Fri    Sep 20      Inspection (Footers) (1)      
Mon    Sep 23      Inspection (Concrete Wall) (1)      
Tue    Sep 24      Inspection (Plumbing Under Slab) (1)      
Wed    Sep 25      Inspection (Conduit Under Slab) (1)      
Thu    Sep 26      Inspection (Slab) (1)      
Fri    Sep 27      Inspection (Drain Tile) (0)      
Fri    Sep 27      Inspection (Rough In HVAC) (1)      
Mon    Sep 30      Inspection (Rough In Plumbing) (1)      
Tue    Oct 1      Inspection (Rough In Electric) (1)      
Wed    Oct 2      Inspection (Deck Piers) (0)      
Wed    Oct 2      Inspection (Framing) (1)      
Thu    Oct 3      Inspection (Insulation) (1)      
Fri    Oct 4      Inspection (Electric Service) (0)      
Fri    Oct 4      Inspection (Main Sewer Line) (0)      
Fri    Oct 4      Inspection (Main Water Line) (0)      
Fri    Oct 4      Inspection (Final HVAC) (1)      
Mon    Oct 7      Inspection (Final Plumbing) (1)      
Tue    Oct 8      Inspection (Final Electric) (1)      
Wed    Oct 9      Inspection (Final Building) (2)