[ BUILD: 1806-0108 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Touch up paint at front door Not done 6/19 Kate
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Order Appliances (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Ceiling Fans (0)      
Fri    Dec 6      Blower Door Test (1)      
Mon    Dec 9      Inspection (Final HVAC) (1)      
Tue    Dec 10      Inspection (Final Plumbing) (1)      
Wed    Dec 11      Inspection (Final Electric) (1)      
Thu    Dec 12      Stain Hardwood Stairs (1)      
Fri    Dec 13      Request Trash Tote From POA Manager (0)      
--   --   Charleston Brick
--   --   Ivory Vinyl Started 2/6
--   --   Yellow front door
--   --  
--   --   Red front door Done but needs touch up
--   --   Cover all tubs/shower Needed in basement and hall shower
--   --   Tub liner needed in basement
--   --   Electrical inspection reschedule (see pic of note)
--   --   Could the yard have been higher? Could the steps have been wider?
--   --   Must be out of apartment by April 30
--   --   Dryer vent cover needed on front?
--   --   Brick repair? (Pic) Dennis
--   --   Pave driveway
--   --   Drain off back downspout
--   --   Dark molding needed by master bathroom vanity Osbaldo/all dark vanities surrounded by white molding
--   --   New Bathroom Countertops Not in 4/27
--   --   Pretty visible seam in basement carpet
--   --   Coffee stain in kitchen drawer
--   --   Carpets need covered
--   --   Stove and dishwasher are black not SS in dining room
--   --   Basement bathroom door opens directly into toilet Fixing 4/27
--   --   Stair railing Osbaldo
--   --   Attic access panel Osbaldo
--   --   Coded Lockbox 5656
--   --   Drywall patch basement bathroom door
--   --   Clean out garage
--   --   Install new tops 5/10
--   --   Missing cabinet front
--   --   Hall lights upside down
--   --   Reinstall bathroom counter tops 5/15
--   --   Install Sink faucets Afternoon 5/9
--   --   Closing 5/10
--   --   Stain steps Not done 5/11
--   --   Paint hand railing 5/6
--   --   Paint attic access 5/6
--   --   Pressure wash back
--   --   Missing light cover basement bath
--   --   Replace shoe molding at cabinets to correct color Osbaldo
--   --   Metal flashing on side of house Osbado
--   --   Leaking faucet in up hall bath Osbaldo
--   --   Fire extinguisher
--   --   Switch shoe in kitchen Matches cabinetry 5/8
--   --   Finish baseboard in basement bathroom
--   --   Replace window in living room
--   --   Install master shower rod
--   --   Install the buyers showerhead in the hall bathroom On counter
--   --   Final paint touch up including garage Mostly done 5/11
--   --   Attic access panel to be painted
--   --   Install master shower stopper
--   --   Caulk all toilets
--   --   Caulk in front of door to garage
--   --   Caulk front windows at brick Osbaldo
--   --   Replace the living room window
--   --   Install window screens Osbaldo
--   --   Brickmason to fix brick the door threshold Not done 6/19
--   --   AdJust the front door hinge
--   --   Install shower rod in the basement
--   --   Install towel ring in powder
--   --   Get paint touch up kits from Classic kitchen and bath for spots in kitchen
--   --   Front door paint touch up Isaac
--   --   Laundry room box? Caulking? (Courtney)
--   --  
--   --  
--   --  
--   --  
--   --  
--   --  
--   --  
--   --  
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)      
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)       Patio done 3/20
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       In process
-- -- Inspection (Rough In HVAC) (1)       Thursday, Feb 7
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)       Just started Jan 28
-- -- Exterior Vinyl (0) *        90% complete 3/23
-- -- Insulation (2)      
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        Starting Feb 12; Almost finished as of Feb 18
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Should be ready for paint after 3/7
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Mostly installed as of Mar 25
-- -- Granite Installation (1) *        April 22
-- -- Interior Trim - Install (3)       Started 3/13-in process 3/20 (Daryl)
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Will be done today 4/10
-- -- Paint 2 (3)       In process as of Apr 4
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)      
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       Almost done as of April 29
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       Still needs quite a bit 5/1
-- -- Install Appliances (0) *        Week of Apr 18
-- -- Paint 3 (2) *        5/6
-- -- Carpet (2)       ASAP
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Thu, May 9
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1)       Thurs, 5/9 10:45
-- -- Payment for Upgrades (0)       $875
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       Tuesday, May 15?
-- -- Remove Coded Lockbox (0)