Thu |
Nov 28 |
Ratified Contract? (0) |
|
|
Thu |
Nov 28 |
$2500 Deposit Received (0) |
|
|
Thu |
Nov 28 |
Association Packet Requested (0) |
|
|
Thu |
Nov 28 |
Association Packet Received (0) |
|
|
Thu |
Nov 28 |
Selections Meeting (0) |
|
|
Thu |
Nov 28 |
Selections Sheet Signed (0) |
|
|
Thu |
Nov 28 |
Amendment for Upgrades (B,S,L,T,BCP) (0) |
|
|
Thu |
Nov 28 |
Deposit For Upgrades Received (0) |
|
|
Thu |
Nov 28 |
Inspection (Concrete Wall) (1) |
|
|
Fri |
Nov 29 |
Inspection (Conduit Under Slab) (1) |
|
|
Mon |
Dec 2 |
Inspection (Drain Tile) (0) |
|
|
Mon |
Dec 2 |
Settlement Agent Confirmed (0) |
|
|
Mon |
Dec 2 |
Verify Window & Roof Structure (0) |
|
|
Mon |
Dec 2 |
Order Appliances (0) |
|
|
Mon |
Dec 2 |
Patio (0) |
|
|
Mon |
Dec 2 |
Rough In Microwave Vent (0) |
|
|
Mon |
Dec 2 |
Inspection (Rough In Plumbing) (1) |
|
|
Tue |
Dec 3 |
Inspection (Rough In Electric) (1) |
|
|
Wed |
Dec 4 |
Inspection (Deck Piers) (0) |
|
|
Wed |
Dec 4 |
Inspection (Framing) (1) |
|
|
Thu |
Dec 5 |
Exterior Stone (0) |
|
|
Thu |
Dec 5 |
Set Electric Meter (0) |
|
|
Thu |
Dec 5 |
Inspection (Main Water Line) (0) |
|
|
Thu |
Dec 5 |
Loan Approval (0) |
|
|
Thu |
Dec 5 |
Deed Preparation (0) |
|
|
Thu |
Dec 5 |
Mailbox (0) |
|
|
Thu |
Dec 5 |
Interior Trim - Paint (1) |
|
|
Fri |
Dec 6 |
Ceiling Fans (0) |
|
|
Fri |
Dec 6 |
Blower Door Test (1) |
|
|
Mon |
Dec 9 |
Inspection (Final HVAC) (1) |
|
|
Tue |
Dec 10 |
Inspection (Final Plumbing) (1) |
|
|
Wed |
Dec 11 |
Inspection (Final Electric) (1) |
|
|
Thu |
Dec 12 |
Stain Hardwood Stairs (1) |
|
|
Fri |
Dec 13 |
Request Trash Tote From POA Manager (0) |
|
|
|
-- |
-- |
Missing Twin Dormers |
|
|
-- |
-- |
Repair damaged tub |
Mindy - waiting on water and electricity |
|
-- |
-- |
Adjust sewer stub is too close too the firewall |
Mindy |
|
-- |
-- |
Garage door |
|
|
-- |
-- |
Powder bath, change door swing |
Kate will tell Mitch |
|
-- |
-- |
Pave driveway |
|
|
-- |
-- |
Remove debris on Thursday for cleaners |
Tom |
|
-- |
-- |
CODED LOCKBOX --- 3438 |
|
|
-- |
-- |
Where are extra keys? |
|
|
-- |
-- |
COMCAST |
|
|
-- |
-- |
Install weather stripping |
|
|
-- |
-- |
Creaks in floor in 2nd and 3rd bedroom |
|
|
-- |
-- |
Adjust laundry room door which is difficult to close |
|
|
-- |
-- |
Upper level newel post needs sanding |
|
|
-- |
-- |
Touch up paint |
|
|
-- |
-- |
Remove coded lockbox |
|
|
-- |
-- |
Vacuum floor vent ductwork |
|
|
-- |
-- |
Repair bow in hall flooring above stairway |
Monday, Dec 18 - Eric |
|
-- |
-- |
Install screens |
Arriving Monday, Dec 18 |
|
-- |
-- |
Paint final coat on front door |
(green) |
|
-- |
-- |
Adjust cabinets next to refrigerator |
Adjust right door, straighten bar on left door |
|
-- |
-- |
Repair missing chunk of window in master bedroom |
Isaac |
|
-- |
-- |
Remove glue in corner of left window in master bedroom |
|
|
-- |
-- |
Install missing bracket at shelves in master closet |
|
|
-- |
-- |
Caulk gap at floor in pantry and install quarter round |
|
|
-- |
-- |
Install missing stopper at upstairs hall bath |
Mindy |
|
-- |
-- |
Clean inside refrigerator |
|
|
-- |
-- |
Install PVC under back patio door |
|
|
-- |
-- |
Adjust front door so lock is secure |
|
|
-- |
-- |
Secure upper railing going to kitchen |
|
|
-- |
-- |
Patch holes in mechnical room |
Majyer |
|
-- |
-- |
Install additional light in basement |
|
|
-- |
-- |
Touch up paint at edge of lower overhang |
Ceiling of foyer - Majyjyjyer |
|
-- |
-- |
Clean basement bath |
|
|
-- |
-- |
Secure plumbing in basement bathroom |
|
|
-- |
-- |
Connect garage door opener to door |
|
|
-- |
-- |
Fill and paint gaps at garage door frame |
|
|
-- |
-- |
Raise chandelier |
Tom will tell Harry |
|
-- |
-- |
