Touch up paint | ||
| -- | -- | Remove coded lockbox | ||
| -- | -- | Vacuum floor vent ductwork | ||
| -- | -- | Repair bow in hall flooring above stairway | Monday, Dec 18 - Eric | |
| -- | -- | Install screens | Arriving Monday, Dec 18 | |
| -- | -- | Paint final coat on front door | (green) | |
| -- | -- | Adjust cabinets next to refrigerator | Adjust right door, straighten bar on left door | |
| -- | -- | Repair missing chunk of window in master bedroom | Isaac | |
| -- | -- | Remove glue in corner of left window in master bedroom | ||
| -- | -- | Install missing bracket at shelves in master closet | ||
| -- | -- | Caulk gap at floor in pantry and install quarter round | ||
| -- | -- | Install missing stopper at upstairs hall bath | Mindy | |
| -- | -- | Clean inside refrigerator | ||
| -- | -- | Install PVC under back patio door | ||
| -- | -- | Adjust front door so lock is secure | ||
| -- | -- | Secure upper railing going to kitchen | ||
| -- | -- | Patch holes in mechnical room | Majyer | |
| -- | -- | Install additional light in basement | ||
| -- | -- | Touch up paint at edge of lower overhang | Ceiling of foyer - Majyjyjyer | |
| -- | -- | Clean basement bath | ||
| -- | -- | Secure plumbing in basement bathroom | ||
| -- | -- | Connect garage door opener to door | ||
| -- | -- | Fill and paint gaps at garage door frame | ||
| -- | -- | Raise chandelier | Tom will tell Harry | |
| -- | -- | Repair flooring issues on kitchen half of main level | Tom meeting her today 4/23 after 12. | |
| -- | -- | Cracked foundation wall | Materials on order as of Aug 27 | |
| -- | -- | Extended warranty on foundation? | ||
| -- | -- | Patch drywall | ||
| -- | -- | Install carpet | ||
| -- | -- | Baseboard and paint | ||
| -- | -- | Water leak/drywall repair | Ronnie re-caulking a/c line | |
| -- | -- | Building Permit (30) * | ||
| -- | -- | Order Roof & Floor Trusses (1) | ||
| -- | -- | Order Windows & Doors (0) | ||
| -- | -- | Stake Out Home (1) | ||
| -- | -- | Excavate (2) | ||
| -- | -- | Inspection (Footers) (1) | ||
| -- | -- | Pour Footers (1) * | ||
| -- | -- | Set Forms (2) | ||
| -- | -- | Pour Foundation Walls (1) | ||
| -- | -- | Plumb Slab (2) | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) | ||
| -- | -- | Prepare Slab (1) | ||
| -- | -- | Inspection (Slab) (1) | ||
| -- | -- | Pour Slab (1) * | ||
| -- | -- | Framing I (9) | ||
| -- | -- | Order Steps (0) | ||
| -- | -- | Order Tubs / Showers (0) | ||
| -- | -- | Framing II (8) | ||
| -- | -- | Framing III (8) * | ||
| -- | -- | Install Stairs (0) * | ||
| -- | -- | Windows & Doors (0) * | ||
| -- | -- | House Number and Status in Window (0) | ||
| -- | -- | Roofing (0) * | ||
| -- | -- | Order Cabinets (0) | ||
| -- | -- | Deck (0) | ||
| -- | -- | Gutters (0) | ||
| -- | -- | Driveway (0) * | ||
| -- | -- | Privacy Divider / Fence (0) * | ||
| -- | -- | Sod / Seed / Landscaping (0) | ||
| -- | -- | HVAC Rough In (4) | ||
| -- | -- | Plumbing Rough In (4) | Started 9/7 | |
| -- | -- | Electric Rough In (4) | 8/28 in process | |
| -- | -- | Inspection (Rough In HVAC) (1) | Thursday, Sept14 | |
| -- | -- | Exterior Vinyl (0) * | ||
| -- | -- | Insulation (2) * | ||
| -- | -- | Inspection (Insulation) (1) | ||
| -- | -- | Inspection (Electric Service) (0) | ||
| -- | -- | Inspection (Main Sewer Line) (0) | ||
| -- | -- | Order Interior Doors & Trim (0) | ||
| -- | -- | Drywall (Hang) (4) * | Complete today 10/9 | |
| -- | -- | Drywall (Tape, Block, Skim, Sand) (6) * | ||
| -- | -- | Paint 1 (1) | Tue, Oct 10 | |
| -- | -- | Garage Door (0) | ||
| -- | -- | House Numbers (0) | ||
| -- | -- | Cabinet Installation (2) * | in process | |
| -- | -- | Granite Installation (1) * | ||
| -- | -- | Interior Trim - Install (3) * | In process | |
| -- | -- | Order Plumbing / Lighting Fixtures (0) | ||
| -- | -- | Luxury Vinyl Plank (3) * | ||
| -- | -- | Luxury Vinyl Tile (0) | Beginning 10/23 | |
| -- | -- | Paint 2 (3) | In process | |
| -- | -- | Cover Floors (1) | ||
| -- | -- | Deliver Plumbing / Lighting Fixtures (0) | ||
| -- | -- | Shoe Moulding (0) | ||
| -- | -- | Shelving, Door Knobs, Fire Extinguisher (0) * | Nearly complete- finishing week of 12/4 | |
| -- | -- | Install Coded Lockbox (add extra keys) (0) | ||
| -- | -- | Pay Water / Sewer Taps (0) | Pay Mon, Dec 4 | |
| -- | -- | Set Water Meter (0) * | ||
| -- | -- | Electric Trim Out (3) * | Nearly Complete- finishing 12/4 | |
| -- | -- | HVAC Trim Out (1) * | ||
| -- | -- | Plumbing Trim Out (2) * | Tue, Dec 5 | |
| -- | -- | Install Appliances (0) * | Mon, Dec 4 | |
| -- | -- | Paint 3 (2) * | In Process now complete by 12/4 | |
| -- | -- | Carpet (2) | ||
| -- | -- | Appraiser Confirms Construction Completion (0) | ||
| -- | -- | Inspection (Final Building) (2) * | Wed, Dec 6 - Mindy will schedule | |
| -- | -- | Pre Walk Through (0) | Thursday after meeting 12/7 | |
| -- | -- | Cleaning (1) | Tom will follow up with Kelly | |
| -- | -- | Certificate of Occupancy (1) * | ||
| -- | -- | C.O. to Lender (0) | ||
| -- | -- | Schedule Closing (0) | ||
| -- | -- | Buyer Walk Through (1) * | ||
| -- | -- | Payment for Upgrades (0) | ||
| -- | -- | Keys to Settlement Agent (0) | ||
| -- | -- | Review Settlement Statement (0) | ||
| -- | -- | Jerry Signs Closing Documents (0) | ||
| -- | -- | Closing (1) | Wed, Dec 13 @ 12PM @ WVT | |
| -- | -- | Remove Coded Lockbox (0) | ||