Fri |
Sep 20 |
Ratified Contract? (0)
|
|
|
Fri |
Sep 20 |
$2500 Deposit Received (0)
|
|
|
Fri |
Sep 20 |
Association Packet Requested (0)
|
|
|
Fri |
Sep 20 |
Association Packet Received (0)
|
|
|
Fri |
Sep 20 |
Selections Meeting (0)
|
|
|
Fri |
Sep 20 |
Selections Sheet Signed (0)
|
|
|
Fri |
Sep 20 |
Amendment for Upgrades (B,S,L,T,BCP) (0)
|
|
|
Fri |
Sep 20 |
Deposit For Upgrades Received (0)
|
|
|
Fri |
Sep 20 |
Inspection (Concrete Wall) (1)
|
|
|
Mon |
Sep 23 |
Inspection (Conduit Under Slab) (1)
|
|
|
Tue |
Sep 24 |
Inspection (Drain Tile) (0)
|
|
|
Tue |
Sep 24 |
Settlement Agent Confirmed (0)
|
|
|
Tue |
Sep 24 |
Verify Window & Roof Structure (0)
|
|
|
Tue |
Sep 24 |
Order Appliances (0)
|
|
|
Tue |
Sep 24 |
Patio (0)
|
|
|
Tue |
Sep 24 |
Rough In Microwave Vent (0)
|
|
|
Tue |
Sep 24 |
Inspection (Rough In Plumbing) (1)
|
|
|
Wed |
Sep 25 |
Inspection (Rough In Electric) (1)
|
|
|
Thu |
Sep 26 |
Inspection (Deck Piers) (0)
|
|
|
Thu |
Sep 26 |
Inspection (Framing) (1)
|
|
|
Fri |
Sep 27 |
Exterior Stone (0)
|
|
|
Fri |
Sep 27 |
Set Electric Meter (0)
|
|
|
Fri |
Sep 27 |
Inspection (Main Water Line) (0)
|
|
|
Fri |
Sep 27 |
Loan Approval (0)
|
|
|
Fri |
Sep 27 |
Deed Preparation (0)
|
|
|
Fri |
Sep 27 |
Mailbox (0)
|
|
|
Fri |
Sep 27 |
Order Plumbing / Lighting Fixtures (0)
|
|
|
Fri |
Sep 27 |
Interior Trim - Paint (1)
|
|
|
Mon |
Sep 30 |
Ceiling Fans (0)
|
|
|
Mon |
Sep 30 |
Blower Door Test (1)
|
|
|
Tue |
Oct 1 |
Inspection (Final HVAC) (1)
|
|
|
Wed |
Oct 2 |
Inspection (Final Plumbing) (1)
|
|
|
Thu |
Oct 3 |
Inspection (Final Electric) (1)
|
|
|
Fri |
Oct 4 |
Stain Hardwood Stairs (1)
|
|
|
Mon |
Oct 7 |
Schedule Closing (0)
|
|
|
Mon |
Oct 7 |
Keys to Settlement Agent (0)
|
|
|
Mon |
Oct 7 |
Review Settlement Statement (0)
|
|
|
Mon |
Oct 7 |
Jerry Signs Closing Documents (0)
|
|
|
Mon |
Oct 7 |
Request Trash Tote From POA Manager (0)
|
|
|
Mon |
Oct 7 |
Remove Coded Lockbox (0)
|
|
|
|
-- |
-- |
Garage door |
|
|
-- |
-- |
Install last section of siding |
Done by Tues, Nov 14 |
|
-- |
-- |
Interest Rate Expires Nov 30! |
$445 to extend to Dec 15 |
|
-- |
-- |
Need outside lights, dining lights, pendant lights, keyless light for basement |
Harry is complete except these fixtures |
|
-- |
-- |
Trim-shoemold Monday 20th |
After hardwood |
|
-- |
-- |
Gutters |
Tues, Dec 12 |
|
-- |
-- |
Pave driveway |
|
|
-- |
-- |
Only need 2 ft. fluorescent - single bulb- Tom -trailor? |
|
|
-- |
-- |
When should buyer do home inspection? |
Fri, Dec 8 - to be scheduled |
|
-- |
-- |
Remove debris on Thursday for cleaners |
|
|
-- |
-- |
Stain stairs |
Waiting on clear coat |
