| Tue | Dec 16 | Ratified Contract? (0) | ||
| Tue | Dec 16 | $2500 Deposit Received (0) | ||
| Tue | Dec 16 | Association Packet Requested (0) | ||
| Tue | Dec 16 | Association Packet Received (0) | ||
| Tue | Dec 16 | Selections Meeting (0) | ||
| Tue | Dec 16 | Selections Sheet Signed (0) | ||
| Tue | Dec 16 | Amendment for Upgrades (B,S,L,T,BCP) (0) | ||
| Tue | Dec 16 | Deposit For Upgrades Received (0) | ||
| Tue | Dec 16 | Inspection (Concrete Wall) (1) | ||
| Wed | Dec 17 | Inspection (Conduit Under Slab) (1) | ||
| Thu | Dec 18 | Inspection (Drain Tile) (0) | ||
| Thu | Dec 18 | Settlement Agent Confirmed (0) | ||
| Thu | Dec 18 | Verify Window & Roof Structure (0) | ||
| Thu | Dec 18 | Order Appliances (0) | ||
| Thu | Dec 18 | Patio (0) | ||
| Thu | Dec 18 | Rough In Microwave Vent (0) | ||
| Thu | Dec 18 | Inspection (Rough In Plumbing) (1) | ||
| Fri | Dec 19 | Inspection (Rough In Electric) (1) | ||
| Mon | Dec 22 | Inspection (Framing) (1) * | ||
| Tue | Dec 23 | Inspection (Deck Piers) (0) | ||
| Tue | Dec 23 | Exterior Stone (0) | ||
| Tue | Dec 23 | Set Electric Meter (0) * | ||
| Tue | Dec 23 | Inspection (Main Water Line) (0) | ||
| Tue | Dec 23 | Loan Approval (0) | ||
| Tue | Dec 23 | Deed Preparation (0) | ||
| Tue | Dec 23 | Mailbox (0) | ||
| Tue | Dec 23 | Order Plumbing / Lighting Fixtures (0) | ||
| Tue | Dec 23 | Interior Trim - Paint (1) | ||
| Wed | Dec 24 | Ceiling Fans (0) | ||
| Wed | Dec 24 | Blower Door Test (1) | ||
| Thu | Dec 25 | Inspection (Final HVAC) (1) | ||
| Fri | Dec 26 | Inspection (Final Plumbing) (1) | ||
| Mon | Dec 29 | Inspection (Final Electric) (1) | ||
| Tue | Dec 30 | Stain Hardwood Stairs (1) * | ||
| Wed | Dec 31 | Schedule Closing (0) | ||
| Wed | Dec 31 | Keys to Settlement Agent (0) | ||
| Wed | Dec 31 | Review Settlement Statement (0) | ||
| Wed | Dec 31 | Jerry Signs Closing Documents (0) | ||
| Wed | Dec 31 | Request Trash Tote From POA Manager (0) | ||
| Wed | Dec 31 | Remove Coded Lockbox (0) | ||
| -- | -- | CHARLESTON BRICK, PEARL VINYL, GOLD FRONT DOOR | ||
| -- | -- | Buyer Walk Through - Fri, Jul 13 @ 9 AM | ||
| -- | -- | PAINT Ghost ship 4007 Dash three a Valspar four main house color | ||
| -- | -- | Paint- Ghost ship 4007-3A Valspar main house color | ||
| -- | -- | Paint- Linwood Sands HGSW2506 Sherwin Williams for all the bathrooms | ||
| -- | -- | Paint- Powder Bath- Ghost Ship | ||
| -- | -- | Last few light fixtures | ||
| -- | -- | Set water meter and connect | ||
| -- | -- | Stoop footer on Monday | Nov 5 | |
| -- | -- | Block and brick for stoop on Tuesday, Nov 6 | ||
| -- | -- | Refrigerator | Monday, Nov 12 | |
| -- | -- | Few more shelves and locks | ||
| -- | -- | Remove mortar from front door | Painter | |
| -- | -- | Front porch - pour and railing | Need railing | |
| -- | -- | Gold Front Door | ||
| -- | -- | Final segment of sidewalk | Partners | |
| -- | -- | Street sign | Not yet as of Nov 29 | |
| -- | -- | Railing for porch | Monday | |
| -- | -- | CODED LOCKBOX 1331 | ||
| -- | -- | Peep hole and linen closet shelves | Monday | |
| -- | -- | Front landscaping after porches | Week of Nov 26 | |
| -- | -- | Front door handle installed upside down | ||
| -- | -- | Final paint touch up | ||
| -- | -- | Final cleaning | ||
| -- | -- | Range drawer needs to be fixed | Mats appliances 11/24 | |
| -- | -- | Need screen in upstairs small bedroom window | ||
| -- | -- | Small Nick in trim on the window in small up bedroom | Buddy | |
| -- | -- | Need three window screens and upstairs bedrooms | Ordered | |
| -- | -- | Paint access panel to attic. | ||
| -- | -- | Remove stickers up master window | Buddy | |
| -- | -- | Touch ups up hall bath | Buddy | |
| -- | -- | |||
| -- | -- | Need door to back bonus room | ||
| -- | -- | Swap out scratched mirrors- both up baths and basement bath | Dec 4 | |
| -- | -- | Two small holes in up bath above mirror to be filled | Hall bath | |
| -- | -- | Replace mirror in basement bathroom | ||
| -- | -- | |||
| -- | -- | Scratches in up hall bath | Dec 4 | |
| -- | -- | Door under stairs does not latch | Buddy | |
| -- | -- | Powder room bath needs toilet paper holder | ||
| -- | -- | Mats appliances is coming to fix the range handle and dishwasher and 11/24 | Nov 29 | |