Repair flooring issues on kitchen half of main level |
Tom meeting her today 4/23 after 12. |
|
-- |
-- |
Cracked foundation wall |
Materials on order as of Aug 27 |
|
-- |
-- |
Extended warranty on foundation? |
|
|
-- |
-- |
Patch drywall |
|
|
-- |
-- |
Install carpet |
|
|
-- |
-- |
Baseboard and paint |
|
|
-- |
-- |
Water leak/drywall repair |
Ronnie re-caulking a/c line |
|
-- |
-- |
Building Permit (30) |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) |
|
|
-- |
-- |
Order Windows & Doors (0) |
|
|
-- |
-- |
Stake Out Home (1) |
|
|
-- |
-- |
Excavate (2) |
|
|
-- |
-- |
Inspection (Footers) (1) |
|
|
-- |
-- |
Pour Footers (1) |
|
|
-- |
-- |
Set Forms (2) |
|
|
-- |
-- |
Pour Foundation Walls (1) |
|
|
-- |
-- |
Plumb Slab (2) |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
-- |
-- |
Prepare Slab (1) |
|
|
-- |
-- |
Inspection (Slab) (1) |
|
|
-- |
-- |
Pour Slab (1) * |
|
|
-- |
-- |
Framing I (9) |
|
|
-- |
-- |
Order Steps (0) |
|
|
-- |
-- |
Order Tubs / Showers (0) |
|
|
-- |
-- |
Framing II (8) |
|
|
-- |
-- |
Framing III (8) * |
|
|
-- |
-- |
Install Stairs (0) |
|
|
-- |
-- |
Windows & Doors (0) |
|
|
-- |
-- |
House Number and Status in Window (0) |
|
|
-- |
-- |
Roofing (0) |
|
|
-- |
-- |
Order Cabinets (0) |
|
|
-- |
-- |
Deck (0) |
|
|
-- |
-- |
Gutters (0) |
|
|
-- |
-- |
Driveway (0) |
|
|
-- |
-- |
Privacy Divider / Fence (0) |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) |
|
|
-- |
-- |
HVAC Rough In (4) |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) |
Thursday, Sept14 |
|
-- |
-- |
Plumbing Rough In (4) |
Started 9/7 |
|
-- |
-- |
Electric Rough In (4) |
8/28 in process |
|
-- |
-- |
Exterior Vinyl (0) * |
|
|
-- |
-- |
Insulation (2) |
|
|
-- |
-- |
Inspection (Insulation) (1) |
|
|
-- |
-- |
Inspection (Electric Service) (0) |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) |
|
|
-- |
-- |
Order Interior Doors & Trim (0) |
|
|
-- |
-- |
Drywall (Hang) (4) * |
Complete today 10/9 |
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
|
|
-- |
-- |
Paint 1 (1) |
Tue, Oct 10 |
|
-- |
-- |
Garage Door (0) |
|
|
-- |
-- |
House Numbers (0) |
|
|
-- |
-- |
Cabinet Installation (2) * |
in process |
|
-- |
-- |
Granite Installation (1) * |
|
|
-- |
-- |
Interior Trim - Install (3) |
In process |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * |
|
|
-- |
-- |
Luxury Vinyl Tile (0) |
Beginning 10/23 |
|
-- |
-- |
Paint 2 (3) |
In process |
|
-- |
-- |
Cover Floors (1) |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) |
|
|
-- |
-- |
Shoe Moulding (0) |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) |
Nearly complete- finishing week of 12/4 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) |
Pay Mon, Dec 4 |
|
-- |
-- |
Set Water Meter (0) |
|
|
-- |
-- |
Electric Trim Out (3) |
Nearly Complete- finishing 12/4 |
|
-- |
-- |
HVAC Trim Out (1) |
|
|
-- |
-- |
Plumbing Trim Out (2) |
Tue, Dec 5 |
|
-- |
-- |
Install Appliances (0) * |
Mon, Dec 4 |
|
-- |
-- |
Paint 3 (2) * |
In Process now complete by 12/4 |
|
-- |
-- |
Carpet (2) |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) |
|
|
-- |
-- |
Inspection (Final Building) (2) * |
Wed, Dec 6 - Mindy will schedule |
|
-- |
-- |
Pre Walk Through (0) |
Thursday after meeting 12/7 |
|
-- |
-- |
Cleaning (1) |
Tom will follow up with Kelly |
|
-- |
-- |
Certificate of Occupancy (1) * |
|
|
-- |
-- |
C.O. to Lender (0) |
|
|
-- |
-- |
Schedule Closing (0) |
|
|
-- |
-- |
Buyer Walk Through (1) |
|
|
-- |
-- |
Payment for Upgrades (0) |
|
|
-- |
-- |
Keys to Settlement Agent (0) |
|
|
-- |
-- |
Review Settlement Statement (0) |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) |
|
|
-- |
-- |
Closing (1) |
Wed, Dec 13 @ 12PM @ WVT |
|
-- |
-- |
Remove Coded Lockbox (0) |
|
|