| Tue | Dec 16 | Ratified Contract? (0) | ||
| Tue | Dec 16 | $2500 Deposit Received (0) | ||
| Tue | Dec 16 | Association Packet Requested (0) | ||
| Tue | Dec 16 | Association Packet Received (0) | ||
| Tue | Dec 16 | Selections Meeting (0) | ||
| Tue | Dec 16 | Selections Sheet Signed (0) | ||
| Tue | Dec 16 | Amendment for Upgrades (B,S,L,T,BCP) (0) | ||
| Tue | Dec 16 | Deposit For Upgrades Received (0) | ||
| Tue | Dec 16 | Inspection (Concrete Wall) (1) | ||
| Wed | Dec 17 | Inspection (Conduit Under Slab) (1) | ||
| Thu | Dec 18 | Inspection (Drain Tile) (0) | ||
| Thu | Dec 18 | Settlement Agent Confirmed (0) | ||
| Thu | Dec 18 | Verify Window & Roof Structure (0) | ||
| Thu | Dec 18 | Order Appliances (0) | ||
| Thu | Dec 18 | Patio (0) | ||
| Thu | Dec 18 | Rough In Microwave Vent (0) | ||
| Thu | Dec 18 | Inspection (Rough In Plumbing) (1) | ||
| Fri | Dec 19 | Inspection (Rough In Electric) (1) | ||
| Mon | Dec 22 | Inspection (Framing) (1) * | ||
| Tue | Dec 23 | Inspection (Deck Piers) (0) | ||
| Tue | Dec 23 | Exterior Stone (0) | ||
| Tue | Dec 23 | Set Electric Meter (0) * | ||
| Tue | Dec 23 | Inspection (Main Water Line) (0) | ||
| Tue | Dec 23 | Loan Approval (0) | ||
| Tue | Dec 23 | Deed Preparation (0) | ||
| Tue | Dec 23 | Mailbox (0) | ||
| Tue | Dec 23 | Order Plumbing / Lighting Fixtures (0) | ||
| Tue | Dec 23 | Interior Trim - Paint (1) | ||
| Wed | Dec 24 | Ceiling Fans (0) | ||
| Wed | Dec 24 | Blower Door Test (1) | ||
| Thu | Dec 25 | Inspection (Final HVAC) (1) | ||
| Fri | Dec 26 | Inspection (Final Plumbing) (1) | ||
| Mon | Dec 29 | Inspection (Final Electric) (1) | ||
| Tue | Dec 30 | Stain Hardwood Stairs (1) * | ||
| Wed | Dec 31 | Schedule Closing (0) | ||
| Wed | Dec 31 | Keys to Settlement Agent (0) | ||
| Wed | Dec 31 | Review Settlement Statement (0) | ||
| Wed | Dec 31 | Jerry Signs Closing Documents (0) | ||
| Wed | Dec 31 | Request Trash Tote From POA Manager (0) | ||
| Wed | Dec 31 | Remove Coded Lockbox (0) | ||
| -- | -- | Garage door | ||
| -- | -- | Install last section of siding | Done by Tues, Nov 14 | |
| -- | -- | Interest Rate Expires Nov 30! | $445 to extend to Dec 15 | |
| -- | -- | Need outside lights, dining lights, pendant lights, keyless light for basement | Harry is complete except these fixtures | |
| -- | -- | Trim-shoemold Monday 20th | After hardwood | |
| -- | -- | Gutters | Tues, Dec 12 | |
| -- | -- | Pave driveway | ||
| -- | -- | Only need 2 ft. fluorescent - single bulb- Tom -trailor? | ||
| -- | -- | When should buyer do home inspection? | Fri, Dec 8 - to be scheduled | |
| -- | -- | Remove debris on Thursday for cleaners | ||
| -- | -- | Stain stairs | Waiting on clear coat | |
| -- | -- | CODED LOCKBOX --- 8865 | ||
| -- | -- | Where are extra keys? | ||
| -- | -- | COMCAST | ||
| -- | -- | Bathroom vent cover | ||
| -- | -- | Repair scratches in hardwood flooring | ||
| -- | -- | Remove coded lockbox | ||
| -- | -- | Cleaning | floors, garage, etc. | |
| -- | -- | Caulk at walls and corner in pantry | ||
| -- | -- | Caulk in half bathroom behind sink to floor, quarter round | ||
| -- | -- | Secure escutcheon in half bathroom | ||
| -- | -- | Caulk in coat closet | ||
| -- | -- | Caulk in half bathroom upstairs near vanity | ||
| -- | -- | Touch up paint at stairs to upper level on baseboard on the right | ||
| -- | -- | Paint in between laundry room door frame and master bedroom | ||
| -- | -- | Touch up paint on master door frame | ||
| -- | -- | Straighten threshold at hall bathroom upstairs | ||
| -- | -- | Add or adjust door hardware at basement utility closet | Tom | |
| -- | -- | Change (?) unfinished basement room door to remove gap under door | ||
| -- | -- | Adjust person door between garage and hallway to open more easily | ||
| -- | -- | Touch up paint and caulk throughout home | ||
| -- | -- | Secure door frame at storage under stairs | ||
| -- | -- | Repair quarter round under front left window | ||
| -- | -- | Repair baseboard under living room right window | ||
| -- | -- | Install missing guides at laundry room pocket dor | ||