|
-- |
-- |
CODED LOCKBOX --- 8865 |
|
|
-- |
-- |
Where are extra keys? |
|
|
-- |
-- |
COMCAST |
|
|
-- |
-- |
Bathroom vent cover |
|
|
-- |
-- |
Repair scratches in hardwood flooring |
|
|
-- |
-- |
Remove coded lockbox |
|
|
-- |
-- |
Cleaning |
floors, garage, etc. |
|
-- |
-- |
Caulk at walls and corner in pantry |
|
|
-- |
-- |
Caulk in half bathroom behind sink to floor, quarter round |
|
|
-- |
-- |
Secure escutcheon in half bathroom |
|
|
-- |
-- |
Caulk in coat closet |
|
|
-- |
-- |
Caulk in half bathroom upstairs near vanity |
|
|
-- |
-- |
Touch up paint at stairs to upper level on baseboard on the right |
|
|
-- |
-- |
Paint in between laundry room door frame and master bedroom |
|
|
-- |
-- |
Touch up paint on master door frame |
|
|
-- |
-- |
Straighten threshold at hall bathroom upstairs |
|
|
-- |
-- |
Add or adjust door hardware at basement utility closet |
Tom |
|
-- |
-- |
Change (?) unfinished basement room door to remove gap under door |
|
|
-- |
-- |
Adjust person door between garage and hallway to open more easily |
|
|
-- |
-- |
Touch up paint and caulk throughout home |
|
|
-- |
-- |
Secure door frame at storage under stairs |
|
|
-- |
-- |
Repair quarter round under front left window |
|
|
-- |
-- |
Repair baseboard under living room right window |
|
|
-- |
-- |
Install missing guides at laundry room pocket dor |
|
|
-- |
-- |
Install missing guides at laundry room pocket door |
|
|
-- |
-- |
Repair trim at master bedroom door frame at top and lock |
|
|
-- |
-- |
Repair master bedroom drawer on inside at chip that prevents smooth operation |
|
|
-- |
-- |
Secure escutcheon at shower head in master bathroom |
|
|
-- |
-- |
Paint final coat on front door |
|
|
-- |
-- |
Align left and right refrigerator doors |
|
|
-- |
-- |
Install door stop at pantry entry door |
|
|
-- |
-- |
Attach (and paint?) quarter round at back patio door |
|
|
-- |
-- |
Re-install tree |
Tom will remind Pettit |
|
-- |
-- |
Repair leak and drywall |
|
|
-- |
-- |
Garrett = 805-444-8370 |
|
|
-- |
-- |
Building Permit (30)
|
|
|
-- |
-- |
Order Roof & Floor Trusses (1)
|
|
|
-- |
-- |
Order Windows & Doors (0)
|
|
|
-- |
-- |
Stake Out Home (1)
|
|
|
-- |
-- |
Excavate (2)
|
|
|
-- |
-- |
Inspection (Footers) (1)
|
|
|
-- |
-- |
Pour Footers (1)
|
|
|
-- |
-- |
Set Forms (2)
|
|
|
-- |
-- |
Pour Foundation Walls (1)
|
|
|
-- |
-- |
Plumb Slab (2)
|
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1)
|
|
|
-- |
-- |
Prepare Slab (1)
|
|
|
-- |
-- |
Inspection (Slab) (1)
|
|
|
-- |
-- |
Pour Slab (1)
|
|
|
-- |
-- |
Framing I (9)
|
|
|
-- |
-- |
Order Steps (0)
|
|
|
-- |
