ADDR
- 58  ::  2244 Deyerle Avenue
[ BUILD: 1806-0110 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   add seed adn straw to yard Tom is aware as of 7/29
Tue    Apr 29      Ratified Contract? (0)      
Tue    Apr 29      $2500 Deposit Received (0)      
Tue    Apr 29      Association Packet Requested (0)      
Tue    Apr 29      Association Packet Received (0)      
Tue    Apr 29      Selections Meeting (0)      
Tue    Apr 29      Selections Sheet Signed (0)      
Tue    Apr 29      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Apr 29      Deposit For Upgrades Received (0)      
Tue    Apr 29      Inspection (Concrete Wall) (1)      
Wed    Apr 30      Inspection (Conduit Under Slab) (1)      
Thu    May 1      Inspection (Drain Tile) (0)      
Thu    May 1      Settlement Agent Confirmed (0)      
Thu    May 1      Verify Window & Roof Structure (0)      
Thu    May 1      Order Appliances (0)      
Thu    May 1      Patio (0)      
Thu    May 1      Rough In Microwave Vent (0)      
Thu    May 1      Inspection (Rough In Plumbing) (1)      
Fri    May 2      Inspection (Rough In Electric) (1)      
Mon    May 5      Inspection (Deck Piers) (0)      
Mon    May 5      Inspection (Framing) (1) *       
Tue    May 6      Exterior Stone (0)      
Tue    May 6      Set Electric Meter (0) *       
Tue    May 6      Inspection (Main Water Line) (0)      
Tue    May 6      Loan Approval (0)      
Tue    May 6      Deed Preparation (0)      
Tue    May 6      Mailbox (0)      
Tue    May 6      Interior Trim - Paint (1)      
Wed    May 7      Ceiling Fans (0)      
Wed    May 7      Blower Door Test (1)      
Thu    May 8      Inspection (Final HVAC) (1)      
Fri    May 9      Inspection (Final Plumbing) (1)      
Mon    May 12      Inspection (Final Electric) (1)      
Tue    May 13      Stain Hardwood Stairs (1)      
Wed    May 14      Request Trash Tote From POA Manager (0)      
--   --   Savannah Brick
--   --   Bone Vinyl Started 2/6
--   --   Red front door
--   --   Green Front Door
--   --   Parking space?
--   --   Pretty significant bump in floor in master bedroom/bathroom (see pic) Tom and Osbaldo will address
--   --   Need liners in every shower/bathtub Need one in basement
--   --   Upstairs window missing
--   --   Replace window in front (marked w large blue X)
--   --   Patch slabs near garages (all units) Osbaldo
--   --   Awaiting replacement cabinet parts
--   --   Cultured Marble Install Just need one piece of side splash/on site just needs installed
--   --   Lots of cabinets in garage? For other units?
--   --   Fill space above window on side of townhouse PVC board, Greg
--   --   Crack on ceiling near kitchen
--   --   Coded Lockbox 6208
--   --   Pave
--   --   Pave driveway Partially paved 4/17
--   --   Still needs electric trim out (none in basement) Working on it 4/20
--   --   Missing kitchen hardware
--   --   Stair railing needed
--   --   Repair blemish on side of cabinet above refrigerator Kyle
--   --   Home Inspection Monday, April 29 at 4PM Buyer doing pre walk through on Apr 27
--   --   Pendant lights need to be extended
--   --   Hardware to be installed in kitchen Kyle -4/31
--   --   Floor vent in laundry room doesn’t quite fit Osbaldo
--   --   Adjust closet doors in upstairs bedrooms Osbaldo
--   --   Missing hardware upstairs hall bathroom Kyle 4/31
--   --   Stairwell sconce lights installed upside down Osbaldo
--   --   Remove all cardboard’s from hardwood floor cleaning today Osbaldo
--   --   Drywall patch basement shower head escutcheon Osbaldo
--   --   Missing hardware basement bathroom Kyle
--   --   Missing side splash basement bathroom vanity Remove from under sink
--   --   Clean floors
--   --   Downspout & paper removal
--   --   Closing next week 4/6
--   --   Mark corners of property
--   --   Basement bonus room ceiling dent
--   --   Drain spout front side Drain spout is there but needs to be dug out a bit to fit
--   --   Need splash blocks Adjust location and mulch
--   --   Touch up kitchen shoe mold
--   --   Tighten threshold at top of stairs
--   --   Caulk tile in foyer by stairs
--   --   Cut wire from dining light fixture
--   --   caulking exterior windows
--   --   corner cabinet adjustement
--   --   secure skin on fridge cabient
--   --   retape and skim ceiling in binus room
--   --   exposed nail master carpet
--   --   floor pops in second and third bedroom floor
--   --   address trim on handrail to BR level
--   --   clean garage floor
--   --   wash outside garage door
--   --   Paint touch up throughout
--   --   tighten master shower handle
--   --   secure skin on fridge cabinet
--   --   Paint ceiling in bonus room
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)       Mon, Oct 8
-- -- Pour Slab (1) *        Tue, Oct 9
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *        Patio done/front patio done
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       Scheduled for Tues, Jan 22
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)       Buyer requests to do an electrical walk through
-- -- Exterior Vinyl (0) *        Working on it 3/20-90% complete 3/23
-- -- Insulation (2) *        90% completed 1/23
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        Tues, Jan 29
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Finishing by Wed, Feb 13
-- -- Paint 1 (1)      
-- -- Garage Door (0) *       
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Complete by Mar 7
-- -- Granite Installation (1) *        Mar 27
-- -- Interior Trim - Install (3) *        Mitch is working on trim as of Feb 18/in progress 2/23
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Working on Mar 25
-- -- Paint 2 (3)      
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)       Mitch working 4/10
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *       
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *        Wed, Apr 17
-- -- Electric Trim Out (3)       Started 3/23
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       Started 4/6
-- -- Install Appliances (0) *        Ready by Apr 12
-- -- Paint 3 (2) *       
-- -- Carpet (2)       In process as of Apr 8
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Mon, Apr 22
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       In process
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1)       Wed, May 15 at 1:00 PM
-- -- Payment for Upgrades (0)       $2450?
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       Fri, May 17
-- -- Remove Coded Lockbox (0)