- 124  ::  390 Tanzanite Drive
[ BUILD: 17080122 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Touch up paint on front door at white scratch/spot Isaac/not done 12/14
--   --   Curb of driveway at one side is very high Tom will Adam that Jerry said Adam should fix it.
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Order Appliances (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Ceiling Fans (0)      
Fri    Dec 6      Blower Door Test (1)      
Mon    Dec 9      Inspection (Final HVAC) (1)      
Tue    Dec 10      Inspection (Final Plumbing) (1)      
Wed    Dec 11      Inspection (Final Electric) (1)      
Thu    Dec 12      Stain Hardwood Stairs (1)      
Fri    Dec 13      Schedule Closing (0)      
Fri    Dec 13      Keys to Settlement Agent (0)      
Fri    Dec 13      Review Settlement Statement (0)      
Fri    Dec 13      Jerry Signs Closing Documents (0)      
Fri    Dec 13      Request Trash Tote From POA Manager (0)      
Fri    Dec 13      Remove Coded Lockbox (0)      
--   --   Pour garage slab
--   --   GOLD FRONT DOOR
--   --   Extended patio is not possible? Please let Basil know
--   --   Bone vinyl
--   --   Possible want a fence Tom marking out borders
--   --   12 x 18 deck instead of patio, with stairs June 4
--   --   Fix pantry framing
--   --   Remove gable
--   --   Expanded deck or expanded patio??
--   --   WIDEN DRIVEWAY
--   --   Instruct buyer to drop off ceiling fans when its time for electrical punch out Kate will take care of this.
--   --   Need peep hole and door knobs Complete by Wed, June 13
--   --   Siding on dormers Greg
--   --   Wrap garage doors Greg
--   --   CODED LOCKBOX --- 8600
--   --   Steps for deck
--   --   Repair drain leak Thursday, Jul 5
--   --   Carpet in room in basement Jul 12
--   --   Final paint and staining steps
--   --   Install appliances In garage
--   --   Christian Graves to extend pendant lighting over island Christian
--   --   Finishing electrical Christian
--   --   Patch drywall hole in master closet Osbaldo
--   --   Closet doors to be trimmed and adjusted and both upstairs bedrooms Isaac
--   --   Small patch in upstairs hall bathroom Osbaldo
--   --   Caulk in front of tubs and showers Osbaldo
--   --   Patch hole next to electrical outlet in upstairs right guest bedroom Osbaldo
--   --   Patch drywall hole on landing at stairs Osbaldo
--   --   Install handrails on stairwells Isaac
--   --   Caps for screw holes French doors Osbaldo
--   --   PVC board at French doors exterior Osbaldo
--   --   Install screens on the windows and doors Osbaldo
--   --   Patch concrete in the basement bonus room Osbaldo
--   --   Patch hole at dishwasher Osbaldo
--   --   Install deadbolt at back the French door Davenport
--   --   I just bathroom door lock on master bathroom Osbaldo
--   --   Address access panel in master closet Osbaldo
--   --   Check all door hardware to make sure doors close properly Osbaldo
--   --   Wash out garage Osbaldo
--   --   Need covers for low-voltage box and electrical panel in garage Christian
--   --  
--   --   Cable missing in bonus room Christian at Graves needs to go back
--   --   Remove cardboards
--   --   Install appliances Tuesday 6/17
--   --   Right rear corner of the house downspouts should be extended to have water drain at least 6 feet from the house
--   --   Replace board along outside edge of the deck that is warped and curves upwards
--   --   Secure a cover on open junction box near the ceiling in utility closet Osbaldo 7/23
--   --   Covers requested for fluorescent lights and first floor closet both second floor closet in the basement utility room
--   --   Add caulking around the escutcheon plate and tub spout and second floor and basement bathrooms
--   --   Showerhead in both the second floor in master bathroom have a leak where the showerhead attaches to the shower arm the head should be removed and a layer of plumbers tape applied to the threats of the shower arm
--   --   First floor bathroom does not latch and stay closed the striker plate on the door frame needs to be adjusted
--   --   Add a doorstop to basement bathroom door
--   --   Yellow door
--   --   Davenport- Please make sure to always check and readjust the striker plates so that doors closed securely Tom to relay this to Davenport
--   --   Clean under kitchen sink
--   --   Raise pendant lights up 6 inches Osbaldo 7/23l
--   --   Touch up paint throughout paint stair risers Tom to talk to Isaac today 7/23
--   --   Railing Tom. Tom to give a price...should handle outside of closing.
--   --   Install cover over cable outet in living room Tom to get cover from Graves
--   --   Adjust closet door in smallest bedroom that is hard to close Osbaldo
--   --   Patch drywall holes at ceiling by outlet Osbaldo - in garage
--   --   Secure loose hardwood at top of stairs from main entrance Osbaldo
--   --   Remove stain on carpet in bonus room Eric called buyer...buyer will contact Eric when he has the room cleaned out
--   --   Refrigerator drawer keeps falling out Cabinet drawer
--   --   Fill holes in back yard Pettit
--   --   Cable outlet instead of full cover plate bonus room
--   --   Cable missing in outside box Christian at Graves needs to go back
--   --   Weatherstripping at threshold between garage and hall Osbaldo
--   --   Master bathroom door cannot be locked
--   --   Draft coming in at one of the dining room windows
--   --   Upstairs floors (mostly in small bedrooms) creak close to walls
--   --   Master Bathroom door cannot be locked
--   --   Osbaldo to go at 10:00 on Monday 1/28
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)       October 23 and 24
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *        Finishing up
-- -- Install Stairs (0)       Wed, Apr 4
-- -- Windows & Doors (0)       Half as of 4/9
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)       Stocking Wed, Apr 11
-- -- Order Cabinets (0)       Tues, May 1
-- -- Deck (0)      
-- -- Gutters (0)       Wed, June 27
-- -- Driveway (0)      
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)       Seed and straw Mon Jul 16
-- -- HVAC Rough In (4)       Wed, Apr 11
-- -- Inspection (Rough In HVAC) (1)       Friday, April 27
-- -- Plumbing Rough In (4)       Monday 4/23 in process- complete today
-- -- Electric Rough In (4)       Monday 4/23
-- -- Exterior Vinyl (0) *        After 119
-- -- Insulation (2)       Monday, April 30
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Last skim coat - Fri, May 11
-- -- Paint 1 (1)      
-- -- Garage Door (0)       Wed, Jun 13
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Delivered June 1, Installed June 4
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3)       Isaac Galindez trim guy
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Started as of May 21
-- -- Paint 2 (3)      
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)       In process of doing so as of June 25
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       Add peephole to front door
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)       Jerry will let Nicolette know
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       In process of doing so as of June 25
-- -- HVAC Trim Out (1)       Needs to be hooked up as of June 25
-- -- Plumbing Trim Out (2)       Just waiting on half bathroom
-- -- Install Appliances (0) *        Scheduled for Thursday, June 28
-- -- Paint 3 (2) *       
-- -- Carpet (2)       Scheduled for Monday, July 2
-- -- Appraiser Confirms Construction Completion (0)       Johnny Hensley - July 20 or 23
-- -- Inspection (Final Building) (2) *        Mon, Jul 16
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Sunday, July 15 - Monday, July 16
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)       And to Welby
-- -- Buyer Walk Through (1)      
-- -- Payment for Upgrades (0)       $2200?
-- -- Closing (1)