- 88  ::  336 Sapphire Drive
[ BUILD: 170500117 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   GOLD FRONT DOOR Needs painting as of 4/17
Mon    Dec 15      Ratified Contract? (0)      
Mon    Dec 15      $2500 Deposit Received (0)      
Mon    Dec 15      Association Packet Requested (0)      
Mon    Dec 15      Association Packet Received (0)      
Mon    Dec 15      Selections Meeting (0)      
Mon    Dec 15      Selections Sheet Signed (0)      
Mon    Dec 15      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Mon    Dec 15      Deposit For Upgrades Received (0)      
Mon    Dec 15      Inspection (Concrete Wall) (1)      
Tue    Dec 16      Inspection (Conduit Under Slab) (1)      
Wed    Dec 17      Inspection (Drain Tile) (0)      
Wed    Dec 17      Settlement Agent Confirmed (0)      
Wed    Dec 17      Verify Window & Roof Structure (0)      
Wed    Dec 17      Order Appliances (0)      
Wed    Dec 17      Patio (0)      
Wed    Dec 17      Rough In Microwave Vent (0)      
Wed    Dec 17      Inspection (Rough In Plumbing) (1)      
Thu    Dec 18      Inspection (Rough In Electric) (1)      
Fri    Dec 19      Inspection (Framing) (1) *       
Mon    Dec 22      Inspection (Deck Piers) (0)      
Mon    Dec 22      Exterior Stone (0)      
Mon    Dec 22      Set Electric Meter (0) *       
Mon    Dec 22      Inspection (Main Water Line) (0)      
Mon    Dec 22      Loan Approval (0)      
Mon    Dec 22      Deed Preparation (0)      
Mon    Dec 22      Mailbox (0)      
Mon    Dec 22      Interior Trim - Paint (1)      
Tue    Dec 23      Ceiling Fans (0)      
Tue    Dec 23      Blower Door Test (1)      
Wed    Dec 24      Inspection (Final HVAC) (1)      
Thu    Dec 25      Inspection (Final Plumbing) (1)      
Fri    Dec 26      Inspection (Final Electric) (1)      
Mon    Dec 29      Stain Hardwood Stairs (1) *       
Tue    Dec 30      Schedule Closing (0)      
Tue    Dec 30      Keys to Settlement Agent (0)      
Tue    Dec 30      Review Settlement Statement (0)      
Tue    Dec 30      Jerry Signs Closing Documents (0)      
Tue    Dec 30      Request Trash Tote From POA Manager (0)      
Tue    Dec 30      Remove Coded Lockbox (0)      
--   --   Kate -- does the buyer want to pay for us to install a shower in the basement? It will be harder for him to do later since we are drywalling everything;
--   --   Add four foot walk in shower to basement bath
--   --   And second master bathroom floor vent needs to move to opposite wall. Likely Nov 3
--   --   In second bathroom plumbing needs to be changed for a double vanity Mindy is making it happen (Nov 3?)
--   --   Add orb faucet
--   --   Finish plumbing rough in after register moved
--   --   Orb hinges? Orb hinges and knobs
--   --   Shower door
--   --   Need paint color and shelving designs
--   --   Finish drywall at front door
--   --   Remind run oil rubbed bronze hinges for all doors
--   --   Sanded drywall at front door so it can be painted
--   --   Missing light fixtures Vicente to install these - Tom will tell Vicente
--   --   Shoemold Mitch - after Glen 54
--   --   Finish electrical install- vanity lights Vicente to install these
--   --   Install ORB flush mount light at front door Arriving Tue, Mar 6
--   --   Please clear out materials in living room and kitchen so appliances can be delivered Friday 2/23 Osbaldo
--   --   Missing lights delivered. Tom to tell Vicente.
--   --   Pour front porch
--   --   CODED LOCKBOX --- 3438
--   --   Install refrigerator (from Best Buy)?
--   --   Home Inspection = Sat, Mar 10, 5:30 PM Mike Donitzen
--   --   Put range in place Really Osbaldo
--   --   The transition strips or caulk between hardwood and tile to hall bath and laundry room Eric
--   --   Drywall loose/gives directly outside master shower Fixed but looks bad- bowed drywall
--   --   Caulk in Front of the bath and shower Osbaldo
--   --   Master bedroom cracks between the ceiling and top of wall Osbaldo
--   --   Screens to be installed Osbaldo
--   --   Paint Touch up Isaac
--   --   Sweep out basement Osbaldo
--   --   Clean basement shower Osbaldo
--   --   Add three additional oil rubbed bronze lights to basement Osbaldo
--   --   Caulk nail holes at back door trim holes at deck Osbaldo
--   --   Paint front door trim
--   --   Install many missing nails in deck stair treads Osbaldo
--   --   Repair or fill hole in deck ledger board Osbaldo
--   --   Install missing nails in deck boards Osbaldo
--   --   Install kick out flashing at front of home Osbaldo is thinking about doing it - he is excited about it
--   --   Install missing exhaust fan cover Greg
--   --   Install refrigerator Osbaldo
--   --   Plug in clothes dryer and un-smush dryer vent Osbaldo
--   --   Secure pantry door hardware Osbaldo
--   --   Install lock on basement sliding door
--   --   Repair master bedroom window with broken balance cord Osbaldo
--   --   Replace dirty air filter Osbaldo
--   --   Turn on breaker for HVAC system Osbaldo
--   --   Repair roof paper and plywood sheathing at unused plumbing vent Osbaldo
--   --   Remove insulation from shower
--   --   Exterior - missing caulk to right of front door.
