ADDR
- 86  ::  332 Sapphire Drive
[ BUILD: 170500115 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Order Appliances (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Order Plumbing / Lighting Fixtures (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Ceiling Fans (0)      
Fri    Dec 6      Blower Door Test (1)      
Mon    Dec 9      Inspection (Final HVAC) (1)      
Tue    Dec 10      Inspection (Final Plumbing) (1)      
Wed    Dec 11      Inspection (Final Electric) (1)      
Thu    Dec 12      Stain Hardwood Stairs (1)      
Fri    Dec 13      Schedule Closing (0)      
Fri    Dec 13      Keys to Settlement Agent (0)      
Fri    Dec 13      Review Settlement Statement (0)      
Fri    Dec 13      Jerry Signs Closing Documents (0)      
Fri    Dec 13      Request Trash Tote From POA Manager (0)      
Fri    Dec 13      Remove Coded Lockbox (0)      
--   --   Note: buyer changed tile from rectangle to square gray summit tile
--   --   Remove the shower Mindy
--   --   Repair the shower Mindy
--   --   Can the buyer move his washer/dryer in before construction is complete? Tell Morgan....
--   --   Finish drywall at front door
--   --   GREEN FRONT DOOR Needs painting as of October 13
--   --   Cover appliances Osbaldo
--   --   Broken window in living room Tom will order sash
--   --   CODED LOCKBOX --- 6787
--   --   Shoemold Mitch - Mon, Mar 12
--   --   Put fridge in place Osbaldo
--   --   Fix window trim in upstairs bedroom Osbaldo??
--   --   Trim down closet doors in upstairs bedrooms Mitch
--   --   Floor pops in middle of master bedroom Osbaldo
--   --   Stain and seal hardwood treads on stairs
--   --   Paint touchups throughout thome Isaac
--   --   tighten all shower escutheons Osbaldo
--   --   Adjust closet doors and trim bottom of doors Osbaldo - In bedroom behind hall bath
--   --   Adjust patio doors Osbaldo
--   --   Move fridge closer to cabinets Osbaldo
--   --   Sliding glass door adjustment and adjust lock Osbaldo
--   --   In basement, fix white wrap in corner
--   --   Cut sewer clean out outside Osbaldo
--   --   Fix front door dents or replace door Isaac
--   --   Patch hole in brick where porch ties to house
--   --   Caulk windows outside Osbaldo
--   --   Adjust deadbolt Osbaldo
--   --   Remove sticker from attic window Osbaldo
--   --   Add pipe to downspout in front Osbaldo
--   --   Fix laundry door Osbaldo
--   --   Remove excess caulk from bath tub
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)      
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)      
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       In process as of Nov 13
-- -- Inspection (Rough In HVAC) (1)       Inspection, Tues Dec 11
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)       Harry starts Mon, Dec 4
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2)       Maybe Mon, Dec 18
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        Starting hanging Jan 2
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Needs sanding/ finish drywall at front door
-- -- Paint 1 (1)       Friday 1/19
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Del 2/2, install 2/5- nearly complete
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3)       In process by Darrell complete by Monday 2/5
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Starting Monday 2/5
-- -- Paint 2 (3)       2/15- in process
-- -- Cover Floors (1)       Wed, Feb 21
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       In process
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       Fixtures being delivered Thursday 2/22
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       Fixtures being delivered Thursday 2/22
-- -- Install Appliances (0) *       
-- -- Paint 3 (2) *        After shoemold
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)       Robbie Miller going Friday, Mar 16
-- -- Inspection (Final Building) (2) *        Fri, Mar 9
-- -- Pre Walk Through (0)       Kate, Osbaldo, Tom - Thursday
-- -- Cleaning (1)       Wed, Mar 28
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1)       Fri, Mar 23
-- -- Payment for Upgrades (0)       $2,825
-- -- Closing (1)