| -- | -- | Install missing guides at laundry room pocket door | ||
| -- | -- | Repair trim at master bedroom door frame at top and lock | ||
| -- | -- | Repair master bedroom drawer on inside at chip that prevents smooth operation | ||
| -- | -- | Secure escutcheon at shower head in master bathroom | ||
| -- | -- | Paint final coat on front door | ||
| -- | -- | Align left and right refrigerator doors | ||
| -- | -- | Install door stop at pantry entry door | ||
| -- | -- | Attach (and paint?) quarter round at back patio door | ||
| -- | -- | Re-install tree | Tom will remind Pettit | |
| -- | -- | Repair leak and drywall | ||
| -- | -- | Garrett = 805-444-8370 | ||
| -- | -- | Building Permit (30) * | ||
| -- | -- | Order Roof & Floor Trusses (1) | ||
| -- | -- | Order Windows & Doors (0) | ||
| -- | -- | Stake Out Home (1) | ||
| -- | -- | Excavate (2) | ||
| -- | -- | Inspection (Footers) (1) | ||
| -- | -- | Pour Footers (1) * | ||
| -- | -- | Set Forms (2) | ||
| -- | -- | Pour Foundation Walls (1) | ||
| -- | -- | Plumb Slab (2) | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) | ||
| -- | -- | Prepare Slab (1) | ||
| -- | -- | Inspection (Slab) (1) | ||
| -- | -- | Pour Slab (1) * | ||
| -- | -- | Framing I (9) | ||
| -- | -- | Order Steps (0) | ||
| -- | -- | Order Tubs / Showers (0) | ||
| -- | -- | Framing II (8) | ||
| -- | -- | Framing III (8) * | ||
| -- | -- | Install Stairs (0) * | ||
| -- | -- | Windows & Doors (0) * | ||
| -- | -- | House Number and Status in Window (0) | ||
| -- | -- | Roofing (0) * | ||
| -- | -- | Order Cabinets (0) | ||
| -- | -- | Deck (0) | ||
| -- | -- | Gutters (0) | ||
| -- | -- | Driveway (0) * | ||
| -- | -- | Privacy Divider / Fence (0) * | ||
| -- | -- | Sod / Seed / Landscaping (0) | ||
| -- | -- | HVAC Rough In (4) | ||
| -- | -- | Plumbing Rough In (4) | Happening now - Sept 14 | |
| -- | -- | Electric Rough In (4) | Almost done 9/7 | |
| -- | -- | Inspection (Rough In HVAC) (1) | Tues, Sep 19 / Wed, Sep 20 | |
| -- | -- | Exterior Vinyl (0) * | ||
| -- | -- | Insulation (2) * | Thu, Sep 21 | |
| -- | -- | Inspection (Insulation) (1) | Mon, Sep 25 | |
| -- | -- | Inspection (Electric Service) (0) | ||
| -- | -- | Inspection (Main Sewer Line) (0) | ||
| -- | -- | Order Interior Doors & Trim (0) | ||
| -- | -- | Drywall (Hang) (4) * | ||
| -- | -- | Drywall (Tape, Block, Skim, Sand) (6) * | will be complete Friday 10/20 | |
| -- | -- | Paint 1 (1) | Saturday 10/21 | |
| -- | -- | Garage Door (0) | ||
| -- | -- | House Numbers (0) | ||
| -- | -- | Cabinet Installation (2) * | Deliver Oct 20, Install Oct 23 | |
| -- | -- | Granite Installation (1) * | 11/10 | |
| -- | -- | Interior Trim - Install (3) * | In process- nearly complete- waiting on tile to finish | |
| -- | -- | Luxury Vinyl Plank (3) * | ||
| -- | -- | Luxury Vinyl Tile (0) | Will be complete 11/15 | |
| -- | -- | Paint 2 (3) | Monday 11/13 | |
| -- | -- | Cover Floors (1) | ||
| -- | -- | Deliver Plumbing / Lighting Fixtures (0) | ||
| -- | -- | Shoe Moulding (0) | ||
| -- | -- | Shelving, Door Knobs, Fire Extinguisher (0) * | tuesday Wednesday 28-29 | |
| -- | -- | Install Coded Lockbox (add extra keys) (0) | ||
| -- | -- | Pay Water / Sewer Taps (0) | Pay Mon, Dec 4 | |
| -- | -- | Set Water Meter (0) * | ||
| -- | -- | Electric Trim Out (3) * | November 14- | |
| -- | -- | HVAC Trim Out (1) * | ||
| -- | -- | Plumbing Trim Out (2) * | Wed, Nov 29 | |
| -- | -- | Install Appliances (0) * | Mon, Dec 4 | |
| -- | -- | Paint 3 (2) * | Tues, Dec 12 | |
| -- | -- | Carpet (2) | Tue, Dec 5 | |
| -- | -- | Appraiser Confirms Construction Completion (0) | Tues, Dec 12 (Steve, Aper Appraisals) | |
| -- | -- | Inspection (Final Building) (2) * | ||
| -- | -- | Pre Walk Through (0) | Thursday after meeting 12/7 | |
| -- | -- | Cleaning (1) | ||
| -- | -- | Certificate of Occupancy (1) * | ||
| -- | -- | C.O. to Lender (0) | ||
| -- | -- | Buyer Walk Through (1) * | Thursday, Dec 14 @ 10:30 AM | |
| -- | -- | Payment for Upgrades (0) | ||
| -- | -- | Closing (1) | ||