-- |
Order Tubs / Showers (0)
|
|
|
-- |
-- |
Framing II (8)
|
|
|
-- |
-- |
Framing III (8)
|
|
|
-- |
-- |
Install Stairs (0)
|
|
|
-- |
-- |
Windows & Doors (0)
|
|
|
-- |
-- |
House Number and Status in Window (0)
|
|
|
-- |
-- |
Roofing (0)
|
|
|
-- |
-- |
Order Cabinets (0)
|
|
|
-- |
-- |
Deck (0)
|
|
|
-- |
-- |
Gutters (0)
|
|
|
-- |
-- |
Driveway (0)
|
|
|
-- |
-- |
Privacy Divider / Fence (0)
|
|
|
-- |
-- |
Sod / Seed / Landscaping (0)
|
|
|
-- |
-- |
HVAC Rough In (4)
|
|
|
-- |
-- |
Inspection (Rough In HVAC) (1)
|
Tues, Sep 19 / Wed, Sep 20 |
|
-- |
-- |
Plumbing Rough In (4)
|
Happening now - Sept 14 |
|
-- |
-- |
Electric Rough In (4)
|
Almost done 9/7 |
|
-- |
-- |
Exterior Vinyl (0)
|
|
|
-- |
-- |
Insulation (2)
|
Thu, Sep 21 |
|
-- |
-- |
Inspection (Insulation) (1)
|
Mon, Sep 25 |
|
-- |
-- |
Inspection (Electric Service) (0)
|
|
|
-- |
-- |
Inspection (Main Sewer Line) (0)
|
|
|
-- |
-- |
Order Interior Doors & Trim (0)
|
|
|
-- |
-- |
Drywall (Hang) (4)
|
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6)
|
will be complete Friday 10/20 |
|
-- |
-- |
Paint 1 (1)
|
Saturday 10/21 |
|
-- |
-- |
Garage Door (0)
|
|
|
-- |
-- |
House Numbers (0)
|
|
|
-- |
-- |
Cabinet Installation (2)
|
Deliver Oct 20, Install Oct 23 |
|
-- |
-- |
Granite Installation (1)
|
11/10 |
|
-- |
-- |
Interior Trim - Install (3)
|
In process- nearly complete- waiting on tile to finish |
|
-- |
-- |
Luxury Vinyl Plank (3)
|
|
|
-- |
-- |
Luxury Vinyl Tile (0)
|
Will be complete 11/15 |
|
-- |
-- |
Paint 2 (3)
|
Monday 11/13 |
|
-- |
-- |
Cover Floors (1)
|
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0)
|
|
|
-- |
-- |
Shoe Moulding (0)
|
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0)
|
tuesday Wednesday 28-29 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0)
|
|
|
-- |
-- |
Pay Water / Sewer Taps (0)
|
Pay Mon, Dec 4 |
|
-- |
-- |
Set Water Meter (0)
|
|
|
-- |
-- |
Electric Trim Out (3)
|
November 14- |
|
-- |
-- |
HVAC Trim Out (1)
|
|
|
-- |
-- |
Plumbing Trim Out (2)
|
Wed, Nov 29 |
|
-- |
-- |
Install Appliances (0)
|
Mon, Dec 4 |
|
-- |
-- |
Paint 3 (2)
|
Tues, Dec 12 |
|
-- |
-- |
Carpet (2)
|
Tue, Dec 5 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0)
|
Tues, Dec 12 (Steve, Aper Appraisals) |
|
-- |
-- |
Inspection (Final Building) (2)
|
|
|
-- |
-- |
Pre Walk Through (0)
|
Thursday after meeting 12/7 |
|
-- |
-- |
Cleaning (1)
|
|
|
-- |
-- |
Certificate of Occupancy (1)
|
|
|
-- |
-- |
C.O. to Lender (0)
|
|
|
-- |
-- |
Buyer Walk Through (1)
|
Thursday, Dec 14 @ 10:30 AM |
|
-- |
-- |
Payment for Upgrades (0)
|
|
|
-- |
-- |
Closing (1)
|
|
|