- 57  ::  2242 Deyerle Avenue
[ BUILD: 1806-0109 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   CODED LOCKBOX 5757
Tue    Dec 16      Ratified Contract? (0)      
Tue    Dec 16      $2500 Deposit Received (0)      
Tue    Dec 16      Association Packet Requested (0)      
Tue    Dec 16      Association Packet Received (0)      
Tue    Dec 16      Selections Meeting (0)      
Tue    Dec 16      Selections Sheet Signed (0)      
Tue    Dec 16      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Dec 16      Deposit For Upgrades Received (0)      
Tue    Dec 16      Inspection (Concrete Wall) (1)      
Wed    Dec 17      Inspection (Conduit Under Slab) (1)      
Thu    Dec 18      Inspection (Drain Tile) (0)      
Thu    Dec 18      Settlement Agent Confirmed (0)      
Thu    Dec 18      Verify Window & Roof Structure (0)      
Thu    Dec 18      Order Appliances (0)      
Thu    Dec 18      Patio (0)      
Thu    Dec 18      Rough In Microwave Vent (0)      
Thu    Dec 18      Inspection (Rough In Plumbing) (1)      
Fri    Dec 19      Inspection (Rough In Electric) (1)      
Mon    Dec 22      Inspection (Framing) (1) *       
Tue    Dec 23      Inspection (Deck Piers) (0)      
Tue    Dec 23      Exterior Stone (0)      
Tue    Dec 23      Set Electric Meter (0) *       
Tue    Dec 23      Inspection (Main Water Line) (0)      
Tue    Dec 23      Loan Approval (0)      
Tue    Dec 23      Deed Preparation (0)      
Tue    Dec 23      Mailbox (0)      
Tue    Dec 23      Interior Trim - Paint (1)      
Wed    Dec 24      Ceiling Fans (0)      
Wed    Dec 24      Blower Door Test (1)      
Thu    Dec 25      Inspection (Final HVAC) (1)      
Fri    Dec 26      Inspection (Final Plumbing) (1)      
Mon    Dec 29      Inspection (Final Electric) (1)      
Tue    Dec 30      Stain Hardwood Stairs (1) *       
Wed    Dec 31      Schedule Closing (0)      
Wed    Dec 31      Payment for Upgrades (0)       $360
Wed    Dec 31      Keys to Settlement Agent (0)      
Wed    Dec 31      Review Settlement Statement (0)      
Wed    Dec 31      Jerry Signs Closing Documents (0)      
Wed    Dec 31      Request Trash Tote From POA Manager (0)      
Wed    Dec 31      Remove Coded Lockbox (0)      
--   --   Country Beige Vinyl Started 2/6/ section missing?
--   --   Green front door
--   --   Yellow Front DOor
--   --   How large can the patio be?
--   --   No slider-standard back door (see pic)
--   --   Tub liner needed in basement
--   --   Showe liner needed in MB
--   --   KATE TO GIVE UPDATE THURSDAY AFTER OPS
--   --   Scheduled closing for May 15 Buyer now requesting closing 5/9
--   --   When should light be delivered? It’s on site 4/14
--   --   Tell Paul the name of foundation company
--   --   Molding at bottom of front door (pic)
--   --   Foundation repair
--   --   Pave driveway
--   --   Peep hole
--   --   Discoloration back of kitchen island? Kyle needs to install it
--   --   Fridge needs finished installing/need stove
--   --   Drywall patching in basement
--   --   Stove? Osbaldo
--   --   Staining steps Friday afternoon
--   --   Light fixtures upside down (hall)
--   --   final walk thru 5/3 1pm
--   --   Closing 5/9
--   --   Pressure wash back
--   --   Front window broken. String hanging out wont stay open.
--   --   Fix glass shower door
--   --   Clean off patio wash cement, and privacy fencing
--   --   Swap out living room window
--   --   Clean off siding in front
--   --   Replace chandelier with Oil Rubbed Bronze Waiting on fixture
-- -- Building Permit (30) *       
    Stainless Steel Appliances  
    8 lb carpet padding (all carpeted areas)  
    Sliding Glass Shower Door  
    GE electric range upgrade  
    Expanded Patio 12x18  
    CREDIT- Buyer to provide thier own pendant light over island- single hole centered  
    Paint- change ALL to STONINGTON  
    Added electrical outlet in garage  
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
    Finished Room Behind Garage with Full Bathroom  
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       Almost done as of Jan 21
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
    Add additional cable drop in basement room- one on each long wall.  
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *        Buyer to take pics after insulation
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        Finishing to begin 3/11
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process 3/27; Still working as of April 1
-- -- Paint 1 (1)       Monday, April 1
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Tuesday, April 2
    Upgraded Bathroom Cabinetry  
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3) *        Finishing Apr 4
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *        Thursday, April 4, TJ- 90% done 4/10
-- -- Luxury Vinyl Tile (0)       Will be done 4/10
    Upgraded 12 x 24 tile in master bathroom  
-- -- Paint 2 (3)       Starting Apr 11
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)       Tom will ask for them
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        Peep Hole/ in process 4/14
    Peep Hole in Front Door  
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3) *        Mostly done as of April 29
    2 added ceiling fans in upstairs bedrooms  
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *        Mostly done as of April 29
    Upgraded Shower Head in Master Bathroom  
-- -- Install Appliances (0) *        install 4/18
-- -- Paint 3 (2) *        Isaac
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        AM 5/1
-- -- Pre Walk Through (0)       Tuesday 4/30
-- -- Cleaning (1)       5/2-5/3
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1) *        Friday 5/3
-- -- Closing (1)       Thursday, May 9
    Credit Per Contract Amendment