- 86  ::  332 Sapphire Drive
[ BUILD: 170500115 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Inspection (Concrete Wall) (1)      
Wed    Dec 17      Inspection (Conduit Under Slab) (1)      
Thu    Dec 18      Inspection (Drain Tile) (0)      
Thu    Dec 18      Settlement Agent Confirmed (0)      
Thu    Dec 18      Verify Window & Roof Structure (0)      
Thu    Dec 18      Order Appliances (0)      
Thu    Dec 18      Patio (0)      
Thu    Dec 18      Rough In Microwave Vent (0)      
Thu    Dec 18      Inspection (Rough In Plumbing) (1)      
Fri    Dec 19      Inspection (Rough In Electric) (1)      
Mon    Dec 22      Inspection (Framing) (1) *       
Tue    Dec 23      Inspection (Deck Piers) (0)      
Tue    Dec 23      Exterior Stone (0)      
Tue    Dec 23      Set Electric Meter (0) *       
Tue    Dec 23      Inspection (Main Water Line) (0)      
Tue    Dec 23      Loan Approval (0)      
Tue    Dec 23      Deed Preparation (0)      
Tue    Dec 23      Mailbox (0)      
Tue    Dec 23      Order Plumbing / Lighting Fixtures (0)      
Tue    Dec 23      Interior Trim - Paint (1)      
Wed    Dec 24      Ceiling Fans (0)      
Wed    Dec 24      Blower Door Test (1)      
Thu    Dec 25      Inspection (Final HVAC) (1)      
Fri    Dec 26      Inspection (Final Plumbing) (1)      
Mon    Dec 29      Inspection (Final Electric) (1)      
Tue    Dec 30      Stain Hardwood Stairs (1) *       
Wed    Dec 31      Schedule Closing (0)      
Wed    Dec 31      Keys to Settlement Agent (0)      
Wed    Dec 31      Review Settlement Statement (0)      
Wed    Dec 31      Jerry Signs Closing Documents (0)      
Wed    Dec 31      Request Trash Tote From POA Manager (0)      
Wed    Dec 31      Remove Coded Lockbox (0)      
--   --   Note: buyer changed tile from rectangle to square gray summit tile
--   --   Remove the shower Mindy
--   --   Repair the shower Mindy
--   --   Can the buyer move his washer/dryer in before construction is complete? Tell Morgan....
--   --   Finish drywall at front door
--   --   GREEN FRONT DOOR Needs painting as of October 13
--   --   Cover appliances Osbaldo
--   --   Broken window in living room Tom will order sash
--   --   CODED LOCKBOX --- 6787
--   --   Shoemold Mitch - Mon, Mar 12
--   --   Put fridge in place Osbaldo
--   --   Fix window trim in upstairs bedroom Osbaldo??
--   --   Trim down closet doors in upstairs bedrooms Mitch
--   --   Floor pops in middle of master bedroom Osbaldo
--   --   Stain and seal hardwood treads on stairs
--   --   Paint touchups throughout thome Isaac
--   --   tighten all shower escutheons Osbaldo
--   --   Adjust closet doors and trim bottom of doors Osbaldo - In bedroom behind hall bath
--   --   Adjust patio doors Osbaldo
--   --   Move fridge closer to cabinets Osbaldo
--   --   Sliding glass door adjustment and adjust lock Osbaldo
--   --   In basement, fix white wrap in corner
--   --   Cut sewer clean out outside Osbaldo
--   --   Fix front door dents or replace door Isaac
--   --   Patch hole in brick where porch ties to house
--   --   Caulk windows outside Osbaldo
--   --   Adjust deadbolt Osbaldo
--   --   Remove sticker from attic window Osbaldo
--   --   Add pipe to downspout in front Osbaldo
--   --   Fix laundry door Osbaldo
--   --   Remove excess caulk from bath tub
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       In process as of Nov 13
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)       Harry starts Mon, Dec 4
-- -- Inspection (Rough In HVAC) (1)       Inspection, Tues Dec 11
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *        Maybe Mon, Dec 18
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        Starting hanging Jan 2
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Needs sanding/ finish drywall at front door
-- -- Paint 1 (1)       Friday 1/19
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Del 2/2, install 2/5- nearly complete
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3) *        In process by Darrell complete by Monday 2/5
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Starting Monday 2/5
-- -- Paint 2 (3)       2/15- in process
-- -- Cover Floors (1)       Wed, Feb 21
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        In process
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3) *        Fixtures being delivered Thursday 2/22
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *        Fixtures being delivered Thursday 2/22
-- -- Install Appliances (0) *       
-- -- Paint 3 (2) *        After shoemold
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)       Robbie Miller going Friday, Mar 16
-- -- Inspection (Final Building) (2) *        Fri, Mar 9
-- -- Pre Walk Through (0)       Kate, Osbaldo, Tom - Thursday
-- -- Cleaning (1)       Wed, Mar 28
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1) *        Fri, Mar 23
-- -- Payment for Upgrades (0)       $2,825
-- -- Closing (1)