| -- | -- | reseed yard as needed | ||
| Tue | Dec 16 | Ratified Contract? (0) | ||
| Tue | Dec 16 | $2500 Deposit Received (0) | ||
| Tue | Dec 16 | Association Packet Requested (0) | ||
| Tue | Dec 16 | Association Packet Received (0) | ||
| Tue | Dec 16 | Selections Meeting (0) | ||
| Tue | Dec 16 | Selections Sheet Signed (0) | ||
| Tue | Dec 16 | Amendment for Upgrades (B,S,L,T,BCP) (0) | ||
| Tue | Dec 16 | Deposit For Upgrades Received (0) | ||
| Tue | Dec 16 | Inspection (Concrete Wall) (1) | ||
| Wed | Dec 17 | Inspection (Conduit Under Slab) (1) | ||
| Thu | Dec 18 | Inspection (Drain Tile) (0) | ||
| Thu | Dec 18 | Settlement Agent Confirmed (0) | ||
| Thu | Dec 18 | Verify Window & Roof Structure (0) | ||
| Thu | Dec 18 | Order Appliances (0) | ||
| Thu | Dec 18 | Patio (0) | ||
| Thu | Dec 18 | Rough In Microwave Vent (0) | ||
| Thu | Dec 18 | Inspection (Rough In Plumbing) (1) | ||
| Fri | Dec 19 | Inspection (Rough In Electric) (1) | ||
| Mon | Dec 22 | Inspection (Framing) (1) * | ||
| Tue | Dec 23 | Inspection (Deck Piers) (0) | ||
| Tue | Dec 23 | Exterior Stone (0) | ||
| Tue | Dec 23 | Set Electric Meter (0) * | ||
| Tue | Dec 23 | Inspection (Main Water Line) (0) | ||
| Tue | Dec 23 | Loan Approval (0) | ||
| Tue | Dec 23 | Deed Preparation (0) | ||
| Tue | Dec 23 | Mailbox (0) | ||
| Tue | Dec 23 | Order Plumbing / Lighting Fixtures (0) | ||
| Tue | Dec 23 | Interior Trim - Paint (1) | ||
| Wed | Dec 24 | Ceiling Fans (0) | ||
| Wed | Dec 24 | Blower Door Test (1) | ||
| Thu | Dec 25 | Inspection (Final HVAC) (1) | ||
| Fri | Dec 26 | Inspection (Final Plumbing) (1) | ||
| Mon | Dec 29 | Inspection (Final Electric) (1) | ||
| Tue | Dec 30 | Stain Hardwood Stairs (1) * | ||
| Wed | Dec 31 | Schedule Closing (0) | ||
| Wed | Dec 31 | Keys to Settlement Agent (0) | ||
| Wed | Dec 31 | Review Settlement Statement (0) | ||
| Wed | Dec 31 | Jerry Signs Closing Documents (0) | ||
| Wed | Dec 31 | Request Trash Tote From POA Manager (0) | ||
| Wed | Dec 31 | Remove Coded Lockbox (0) | ||
| -- | -- | Tom will inspect framing | Finished basement with full bathroom | |
| -- | -- | Install last two twin windows (Jan 3) | ||
| -- | -- | EXTEND DECK | Tom | |
| -- | -- | Set furnace | ||
| -- | -- | final paint touch up as marked | ||
| -- | -- | final cleaning | ||
| -- | -- | shoemold at base of french doors | ||
| -- | -- | adjust closet doors upstairs bedrooms | ||
| -- | -- | caulk in front of tubs and shower | ||
| -- | -- | hall bath- fasten baseboard beside door | ||
| -- | -- | add caluk to tile at laundry threshold | ||
| -- | -- | caulk all toilets | ||
| -- | -- | sand and paint rough door edges | ||
| -- | -- | paint tops of doors | ||
| -- | -- | adjust patio door | ||
| -- | -- | basement bath- secure shoemold by door | ||
| -- | -- | adjust basement patio door and latch | ||
| -- | -- | access panel for water main cut off | ||
| -- | -- | access panel low voltage box | ||
| -- | -- | adjust door latch basement closet under stairs | ||
| -- | -- | install window screens | ||
| -- | -- | caulk bottom of all doors and jams on first floor | ||
| -- | -- | dust all lights | ||
| -- | -- | coat closet does not latch | ||
| -- | -- | repair any damaged flooring after cardboard is removed | ||
| -- | -- | install all shelves in kitchen cabinets | ||
| -- | -- | fix hold in ceiling pantry | ||
| -- | -- | clean tape off of light fixture in pantry | ||
| -- | -- | put stop on pocket door so it will not open too far | ||
| -- | -- | paint access panel to door in master closet | ||
| -- | -- | fix ceiling in master bedroom at fan | ||
| -- | -- | put strip at bathroom door in basement | ||