| -- | -- | Need mailbox keys | Buddy | |
| -- | -- | Master bathroom towel rack is unlevel | ||
| -- | -- | Bedroom with a double door closet couldn’t open vent severely damaged | ||
| -- | -- | Areas where wood floor is damaged | ||
| -- | -- | Master bedroom, rise in score between bathroom and ceiling fan area near double windows. | ||
| -- | -- | Funds Escrowed For Fence = $5850 | (with West View Title) | |
| -- | -- | Remove coded lockbox | ||
| -- | -- | Building Permit (30) * | ||
| -- | -- | Order Roof & Floor Trusses (1) | ||
| -- | -- | Order Windows & Doors (0) | ||
| -- | -- | Stake Out Home (1) | ||
| -- | -- | Excavate (2) | ||
| -- | -- | Inspection (Footers) (1) | ||
| -- | -- | Pour Footers (1) * | ||
| -- | -- | Set Forms (2) | ||
| -- | -- | Pour Foundation Walls (1) | ||
| -- | -- | Plumb Slab (2) | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) | ||
| -- | -- | Prepare Slab (1) | ||
| -- | -- | Inspection (Slab) (1) | ||
| -- | -- | Pour Slab (1) * | ||
| -- | -- | Framing I (9) | ||
| -- | -- | Order Steps (0) | ||
| -- | -- | Order Tubs / Showers (0) | ||
| -- | -- | Framing II (8) | ||
| -- | -- | Framing III (8) * | ||
| -- | -- | Install Stairs (0) * | ||
| -- | -- | Windows & Doors (0) * | ||
| -- | -- | House Number and Status in Window (0) | ||
| -- | -- | Roofing (0) * | Starting June 18 81,80,79 and black papered today before rain. | |
| -- | -- | Order Cabinets (0) | ||
| Upgraded cabinetry | ||||
| -- | -- | Deck (0) | In process as of Sep 20 | |
| Expanded 12 x 18 pressure treated deck | ||||
| -- | -- | Gutters (0) | Ordered as of Sep 20 | |
| -- | -- | Driveway (0) * | ||
| -- | -- | Privacy Divider / Fence (0) * | Almost complete as of Dec 13 | |
| -- | -- | Sod / Seed / Landscaping (0) | Thursday, Nov 8 | |
| -- | -- | HVAC Rough In (4) | ||
| -- | -- | Plumbing Rough In (4) | ||
| Full finished basement with a bathroom with vanity | ||||
| -- | -- | Electric Rough In (4) | ||
| -- | -- | Inspection (Rough In HVAC) (1) | ||
| -- | -- | Exterior Vinyl (0) * | ||
| -- | -- | Insulation (2) * | ||
| -- | -- | Inspection (Insulation) (1) | ||
| -- | -- | Inspection (Electric Service) (0) | ||
| -- | -- | Inspection (Main Sewer Line) (0) | ||
| -- | -- | Order Interior Doors & Trim (0) | ||
| -- | -- | Drywall (Hang) (4) * | Finishing August 6 | |
| -- | -- | Drywall (Tape, Block, Skim, Sand) (6) * | Sanding Aug 13 | |
| -- | -- | Paint 1 (1) | ||
| -- | -- | Garage Door (0) | ||
| -- | -- | House Numbers (0) | Need keys for mailboxes | |
| -- | -- | Cabinet Installation (2) * | Delivered 9/7, Install 9/10 | |
| Four undercabinet lights in kitchen | ||||
| -- | -- | Granite Installation (1) * | Mon, Oct 8 | |
| -- | -- | Interior Trim - Install (3) * | ||
| -- | -- | Luxury Vinyl Plank (3) * | ||
| -- | -- | Luxury Vinyl Tile (0) | ||
| -- | -- | Paint 2 (3) | ||
| -- | -- | Cover Floors (1) | Monday, Oct 29 | |
| -- | -- | Deliver Plumbing / Lighting Fixtures (0) | ||
| -- | -- | Shoe Moulding (0) | ||
| -- | -- | Shelving, Door Knobs, Fire Extinguisher (0) * | Still waiting as of Oct 8, needs peephole | |
| -- | -- | Install Coded Lockbox (add extra keys) (0) | ||
| -- | -- | Pay Water / Sewer Taps (0) | ||
| -- | -- | Set Water Meter (0) * | Need more dirt at water crock | |
| -- | -- | Electric Trim Out (3) * | Waiting on a few fixtures | |
| Ceiling fans for two bedrooms to be provided by Meyer and installed by seller | ||||
| -- | -- | HVAC Trim Out (1) * | Oct 18 / 19 | |
| -- | -- | Plumbing Trim Out (2) * | ||
| -- | -- | Install Appliances (0) * | Waiting on installation date from Jeff | |
| Stainless steel appliances | ||||
| -- | -- | Paint 3 (2) * | ||
| -- | -- | Carpet (2) | Oct 29 | |
| Upgraded pad and all carpeted areas | ||||
| -- | -- | Appraiser Confirms Construction Completion (0) | ||
| -- | -- | Inspection (Final Building) (2) * | Hopefully Tuesday, Nov 13 | |
| -- | -- | Pre Walk Through (0) | Tuesday, Nov 12 or Wednesday, Nov 13 | |
| -- | -- | Cleaning (1) | Monday, Nov 12 | |
| -- | -- | Certificate of Occupancy (1) * | ||
| -- | -- | C.O. to Lender (0) | ||
| -- | -- | Buyer Walk Through (1) * | ||
| -- | -- | Payment for Upgrades (0) | ||
| -- | -- | Closing (1) | Thursday, Nov 29 at 2PM | |