ADDR
- 117  ::  374 Tanzanite Drive
[ BUILD: 17040010 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Apr 29      Ratified Contract? (0)      
Tue    Apr 29      $2500 Deposit Received (0)      
Tue    Apr 29      Association Packet Requested (0)      
Tue    Apr 29      Association Packet Received (0)      
Tue    Apr 29      Selections Meeting (0)      
Tue    Apr 29      Selections Sheet Signed (0)      
Tue    Apr 29      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Apr 29      Deposit For Upgrades Received (0)      
Tue    Apr 29      Inspection (Concrete Wall) (1)      
Wed    Apr 30      Inspection (Conduit Under Slab) (1)      
Thu    May 1      Inspection (Drain Tile) (0)      
Thu    May 1      Settlement Agent Confirmed (0)      
Thu    May 1      Verify Window & Roof Structure (0)      
Thu    May 1      Order Appliances (0)      
Thu    May 1      Patio (0)      
Thu    May 1      Rough In Microwave Vent (0)      
Thu    May 1      Inspection (Rough In Plumbing) (1)      
Fri    May 2      Inspection (Rough In Electric) (1)      
Mon    May 5      Inspection (Deck Piers) (0)      
Mon    May 5      Inspection (Framing) (1) *       
Tue    May 6      Exterior Stone (0)      
Tue    May 6      Set Electric Meter (0) *       
Tue    May 6      Inspection (Main Water Line) (0)      
Tue    May 6      Loan Approval (0)      
Tue    May 6      Deed Preparation (0)      
Tue    May 6      Mailbox (0)      
Tue    May 6      Interior Trim - Paint (1)      
Wed    May 7      Ceiling Fans (0)      
Wed    May 7      Blower Door Test (1)      
Thu    May 8      Inspection (Final HVAC) (1)      
Fri    May 9      Inspection (Final Plumbing) (1)      
Mon    May 12      Inspection (Final Electric) (1)      
Tue    May 13      Stain Hardwood Stairs (1)      
Wed    May 14      Request Trash Tote From POA Manager (0)      
--   --   Missing Twin Dormers
--   --   Repair damaged tub Mindy - waiting on water and electricity
--   --   Adjust sewer stub is too close too the firewall Mindy
--   --   Garage door
--   --   Powder bath, change door swing Kate will tell Mitch
--   --   Pave driveway
--   --   Remove debris on Thursday for cleaners Tom
--   --   CODED LOCKBOX --- 3438
--   --   Where are extra keys?
--   --   COMCAST
--   --   Install weather stripping
--   --   Creaks in floor in 2nd and 3rd bedroom
--   --   Adjust laundry room door which is difficult to close
--   --   Upper level newel post needs sanding
--   --   Touch up paint
--   --   Remove coded lockbox
--   --   Vacuum floor vent ductwork
--   --   Repair bow in hall flooring above stairway Monday, Dec 18 - Eric
--   --   Install screens Arriving Monday, Dec 18
--   --   Paint final coat on front door (green)
--   --   Adjust cabinets next to refrigerator Adjust right door, straighten bar on left door
--   --   Repair missing chunk of window in master bedroom Isaac
--   --   Remove glue in corner of left window in master bedroom
--   --   Install missing bracket at shelves in master closet
--   --   Caulk gap at floor in pantry and install quarter round
--   --   Install missing stopper at upstairs hall bath Mindy
--   --   Clean inside refrigerator
--   --   Install PVC under back patio door
--   --   Adjust front door so lock is secure
--   --   Secure upper railing going to kitchen
--   --   Patch holes in mechnical room Majyer
--   --   Install additional light in basement
--   --   Touch up paint at edge of lower overhang Ceiling of foyer - Majyjyjyer
--   --   Clean basement bath
--   --   Secure plumbing in basement bathroom
--   --   Connect garage door opener to door
--   --   Fill and paint gaps at garage door frame
--   --   Raise chandelier Tom will tell Harry
--   --   Repair flooring issues on kitchen half of main level Tom meeting her today 4/23 after 12.
--   --   Cracked foundation wall Materials on order as of Aug 27
--   --   Extended warranty on foundation?
--   --   Patch drywall
--   --   Install carpet
--   --   Baseboard and paint
--   --   Water leak/drywall repair Ronnie re-caulking a/c line
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       Thursday, Sept14
-- -- Plumbing Rough In (4)       Started 9/7
-- -- Electric Rough In (4)       8/28 in process
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        Complete today 10/9
-- -- Drywall (Tape, Block, Skim, Sand) (6) *       
-- -- Paint 1 (1)       Tue, Oct 10
-- -- Garage Door (0) *       
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        in process
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3) *        In process
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Beginning 10/23
-- -- Paint 2 (3)       In process
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        Nearly complete- finishing week of 12/4
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)       Pay Mon, Dec 4
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3)       Nearly Complete- finishing 12/4
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       Tue, Dec 5
-- -- Install Appliances (0) *        Mon, Dec 4
-- -- Paint 3 (2) *        In Process now complete by 12/4
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Wed, Dec 6 - Mindy will schedule
-- -- Pre Walk Through (0)       Thursday after meeting 12/7
-- -- Cleaning (1)       Tom will follow up with Kelly
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1)      
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       Wed, Dec 13 @ 12PM @ WVT
-- -- Remove Coded Lockbox (0)