--   --   Paint, caulk, trim touch ups as marked throughout the main and second level Isaac
--   --   Cable receptacle in living room (marked) needs tightened.
--   --   Kitchen cabinets need cleaned.
--   --   Fence to be installed. Waiting on panel
--   --   Holes on exterior trim surrounding door between back deck and kitchen need filled.
--   --   Josh would like to add two electric outlets. One in the pantry and one in the coat closet. Tom is aware of this and working on it.**
--   --   Gap between sink and wall in main level half bath (marked) needs a cover.
--   --   Basement - the cutout in front of the main water valve needs a cover. Osbaldo
--   --   Basement - the data box/panel needs a cover. Vicente
--   --   Missing pieces of trim/molding in stairwell. Osbaldo
--   --   Knicks in trim/molding in stairwell. Isaac and Osbaldo - hooray!
--   --   Knicks in trim/molding in stairwell.
--   --   Transition between top stair and 2nd floor hallway needs addressed (uneven/bowing).
--   --   Guest tub/shower needs cleaned.
--   --   Caulk needs added between window and wall in master bathroom. Isaac
--   --   Master bedroom windows need adjusting to operate property. Osbaldo
--   --   17. Missing trim/molding between 2nd floor hall / guest bath/ guest bedroom
--   --   Missing trim/molding between 2nd floor hall / guest bath/ guest bedroom
--   --   Caulk needs added above guest bath/shower Isaac
--   --   Caulk above molding/trim in guest bedroom. Isaac
--   --   Guest bedroom closet doors were installed incorrectly
--   --   Secure crown moulding above kitchen cabinets Jeff
--   --   Correct kitchen cabinet door installation Jeff
--   --   Paint Touch Ups Mon, Mar 26
--   --   Caulk on landing at shoemold Osbaldo
--   --   Caulk in master bath at shoemold under window Osbaldo
--   --   Change 220 outlet to a plug-in Tom or Osbaldo
--   --   Closing Friday
--   --   Change door swing of half bathroom Mitch
--   --   Patch drywall at new outlet Osbaldo
--   --   Move exterior light fixture Tom
--   --   Putty hardwood nail holes Eric
--   --   Repair nail pop in corner of guest bedroom Joe
--   --   Remove door stops Osbaldo
--   --   Josh = 540-471-1321
--   --   Run cable from outside of building to inside Vince
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *        Waiting on Miss Utility
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       Almost done as of 10/30
-- -- Plumbing Rough In (4)       In process
-- -- Electric Rough In (4)       Starting Tues, Nov 14
-- -- Inspection (Rough In HVAC) (1)       Inspection Tues, Dec 12
-- -- Exterior Vinyl (0) *        Waiting on vinyl
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       Tom will check with Mitch
-- -- Drywall (Hang) (4) *        Done by Tues, Dec 19
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Hope to be done by Tues, Jan 9
-- -- Paint 1 (1)       Fri, Jan 12
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Install starts Jan 15 +/-
-- -- Granite Installation (1) *        Thursday, Feb 8
-- -- Interior Trim - Install (3) *        Beginning 1/22
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       ready for Joe to pick up
-- -- Paint 2 (3)       Now - Feb 12
-- -- Cover Floors (1)       Friday, Feb 9
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *       
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3) *        Started as of Thu, Fe 8
-- -- HVAC Trim Out (1) *        Waiting on concrete patio to set heat pump - Fri, Feb 23
-- -- Plumbing Trim Out (2) *        Started Mon, Feb 12
-- -- Install Appliances (0) *        Fri, Feb 23 delivery, installation- sweep under appliances
-- -- Paint 3 (2) *        Thu, Mar 8
-- -- Carpet (2)       Kate will check with Eric
-- -- Appraiser Confirms Construction Completion (0)       Afternoon of Thursday, March 15
-- -- Inspection (Final Building) (2) *        Re-inspect Thu, Mar 8
-- -- Pre Walk Through (0)       Kate and Osbaldo
-- -- Cleaning (1)       Starting Tue, Mar 6
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1) *        Thurs, Mar 15 @ 4:15 PM
-- -- Payment for Upgrades (0)       Total Cost/Credit: $2125
-- -- Closing (1)       April 4?