ADDR
- 124  ::  390 Tanzanite Drive
[ BUILD: 17080122 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Touch up paint on front door at white scratch/spot Isaac/not done 12/14
--   --   Curb of driveway at one side is very high Tom will Adam that Jerry said Adam should fix it.
Tue    Apr 29      Ratified Contract? (0)      
Tue    Apr 29      $2500 Deposit Received (0)      
Tue    Apr 29      Association Packet Requested (0)      
Tue    Apr 29      Association Packet Received (0)      
Tue    Apr 29      Selections Meeting (0)      
Tue    Apr 29      Selections Sheet Signed (0)      
Tue    Apr 29      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Apr 29      Deposit For Upgrades Received (0)      
Tue    Apr 29      Inspection (Concrete Wall) (1)      
Wed    Apr 30      Inspection (Conduit Under Slab) (1)      
Thu    May 1      Inspection (Drain Tile) (0)      
Thu    May 1      Settlement Agent Confirmed (0)      
Thu    May 1      Verify Window & Roof Structure (0)      
Thu    May 1      Order Appliances (0)      
Thu    May 1      Patio (0)      
Thu    May 1      Rough In Microwave Vent (0)      
Thu    May 1      Inspection (Rough In Plumbing) (1)      
Fri    May 2      Inspection (Rough In Electric) (1)      
Mon    May 5      Inspection (Deck Piers) (0)      
Mon    May 5      Inspection (Framing) (1) *       
Tue    May 6      Exterior Stone (0)      
Tue    May 6      Set Electric Meter (0) *       
Tue    May 6      Inspection (Main Water Line) (0)      
Tue    May 6      Loan Approval (0)      
Tue    May 6      Deed Preparation (0)      
Tue    May 6      Mailbox (0)      
Tue    May 6      Interior Trim - Paint (1)      
Wed    May 7      Ceiling Fans (0)      
Wed    May 7      Blower Door Test (1)      
Thu    May 8      Inspection (Final HVAC) (1)      
Fri    May 9      Inspection (Final Plumbing) (1)      
Mon    May 12      Inspection (Final Electric) (1)      
Tue    May 13      Stain Hardwood Stairs (1)      
Wed    May 14      Schedule Closing (0)      
Wed    May 14      Keys to Settlement Agent (0)      
Wed    May 14      Review Settlement Statement (0)      
Wed    May 14      Jerry Signs Closing Documents (0)      
Wed    May 14      Request Trash Tote From POA Manager (0)      
Wed    May 14      Remove Coded Lockbox (0)      
--   --   Pour garage slab
--   --   GOLD FRONT DOOR
--   --   Extended patio is not possible? Please let Basil know
--   --   Bone vinyl
--   --   Possible want a fence Tom marking out borders
--   --   12 x 18 deck instead of patio, with stairs June 4
--   --   Fix pantry framing
--   --   Remove gable
--   --   Expanded deck or expanded patio??
--   --   WIDEN DRIVEWAY
--   --   Instruct buyer to drop off ceiling fans when its time for electrical punch out Kate will take care of this.
--   --   Need peep hole and door knobs Complete by Wed, June 13
--   --   Siding on dormers Greg
--   --   Wrap garage doors Greg
--   --   CODED LOCKBOX --- 8600
--   --   Steps for deck
--   --   Repair drain leak Thursday, Jul 5
--   --   Carpet in room in basement Jul 12
--   --   Final paint and staining steps
--   --   Install appliances In garage
--   --   Christian Graves to extend pendant lighting over island Christian
--   --   Finishing electrical Christian
--   --   Patch drywall hole in master closet Osbaldo
--   --   Closet doors to be trimmed and adjusted and both upstairs bedrooms Isaac
--   --   Small patch in upstairs hall bathroom Osbaldo
--   --   Caulk in front of tubs and showers Osbaldo
--   --   Patch hole next to electrical outlet in upstairs right guest bedroom Osbaldo
--   --   Patch drywall hole on landing at stairs Osbaldo
--   --   Install handrails on stairwells Isaac
--   --   Caps for screw holes French doors Osbaldo
--   --   PVC board at French doors exterior Osbaldo
--   --   Install screens on the windows and doors Osbaldo
--   --   Patch concrete in the basement bonus room Osbaldo
--   --   Patch hole at dishwasher Osbaldo
--   --   Install deadbolt at back the French door Davenport
--   --   I just bathroom door lock on master bathroom Osbaldo
--   --   Address access panel in master closet Osbaldo
--   --   Check all door hardware to make sure doors close properly Osbaldo
--   --   Wash out garage Osbaldo
--   --   Need covers for low-voltage box and electrical panel in garage Christian
--   --  
--   --   Cable missing in bonus room Christian at Graves needs to go back
--   --   Remove cardboards
--   --   Install appliances Tuesday 6/17
--   --   Right rear corner of the house downspouts should be extended to have water drain at least 6 feet from the house
