- 86  ::  332 Sapphire Drive
[ BUILD: 170500115 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Fri    Sep 20      Ratified Contract? (0)      
Fri    Sep 20      $2500 Deposit Received (0)      
Fri    Sep 20      Association Packet Requested (0)      
Fri    Sep 20      Association Packet Received (0)      
Fri    Sep 20      Selections Meeting (0)      
Fri    Sep 20      Selections Sheet Signed (0)      
Fri    Sep 20      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Fri    Sep 20      Deposit For Upgrades Received (0)      
Fri    Sep 20      Inspection (Concrete Wall) (1)      
Mon    Sep 23      Inspection (Conduit Under Slab) (1)      
Tue    Sep 24      Inspection (Drain Tile) (0)      
Tue    Sep 24      Settlement Agent Confirmed (0)      
Tue    Sep 24      Verify Window & Roof Structure (0)      
Tue    Sep 24      Order Appliances (0)      
Tue    Sep 24      Patio (0)      
Tue    Sep 24      Rough In Microwave Vent (0)      
Tue    Sep 24      Inspection (Rough In Plumbing) (1)      
Wed    Sep 25      Inspection (Rough In Electric) (1)      
Thu    Sep 26      Inspection (Deck Piers) (0)      
Thu    Sep 26      Inspection (Framing) (1)      
Fri    Sep 27      Exterior Stone (0)      
Fri    Sep 27      Set Electric Meter (0)      
Fri    Sep 27      Inspection (Main Water Line) (0)      
Fri    Sep 27      Loan Approval (0)      
Fri    Sep 27      Deed Preparation (0)      
Fri    Sep 27      Mailbox (0)      
Fri    Sep 27      Order Plumbing / Lighting Fixtures (0)      
Fri    Sep 27      Interior Trim - Paint (1)      
Mon    Sep 30      Ceiling Fans (0)      
Mon    Sep 30      Blower Door Test (1)      
Tue    Oct 1      Inspection (Final HVAC) (1)      
Wed    Oct 2      Inspection (Final Plumbing) (1)      
Thu    Oct 3      Inspection (Final Electric) (1)      
Fri    Oct 4      Stain Hardwood Stairs (1)      
Mon    Oct 7      Schedule Closing (0)      
Mon    Oct 7      Keys to Settlement Agent (0)      
Mon    Oct 7      Review Settlement Statement (0)      
Mon    Oct 7      Jerry Signs Closing Documents (0)      
Mon    Oct 7      Request Trash Tote From POA Manager (0)      
Mon    Oct 7      Remove Coded Lockbox (0)      
--   --   Note: buyer changed tile from rectangle to square gray summit tile
--   --   Remove the shower Mindy
--   --   Repair the shower Mindy
--   --   Can the buyer move his washer/dryer in before construction is complete? Tell Morgan....
--   --   Finish drywall at front door
--   --   GREEN FRONT DOOR Needs painting as of October 13
--   --   Cover appliances Osbaldo
--   --   Broken window in living room Tom will order sash
--   --   CODED LOCKBOX --- 6787
--   --   Shoemold Mitch - Mon, Mar 12
--   --   Put fridge in place Osbaldo
--   --   Fix window trim in upstairs bedroom Osbaldo??
--   --   Trim down closet doors in upstairs bedrooms Mitch
--   --   Floor pops in middle of master bedroom Osbaldo
--   --   Stain and seal hardwood treads on stairs
--   --   Paint touchups throughout thome Isaac
--   --   tighten all shower escutheons Osbaldo
--   --   Adjust closet doors and trim bottom of doors Osbaldo - In bedroom behind hall bath
--   --   Adjust patio doors Osbaldo
--   --   Move fridge closer to cabinets Osbaldo
--   --   Sliding glass door adjustment and adjust lock Osbaldo
--   --   In basement, fix white wrap in corner
--   --   Cut sewer clean out outside Osbaldo
--   --   Fix front door dents or replace door Isaac
--   --   Patch hole in brick where porch ties to house
--   --   Caulk windows outside Osbaldo
--   --   Adjust deadbolt Osbaldo
--   --   Remove sticker from attic window Osbaldo
--   --   Add pipe to downspout in front Osbaldo
--   --   Fix laundry door Osbaldo
--   --   Remove excess caulk from bath tub
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1)      
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8)      
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)      
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)      
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       In process as of Nov 13
-- -- Inspection (Rough In HVAC) (1)       Inspection, Tues Dec 11
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)       Harry starts Mon, Dec 4
-- -- Exterior Vinyl (0)      
-- -- Insulation (2)       Maybe Mon, Dec 18
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4)       Starting hanging Jan 2
-- -- Drywall (Tape, Block, Skim, Sand) (6)       Needs sanding/ finish drywall at front door
-- -- Paint 1 (1)       Friday 1/19
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2)       Del 2/2, install 2/5- nearly complete
-- -- Granite Installation (1)      
-- -- Interior Trim - Install (3)       In process by Darrell complete by Monday 2/5
-- -- Luxury Vinyl Plank (3)      
-- -- Luxury Vinyl Tile (0)       Starting Monday 2/5
-- -- Paint 2 (3)       2/15- in process
-- -- Cover Floors (1)       Wed, Feb 21
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       In process
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       Fixtures being delivered Thursday 2/22
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       Fixtures being delivered Thursday 2/22
-- -- Install Appliances (0)      
-- -- Paint 3 (2)       After shoemold
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)       Robbie Miller going Friday, Mar 16
-- -- Inspection (Final Building) (2)       Fri, Mar 9
-- -- Pre Walk Through (0)       Kate, Osbaldo, Tom - Thursday
-- -- Cleaning (1)       Wed, Mar 28
-- -- Certificate of Occupancy (1)      
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1)       Fri, Mar 23
-- -- Payment for Upgrades (0)       $2,825
-- -- Closing (1)