-- |
-- |
Stephen Payne |
|
|
-- |
-- |
Cracked master bathroom floor tile |
Joe, Tile Time, is scheduling with Stephen and Tom a good time to come out |
|
-- |
-- |
Upstairs flooring and subflooring creaks throughout upper floor |
Will be fixed at same time as Tile |
|
-- |
-- |
Cracked tile in basement bathroom |
Joe, Tile Time, is scheduling with Stephen and Tom a good time to come out |
|
Thu |
Nov 28 |
Ratified Contract? (0) |
|
|
Thu |
Nov 28 |
$2500 Deposit Received (0) |
|
|
Thu |
Nov 28 |
Association Packet Requested (0) |
|
|
Thu |
Nov 28 |
Association Packet Received (0) |
|
|
Thu |
Nov 28 |
Selections Meeting (0) |
|
|
Thu |
Nov 28 |
Selections Sheet Signed (0) |
|
|
Thu |
Nov 28 |
Amendment for Upgrades (B,S,L,T,BCP) (0) |
|
|
Thu |
Nov 28 |
Deposit For Upgrades Received (0) |
|
|
Thu |
Nov 28 |
Inspection (Concrete Wall) (1) |
|
|
Fri |
Nov 29 |
Inspection (Conduit Under Slab) (1) |
|
|
Mon |
Dec 2 |
Inspection (Drain Tile) (0) |
|
|
Mon |
Dec 2 |
Settlement Agent Confirmed (0) |
|
|
Mon |
Dec 2 |
Verify Window & Roof Structure (0) |
|
|
Mon |
Dec 2 |
Patio (0) |
|
|
Mon |
Dec 2 |
Rough In Microwave Vent (0) |
|
|
Mon |
Dec 2 |
Inspection (Rough In Plumbing) (1) |
|
|
Tue |
Dec 3 |
Inspection (Rough In Electric) (1) |
|
|
Wed |
Dec 4 |
Inspection (Deck Piers) (0) |
|
|
Wed |
Dec 4 |
Inspection (Framing) (1) |
|
|
Thu |
Dec 5 |
Exterior Stone (0) |
|
|
Thu |
Dec 5 |
Set Electric Meter (0) |
|
|
Thu |
Dec 5 |
Inspection (Main Water Line) (0) |
|
|
Thu |
Dec 5 |
Loan Approval (0) |
|
|
Thu |
Dec 5 |
Deed Preparation (0) |
|
|
Thu |
Dec 5 |
Mailbox (0) |
|
|
Thu |
Dec 5 |
Interior Trim - Paint (1) |
|
|
Fri |
Dec 6 |
Ceiling Fans (0) |
|
|
Fri |
Dec 6 |
Blower Door Test (1) |
|
|
Mon |
Dec 9 |
Inspection (Final HVAC) (1) |
|
|
Tue |
Dec 10 |
Inspection (Final Plumbing) (1) |
|
|
Wed |
Dec 11 |
Inspection (Final Electric) (1) |
|
|
Thu |
Dec 12 |
Stain Hardwood Stairs (1) |
|
|
Fri |
Dec 13 |
Request Trash Tote From POA Manager (0) |
|
|
|
-- |
-- |
COUNTRY BEIGE VINYL- GREEN FRONT DOOR |
|
|
-- |
-- |
Added window in basement |
Framed and window was delivered to be installed this week 7/23 |
|
-- |
-- |
Crown mounding main level |
|
|
-- |
-- |
Once cabients and gtanite are in schedule customer walk through |
|
|
-- |
-- |
Buyer providing mirrors |
|
|
-- |
-- |
Buyer Walk Through - Nov 9 @ 12:30 PM |
|
|
-- |
-- |
Buyer to drop off mirrors- lights to be installed above mirrors |
|
|
-- |
-- |
Mirrors- master bathroom- dimensions are 28x 40- options for sconce lights? |
|
|
-- |
-- |
Yard amendment |
|
|
-- |
-- |
Loud noise in ductwork |
|
|
-- |
-- |
Need to close by Dec 15! |
|
|
-- |
-- |
Potential “hump” in master floor (see pic) |
|
|
-- |
-- |
Potential “hump” in master floor (see pic) |
|
|
-- |
-- |
CODED LOCKBOX 1225 |
|
|
-- |
-- |
Fill nail holes In Centcenter board in kitchen |
Buddy |
|
-- |
-- |
Squeaky floor and up hallway by wall between full bath and laundry room |
|
|
-- |
-- |
Floor pops in second bedroom all along wall between rooms |
Osbaldo |
|
-- |
-- |
Flip-flops in other upstairs that ran by wall Between rooms |
Osbaldo |
|
-- |
-- |
