-- |
-- |
GREEN FRONT DOOR |
|
|
-- |
-- |
Paint |
|
|
Thu |
Nov 28 |
Ratified Contract? (0) |
|
|
Thu |
Nov 28 |
$2500 Deposit Received (0) |
|
|
Thu |
Nov 28 |
Association Packet Requested (0) |
|
|
Thu |
Nov 28 |
Association Packet Received (0) |
|
|
Thu |
Nov 28 |
Selections Meeting (0) |
|
|
Thu |
Nov 28 |
Selections Sheet Signed (0) |
|
|
Thu |
Nov 28 |
Amendment for Upgrades (B,S,L,T,BCP) (0) |
|
|
Thu |
Nov 28 |
Deposit For Upgrades Received (0) |
|
|
Thu |
Nov 28 |
Inspection (Concrete Wall) (1) |
|
|
Fri |
Nov 29 |
Inspection (Conduit Under Slab) (1) |
|
|
Mon |
Dec 2 |
Inspection (Drain Tile) (0) |
|
|
Mon |
Dec 2 |
Settlement Agent Confirmed (0) |
|
|
Mon |
Dec 2 |
Verify Window & Roof Structure (0) |
|
|
Mon |
Dec 2 |
Order Appliances (0) |
|
|
Mon |
Dec 2 |
Patio (0) |
|
|
Mon |
Dec 2 |
Rough In Microwave Vent (0) |
|
|
Mon |
Dec 2 |
Inspection (Rough In Plumbing) (1) |
|
|
Tue |
Dec 3 |
Inspection (Rough In Electric) (1) |
|
|
Wed |
Dec 4 |
Inspection (Deck Piers) (0) |
|
|
Wed |
Dec 4 |
Inspection (Framing) (1) |
|
|
Thu |
Dec 5 |
Exterior Stone (0) |
|
|
Thu |
Dec 5 |
Set Electric Meter (0) |
|
|
Thu |
Dec 5 |
Inspection (Main Water Line) (0) |
|
|
Thu |
Dec 5 |
Loan Approval (0) |
|
|
Thu |
Dec 5 |
Deed Preparation (0) |
|
|
Thu |
Dec 5 |
Mailbox (0) |
|
|
Thu |
Dec 5 |
Order Plumbing / Lighting Fixtures (0) |
|
|
Thu |
Dec 5 |
Interior Trim - Paint (1) |
|
|
Fri |
Dec 6 |
Ceiling Fans (0) |
|
|
Fri |
Dec 6 |
Blower Door Test (1) |
|
|
Mon |
Dec 9 |
Inspection (Final HVAC) (1) |
|
|
Tue |
Dec 10 |
Inspection (Final Plumbing) (1) |
|
|
Wed |
Dec 11 |
Inspection (Final Electric) (1) |
|
|
Thu |
Dec 12 |
Stain Hardwood Stairs (1) |
|
|
Fri |
Dec 13 |
Schedule Closing (0) |
|
|
Fri |
Dec 13 |
Keys to Settlement Agent (0) |
|
|
Fri |
Dec 13 |
Review Settlement Statement (0) |
|
|
Fri |
Dec 13 |
Jerry Signs Closing Documents (0) |
|
|
Fri |
Dec 13 |
Request Trash Tote From POA Manager (0) |
|
|
Fri |
Dec 13 |
Remove Coded Lockbox (0) |
|
|
|
-- |
-- |
Finished family room and half bathroom |
Tom will inspect all framing |
|
-- |
-- |
Electrical meters (82-85) |
Mounted - need to dig ditch |
|
-- |
-- |
Showmold |
Mitch - Tues, Mar 13 |
|
-- |
-- |
Need laundry room hardwood |
Eric |
|
-- |
-- |
Half bathroom hardwood |
Eric - Tues, Mar 20 |
|
-- |
-- |
CODED LOCKBOX --- 7790 |
|
|
-- |
-- |
Trim powder bath |
Mitch |
|
-- |
-- |
Re-tile over shower future floor drain |
Joe |
|
-- |
-- |
Connect water heater |
Harry |
|
-- |
-- |
Finish trim/shoe on bottom of basement bath vanity |
CK |
|
-- |
-- |
Install screens |
Osbaldo |
|
-- |
-- |
Missing lightbulb basement bath |
Osbaldo |
|
-- |
-- |
Final paint |
Isaac |
|
-- |
-- |
Caulk around the bottom of the door outside |
|
|
-- |
-- |
Patio door rubbing at bottom |
|
|
-- |
-- |
Lots of kitchen problems |
|
|
-- |
-- |
Shoe mold at the top of the steps |
|
|
-- |
-- |
Clear out unfinished room in basement |