--   --   Replace board along outside edge of the deck that is warped and curves upwards
--   --   Secure a cover on open junction box near the ceiling in utility closet Osbaldo 7/23
--   --   Covers requested for fluorescent lights and first floor closet both second floor closet in the basement utility room
--   --   Add caulking around the escutcheon plate and tub spout and second floor and basement bathrooms
--   --   Showerhead in both the second floor in master bathroom have a leak where the showerhead attaches to the shower arm the head should be removed and a layer of plumbers tape applied to the threats of the shower arm
--   --   First floor bathroom does not latch and stay closed the striker plate on the door frame needs to be adjusted
--   --   Add a doorstop to basement bathroom door
--   --   Yellow door
--   --   Davenport- Please make sure to always check and readjust the striker plates so that doors closed securely Tom to relay this to Davenport
--   --   Clean under kitchen sink
--   --   Raise pendant lights up 6 inches Osbaldo 7/23l
--   --   Touch up paint throughout paint stair risers Tom to talk to Isaac today 7/23
--   --   Railing Tom. Tom to give a price...should handle outside of closing.
--   --   Install cover over cable outet in living room Tom to get cover from Graves
--   --   Adjust closet door in smallest bedroom that is hard to close Osbaldo
--   --   Patch drywall holes at ceiling by outlet Osbaldo - in garage
--   --   Secure loose hardwood at top of stairs from main entrance Osbaldo
--   --   Remove stain on carpet in bonus room Eric called buyer...buyer will contact Eric when he has the room cleaned out
--   --   Refrigerator drawer keeps falling out Cabinet drawer
--   --   Fill holes in back yard Pettit
--   --   Cable outlet instead of full cover plate bonus room
--   --   Cable missing in outside box Christian at Graves needs to go back
--   --   Weatherstripping at threshold between garage and hall Osbaldo
--   --   Master bathroom door cannot be locked
--   --   Draft coming in at one of the dining room windows
--   --   Upstairs floors (mostly in small bedrooms) creak close to walls
--   --   Master Bathroom door cannot be locked
--   --   Osbaldo to go at 10:00 on Monday 1/28
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)       October 23 and 24
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *        Finishing up
-- -- Install Stairs (0)       Wed, Apr 4
-- -- Windows & Doors (0) *        Half as of 4/9
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *        Stocking Wed, Apr 11
-- -- Order Cabinets (0)       Tues, May 1
-- -- Deck (0)      
-- -- Gutters (0)       Wed, June 27
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)       Seed and straw Mon Jul 16
-- -- HVAC Rough In (4)       Wed, Apr 11
-- -- Inspection (Rough In HVAC) (1)       Friday, April 27
-- -- Plumbing Rough In (4)       Monday 4/23 in process- complete today
-- -- Electric Rough In (4)       Monday 4/23
-- -- Exterior Vinyl (0) *        After 119
-- -- Insulation (2) *        Monday, April 30
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Last skim coat - Fri, May 11
-- -- Paint 1 (1)      
-- -- Garage Door (0) *        Wed, Jun 13
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Delivered June 1, Installed June 4
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3) *        Isaac Galindez trim guy
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Started as of May 21
-- -- Paint 2 (3)      
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)       In process of doing so as of June 25
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        Add peephole to front door
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)       Jerry will let Nicolette know
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3)       In process of doing so as of June 25
-- -- HVAC Trim Out (1)       Needs to be hooked up as of June 25
-- -- Plumbing Trim Out (2)       Just waiting on half bathroom
-- -- Install Appliances (0) *        Scheduled for Thursday, June 28
-- -- Paint 3 (2) *       
-- -- Carpet (2)       Scheduled for Monday, July 2
-- -- Appraiser Confirms Construction Completion (0)       Johnny Hensley - July 20 or 23
-- -- Inspection (Final Building) (2) *        Mon, Jul 16
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Sunday, July 15 - Monday, July 16
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)       And to Welby
-- -- Buyer Walk Through (1)      
-- -- Payment for Upgrades (0)       $2200?
-- -- Closing (1)