ADDR
- 121  ::  384 Tanzanite Drive
[ BUILD: 17080119 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Inspection (Concrete Wall) (1)      
Wed    Dec 17      Inspection (Conduit Under Slab) (1)      
Thu    Dec 18      Inspection (Drain Tile) (0)      
Thu    Dec 18      Settlement Agent Confirmed (0)      
Thu    Dec 18      Verify Window & Roof Structure (0)      
Thu    Dec 18      Order Appliances (0)      
Thu    Dec 18      Patio (0)      
Thu    Dec 18      Rough In Microwave Vent (0)      
Thu    Dec 18      Inspection (Rough In Plumbing) (1)      
Fri    Dec 19      Inspection (Rough In Electric) (1)      
Mon    Dec 22      Inspection (Framing) (1) *       
Tue    Dec 23      Inspection (Deck Piers) (0)      
Tue    Dec 23      Exterior Stone (0)      
Tue    Dec 23      Set Electric Meter (0) *       
Tue    Dec 23      Inspection (Main Water Line) (0)      
Tue    Dec 23      Loan Approval (0)      
Tue    Dec 23      Deed Preparation (0)      
Tue    Dec 23      Mailbox (0)      
Tue    Dec 23      Interior Trim - Paint (1)      
Wed    Dec 24      Ceiling Fans (0)      
Wed    Dec 24      Blower Door Test (1)      
Thu    Dec 25      Inspection (Final HVAC) (1)      
Fri    Dec 26      Inspection (Final Plumbing) (1)      
Mon    Dec 29      Inspection (Final Electric) (1)      
Tue    Dec 30      Stain Hardwood Stairs (1) *       
Wed    Dec 31      Request Trash Tote From POA Manager (0)      
--   --   GOLD FRONT DOOR
--   --   Charlston brick, bone vinyl
--   --   WIDEN DRIVEWAY
--   --   Green door
--   --   Green door
--   --   Repaint door green
--   --   CODED LOCKBOX --- 1274
--   --   Harry -- last three lights
--   --   Repair chipped granite at stove Thursday, Aug 16
--   --   Fixing back step in patio
--   --   Lights over mirrors Waiting on mirrors
--   --   Would like to close on Aug 24
--   --   Fence Need price for six foot privacy fence instead
--   --   Buyer would like to know if she can store things inside starting Fri, Aug 17 In the basement
--   --   Water intrusion in basement bonus room Tom will look at this
--   --   Last coat of poly on steps Mon, Aug 20
--   --   Paint Touch Up Throughout
--   --   Receptacle needed outside of powder bathroom
--   --   Secure Low Voltage Box
--   --   Light Bulb for garage opener Osbaldo
--   --   Caulk condensate line Osbaldo - around freon line
--   --   Flashing between patio and siding Osbaldo - needs metal from Tom
--   --   Crown Moulding at top of steps needs adjustment
--   --   replace sash LR window
--   --   Oak Shoemold at back patio door
--   --   Oak Shoemold at back patio door
--   --   Install Screens
--   --   Patch chipped concrete Osbaldo
--   --   Need Paint Touch Up Pens CK
--   --   Replace floor register living room
--   --   Replace front door handle installed incorrectly Wed, Aug 29
--   --   Final cleaning of floors
--   --   replace toilet tank in up bathroom
--   --   touch up drywall corners on tray ceiling
--   --   adjust attic access panel
--   --   master bath tub repair
--   --   squeak in up bedroom floors
--   --   Need latch hardware laundry door
--   --   Mason- replace brick- right of garage door Tom told the mason
--   --   Need screen on patio door
--   --   Install fence
--   --   Install flashing at patio
--   --   Backyard fine tuning
--   --   Caulking and painting
--   --   ceiling to be painted after drywall fix Kate communicated to Maher on 7/22
--   --   correct dryer vent needed so leak does not reoccur?- TOM- Ronnie? leak into kitchen; Tom and GREG to meet with Cynthia to discuss.
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)       October 23 and 24
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       In process as of Apr 30
-- -- Plumbing Rough In (4)       In process as of Monday, May 7
-- -- Electric Rough In (4)       Harry - just started as of Monday, May 7
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)       Thursday, May 17
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        Starting May 22
-- -- Drywall (Tape, Block, Skim, Sand) (6) *       
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Installed June 26
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3) *        Finishing as of June 25
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       This week June 18
-- -- Paint 2 (3)       In process as of July 2
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        In process 7/23
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)       Mon, Aug 13
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3) *        Harry
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *        Mast & Brunk
-- -- Install Appliances (0) *        Scheduled for August 1
-- -- Paint 3 (2) *        Tom will talk to Isaac
-- -- Carpet (2)       8/6
-- -- Appraiser Confirms Construction Completion (0)       Jeff Eye going Aug 17 or soon thereafter
-- -- Inspection (Final Building) (2) *        Tues, Aug 14
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Tues, Aug 21
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1) *        Tues, Aug 21 @ 5PM
-- -- Payment for Upgrades (0)       $2,286
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       Prefers to close Aug 24
-- -- Remove Coded Lockbox (0)