|
|
-- |
-- |
Basement bathroom vanity unfinished shoe mold |
|
|
-- |
-- |
The cover of low-voltage box |
Osbaldo |
|
-- |
-- |
Slow close doors on basement vanity close way too slow |
|
|
-- |
-- |
Re-cut tile upstairs hall bath back door trim |
Joe |
|
-- |
-- |
Cut off bottom of master closet doors |
|
|
-- |
-- |
Fix trim on handrail going upstairs add trim in between two bedroom at floor |
|
|
-- |
-- |
Fix trim on handrail going upstairs add trim in between two bedroom at floor |
|
|
-- |
-- |
And touchups throughout the nail pops |
Isaac |
|
-- |
-- |
Closet latch upstairs bedroom |
Osbaldo |
|
-- |
-- |
Fix drywall is sketches in hall and master bath shower head |
Escutcheons - Osbaldo, Isaac |
|
-- |
-- |
Nick in hardwood floor |
Osbaldo |
|
-- |
-- |
Move refrigerator toward cabinets |
|
|
-- |
-- |
Adjust fan in basement bath |
Osbaldo |
|
-- |
-- |
Just cable and electrical outlet open room in basement |
Osbaldo |
|
-- |
-- |
add vinyl to furnace room I basement |
Eric |
|
-- |
-- |
Trim door to furnace room |
Trim down door - Osbaldo |
|
-- |
-- |
3 missing window screens |
On order |
|
-- |
-- |
Fix dip in road |
Adam |
|
-- |
-- |
Add missing fasteners to deck boards |
|
|
-- |
-- |
Adjust deck board with inadequite bearing on the joist |
|
|
-- |
-- |
Repair drain port on the clothes washer flow pan (too large) |
Dry River |
|
-- |
-- |
Confirm light switches are for fans |
|
|
-- |
-- |
Install clean air filter |
|
|
-- |
-- |
Repair leaking spots in plumbing drain line |
Dry River |
|
-- |
-- |
Install batte of insulation where missing (master bathroom?) |
Greg |
|
-- |
-- |
Sod |
|
|
-- |
-- |
Paving |
Tomorrow 4/24 |
|
-- |
-- |
1 missing screen |
Tom to check if it came in |
|
-- |
-- |
Buyer doing final walk through |
Wednesday, April 25 @ 8PM |
|
-- |
-- |
Sand and paint powder room where powder room vanity meets wall |
|
|
-- |
-- |
Repair chip on laundry room door |
|
|
-- |
-- |
Remove paint on master bedroom door |
|
|
-- |
-- |
Grout in basement bathroom is two different colors |
|
|
-- |
-- |
Flooring missing in utility room |
|
|
-- |
-- |
Sewer clean out behind water heater needs plumber tape |
|
|
-- |
-- |
Cable jack in basement is crooked |
|
|
-- |
-- |
Basement flooded with sewer water |
|
|
-- |
-- |
Remove a foot of drywall |
|
|
-- |
-- |
Remove insulation |
|
|
-- |
-- |
Wet floor near condensate drain |
|
|
-- |
-- |
Re-install drywall |
|
|
-- |
-- |
Carpet |
Week of Jun 18 |
|
-- |
-- |
Trim |
|
|
-- |
-- |
Building Permit (30) |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) |
|
|
-- |
-- |
Order Windows & Doors (0) |
|
|
-- |
-- |
Stake Out Home (1) |
|
|
-- |
-- |
Excavate (2) |
|
|
-- |
-- |
Inspection (Footers) (1) |
|
|
-- |
-- |
Pour Footers (1) |
|
|
-- |
-- |
Set Forms (2) |
|
|
-- |
-- |
Pour Foundation Walls (1) |
|
|
-- |
-- |
Plumb Slab (2) |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