Add electrical outlet to pantry |
|
|
-- |
-- |
Upstairs guest bedroom trim issues (see pics) |
|
|
-- |
-- |
Benjamin Meredith, Inspection, Fri, Dec 14, 9AM; |
|
|
-- |
-- |
Paint touch up |
|
|
-- |
-- |
Fix two large drywall holes behind hall and master bath mirrors |
|
|
-- |
-- |
Replace window grids in basement |
|
|
-- |
-- |
Stain nail holes in kitchen hardwood |
|
|
-- |
-- |
No stain pen - need new one for coco cabinet |
|
|
-- |
-- |
Replace nosing at top of stairs |
|
|
-- |
-- |
hose faucet is loose at the wall in the 1st floor bathroom ( below the sink. left side) |
|
|
-- |
-- |
Observed a cracked gable end truss in the attic, as well as a loose nail plate adjacent; recommend having a licensed contractor repair. (See Figure #10) |
|
|
-- |
-- |
Recommend installing gutter downspout extensions where they are missing to improve the water control at the perimeter of the foundation. (See Figure #1) (See Figure #2) |
|
|
-- |
-- |
Observed the rear hose faucet is loose at the wall; recommend having the faucet fastened as intended. (See Figure #5) |
|
|
-- |
-- |
Noted master bedroom Arc fault breaker does not trip when tested, and there is a wire extending into the breaker panel that is missing its wire clamp; recommend repair by a licensed electrician. (See Figure #3) (See Figure #4) |
|
|
-- |
-- |
Observed cracked floor tiles in the master bathroom; recommend repair as necessary. (See Figure #6) |
|
|
-- |
-- |
Second floor bedroom door knob is loose; recommend repair. (See Figure #8) |
|
|
-- |
-- |
Second floor rear bedroom window lock does not function as intended; recommend repair. (See Figure #9) |
|
|
-- |
-- |
The basement bathroom shower head water flow is minimal; recommend further evaluation and repair as necessary. (See Figure #7) |
|
|
-- |
-- |
We noticed that the water flow/pressure throughout the house is very weak - it was noted in the punch list). ------------- |
|
|
-- |
-- |
Raise powder bath mirror several inches |
|
|
-- |
-- |
Drywall holes in upstairs bathroom outlets below mirrors |
|
|
-- |
-- |
Raise powder bath mirror two inches |
|
|
-- |
-- |
Missing screens |
|
|
-- |
-- |
Issue with coax cable inside the home |
|
|
-- |
-- |
Water leak at light above refrigerator |
Will need drywall, paint |
|
-- |
-- |
Crack in tile in master and basement bathroom |
Joe |
|
-- |
-- |
Low flow at basement shower |
|
|
-- |
-- |
Cracking tile floors |
Tile is in as of June 17 |
|
-- |
-- |
Low water pressure in the basement shower |
Bobby in contact with Stephen |
|
-- |
-- |
Truss meeting - 2PM on Jan 2 |
|
|
-- |
-- |
Creaky floors |
|
|
-- |
-- |
Building Permit (30) |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) |
|
|
-- |
-- |
Order Windows & Doors (0) |
|
|
-- |
-- |
Stake Out Home (1) |
|
|
-- |
-- |
Excavate (2) |
|
|
-- |
-- |
Inspection (Footers) (1) |
Tue, Mar 27 |
|
-- |
-- |
Pour Footers (1) |
Tue, Mar 27 |
|
-- |
-- |
Set Forms (2) |
Mon, Apr 2 |
|
-- |
-- |
Pour Foundation Walls (1) |
Wed, Apr 4 |
|
-- |
-- |
Plumb Slab (2) |
finish 76-81 Mon (4/16) pending weather - insp (4/17) |
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
-- |