| -- | -- | cut off bottom door going into furnace room | ||
| -- | -- | put 2 screws in return air cover in furnace room | ||
| -- | -- | put shoe molding down in closet under steps | ||
| -- | -- | Put stop on master bathroom door | ||
| -- | -- | Building Permit (30) * | ||
| -- | -- | Order Roof & Floor Trusses (1) | ||
| -- | -- | Order Windows & Doors (0) | ||
| -- | -- | Stake Out Home (1) | ||
| -- | -- | Excavate (2) | ||
| -- | -- | Inspection (Footers) (1) | ||
| -- | -- | Pour Footers (1) * | ||
| -- | -- | Set Forms (2) | ||
| -- | -- | Pour Foundation Walls (1) | ||
| -- | -- | Plumb Slab (2) | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) | ||
| -- | -- | Prepare Slab (1) | ||
| -- | -- | Inspection (Slab) (1) | ||
| -- | -- | Pour Slab (1) * | ||
| -- | -- | Framing I (9) | Framing to begin this week 10/16 | |
| -- | -- | Order Steps (0) | ||
| -- | -- | Order Tubs / Showers (0) | ||
| -- | -- | Framing II (8) | ||
| -- | -- | Framing III (8) * | ||
| -- | -- | Install Stairs (0) * | ||
| -- | -- | Windows & Doors (0) * | ||
| -- | -- | House Number and Status in Window (0) | ||
| -- | -- | Roofing (0) * | ||
| -- | -- | Order Cabinets (0) | ||
| -- | -- | Deck (0) | ||
| -- | -- | Gutters (0) | ||
| -- | -- | Driveway (0) * | ||
| -- | -- | Privacy Divider / Fence (0) * | ||
| -- | -- | Sod / Seed / Landscaping (0) | Sod needed | |
| -- | -- | HVAC Rough In (4) | ||
| -- | -- | Plumbing Rough In (4) | Mon, Jan 29 | |
| -- | -- | Electric Rough In (4) | Finishing Mon, Feb 12 | |
| -- | -- | Inspection (Rough In HVAC) (1) | Tues, Feb 13 ? | |
| -- | -- | Exterior Vinyl (0) * | ||
| -- | -- | Insulation (2) * | Wed, Feb 14 ? | |
| -- | -- | Inspection (Insulation) (1) | Thurs, Feb 15 | |
| -- | -- | Inspection (Electric Service) (0) | ||
| -- | -- | Inspection (Main Sewer Line) (0) | ||
| -- | -- | Order Interior Doors & Trim (0) | ||
| -- | -- | Drywall (Hang) (4) * | Stock Tuesday, Feb 20 | |
| -- | -- | Drywall (Tape, Block, Skim, Sand) (6) * | Will be finished Friday 3/9 | |
| -- | -- | Paint 1 (1) | Monday 3/12 | |
| -- | -- | Garage Door (0) | ||
| -- | -- | House Numbers (0) | Fire extinguisher? | |
| -- | -- | Cabinet Installation (2) * | Del Mar 23, Installed Mar 26 | |
| -- | -- | Granite Installation (1) * | Thursday 4/19 | |
| -- | -- | Interior Trim - Install (3) * | Nearly complete | |
| -- | -- | Luxury Vinyl Plank (3) * | ||
| -- | -- | Luxury Vinyl Tile (0) | Almost done as of Mar 19 | |
| -- | -- | Paint 2 (3) | Tuesday 4/3 | |
| -- | -- | Cover Floors (1) | Monday 4/9 | |
| -- | -- | Deliver Plumbing / Lighting Fixtures (0) | ||
| -- | -- | Shoe Moulding (0) | ||
| -- | -- | Shelving, Door Knobs, Fire Extinguisher (0) * | Maybe done? | |
| -- | -- | Install Coded Lockbox (add extra keys) (0) | ||
| -- | -- | Pay Water / Sewer Taps (0) | Melissa to take the check to pay. Tom to tell Melissa 4/23 | |
| -- | -- | Set Water Meter (0) * | ||
| -- | -- | Electric Trim Out (3) * | Ready for Harry | |
| -- | -- | HVAC Trim Out (1) * | ||
| -- | -- | Plumbing Trim Out (2) * | Tues, 4/17 | |
| -- | -- | Install Appliances (0) * | Present, but not set, Apr 19 Need water | |
| -- | -- | Paint 3 (2) * | Now, Apr 19 | |
| -- | -- | Carpet (2) | 4/16 installing now | |
| -- | -- | Appraiser Confirms Construction Completion (0) | Lender ordering Friday, Apr 27 | |
| -- | -- | Inspection (Final Building) (2) * | As soon as we have water | |
| -- | -- | Pre Walk Through (0) | ||
| -- | -- | Cleaning (1) | ||
| -- | -- | Certificate of Occupancy (1) * | ||
| -- | -- | C.O. to Lender (0) | ||
| -- | -- | Buyer Walk Through (1) * | ||
| -- | -- | Payment for Upgrades (0) | $3374 | |
| -- | -- | Closing (1) | Friday, May 4 | |