-- |
-- |
Prepare Slab (1) |
|
|
-- |
-- |
Inspection (Slab) (1) |
|
|
-- |
-- |
Pour Slab (1) * |
|
|
-- |
-- |
Framing I (9) |
Framing to begin this week 10/16 |
|
-- |
-- |
Order Steps (0) |
|
|
-- |
-- |
Order Tubs / Showers (0) |
|
|
-- |
-- |
Framing II (8) |
|
|
-- |
-- |
Framing III (8) * |
|
|
-- |
-- |
Install Stairs (0) |
|
|
-- |
-- |
Windows & Doors (0) |
|
|
-- |
-- |
House Number and Status in Window (0) |
|
|
-- |
-- |
Roofing (0) |
|
|
-- |
-- |
Order Cabinets (0) |
|
|
-- |
-- |
Deck (0) |
|
|
-- |
-- |
Gutters (0) |
|
|
-- |
-- |
Driveway (0) |
Pouring Tue, Mar 27 |
|
-- |
-- |
Privacy Divider / Fence (0) |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) |
Friday, April 12 |
|
-- |
-- |
HVAC Rough In (4) |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) |
Thu, Jan 4 |
|
-- |
-- |
Plumbing Rough In (4) |
Done by Tues, Jan 2 |
|
-- |
-- |
Electric Rough In (4) |
Harry -- complete by Wed, Jan 3 |
|
-- |
-- |
Exterior Vinyl (0) * |
2/22 - Brick nearly complete |
|
-- |
-- |
Insulation (2) |
Fri, Jan 5 |
|
-- |
-- |
Inspection (Insulation) (1) |
|
|
-- |
-- |
Inspection (Electric Service) (0) |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) |
|
|
-- |
-- |
Order Interior Doors & Trim (0) |
|
|
-- |
-- |
Drywall (Hang) (4) * |
Stocked as of Jan 15 |
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
Just needs to be sanded and sheet rock by the front door |
|
-- |
-- |
Paint 1 (1) |
ready mid week |
|
-- |
-- |
Garage Door (0) |
|
|
-- |
-- |
House Numbers (0) |
|
|
-- |
-- |
Cabinet Installation (2) * |
Del Feb 12, Install Feb 13 |
|
-- |
-- |
Granite Installation (1) * |
|
|
-- |
-- |
Interior Trim - Install (3) |
Started Feb 22 |
|
-- |
-- |
Luxury Vinyl Plank (3) * |
|
|
-- |
-- |
Luxury Vinyl Tile (0) |
2/12- grouting today |
|
-- |
-- |
Paint 2 (3) |
Fri, Mar 16 |
|
-- |
-- |
Cover Floors (1) |
Monday 3/12 |
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) |
|
|
-- |
-- |
Shoe Moulding (0) |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) |
|
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) |
Mindy to request check from Nicolette |
|
-- |
-- |
Set Water Meter (0) |
|
|
-- |
-- |
Electric Trim Out (3) |
Almost complete- finishing today 3/26 |
|
-- |
-- |
HVAC Trim Out (1) |
|
|
-- |
-- |
Plumbing Trim Out (2) |
Almost complete as of Mon, Mar 26 |
|
-- |
-- |
Install Appliances (0) * |
Mon, Apr 2 |
|
-- |
-- |
Paint 3 (2) * |
|
|
-- |
-- |
Carpet (2) |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) |
Monday, April 16 |
|
-- |
-- |
Inspection (Final Building) (2) * |
Tuesday 4/3 |
|
-- |
-- |
Pre Walk Through (0) |
Wed, April 4 |
|
-- |
-- |
Cleaning (1) |
Tuesday 4/3 |
|
-- |
-- |
Certificate of Occupancy (1) * |
|
|
-- |
-- |
C.O. to Lender (0) |
|
|
-- |
-- |
Buyer Walk Through (1) |
Friday 4/6 at 4:00 |
|
-- |
-- |
Payment for Upgrades (0) |
|
|
-- |
-- |
Closing (1) |
Friday, April 27 @ 2PM |
|