-- |
Prepare Slab (1) |
|
|
-- |
-- |
Inspection (Slab) (1) |
|
|
-- |
-- |
Pour Slab (1) * |
Wed 4/25 start- approximately 2 day |
|
-- |
-- |
Framing I (9) |
Two to three weeks as of May 7, 2018 |
|
-- |
-- |
Order Steps (0) |
|
|
-- |
-- |
Order Tubs / Showers (0) |
|
|
-- |
-- |
Framing II (8) |
|
|
-- |
-- |
Framing III (8) * |
Trusses Tuesday June 12 ALL SET |
|
-- |
-- |
Install Stairs (0) |
Monday, July 9 |
|
-- |
-- |
Windows & Doors (0) |
Missing three windows |
|
-- |
-- |
House Number and Status in Window (0) |
|
|
-- |
-- |
Roofing (0) |
Waiting on plywood |
|
-- |
-- |
Order Cabinets (0) |
|
|
-- |
-- |
Order Appliances (0) |
|
|
-- |
-- |
Deck (0) |
|
|
-- |
-- |
Gutters (0) |
|
|
-- |
-- |
Driveway (0) |
|
|
-- |
-- |
Privacy Divider / Fence (0) |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) |
|
|
-- |
-- |
HVAC Rough In (4) |
Starting July 30 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) |
|
|
-- |
-- |
Plumbing Rough In (4) |
Bobby - hopefully starting Tues, Sept 4 |
|
-- |
-- |
Electric Rough In (4) |
|
|
-- |
-- |
Exterior Vinyl (0) * |
|
|
-- |
-- |
Insulation (2) |
|
|
-- |
-- |
Inspection (Insulation) (1) |
Tuesday, Sep 11 |
|
-- |
-- |
Inspection (Electric Service) (0) |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) |
Just waiting on water lines |
|
-- |
-- |
Order Interior Doors & Trim (0) |
|
|
-- |
-- |
Drywall (Hang) (4) * |
Starting Sep 14 |
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
Needs sanding as of Oct 1 |
|
-- |
-- |
Paint 1 (1) |
Week of Oct 8 |
|
-- |
-- |
Garage Door (0) |
|
|
-- |
-- |
House Numbers (0) |
|
|
-- |
-- |
Cabinet Installation (2) * |
Delivered 10/1, installed 10/2 |
|
-- |
-- |
Granite Installation (1) * |
|
|
-- |
-- |
Interior Trim - Install (3) |
Started as of Oct 11 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * |
|
|
-- |
-- |
Luxury Vinyl Tile (0) |
|
|
-- |
-- |
Paint 2 (3) |
|
|
-- |
-- |
Cover Floors (1) |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) |
|
|
-- |
-- |
Shoe Moulding (0) |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) |
Shelving, No mirrors needed |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) |
|
|
-- |
-- |
Set Water Meter (0) |
|
|
-- |
-- |
Electric Trim Out (3) |
Missing eight snap lights |
|
-- |
-- |
HVAC Trim Out (1) |
|
|
-- |
-- |
Plumbing Trim Out (2) |
|
|
-- |
-- |
Install Appliances (0) * |
Thu Dec 6 |
|
-- |
-- |
Paint 3 (2) * |
|
|
-- |
-- |
Carpet (2) |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) |
Tell Scott Brown |
|
-- |
-- |
Inspection (Final Building) (2) * |
Tuesday afternoon (Dec 11) |
|
-- |
-- |
Pre Walk Through (0) |
|
|
-- |
-- |
Cleaning (1) |
|
|
-- |
-- |
Certificate of Occupancy (1) * |
|
|
-- |
-- |
C.O. to Lender (0) |
|
|
-- |
-- |
Schedule Closing (0) |
|
|
-- |
-- |
Buyer Walk Through (1) |
Dec 13 at 12:20 PM |
|
-- |
-- |
Payment for Upgrades (0) |
$725 |
|
-- |
-- |
Keys to Settlement Agent (0) |
|
|
-- |
-- |
Review Settlement Statement (0) |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) |
|
|
-- |
-- |
Closing (1) |
Dec 14 at 11AM |
|
-- |
-- |
Remove Coded Lockbox (0) |
|
|