ADDR
CONGERS - 8  ::  2818 Belgian Drive
[ BUILD: 20200001989 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
    Ratified Contract? (0)      
    $2500 Deposit Received (0)      
    Association Packet Requested (0)      
    Association Packet Received (0)      
    Selections Meeting (0)      
    Selections Sheet Signed (0)      
    Amendment for Upgrades (B,S,L,T,BCP) (0)      
    Deposit For Upgrades Received (0)      
CRITICAL PATH
Tue    Feb 3      Inspection (Concrete Wall) (1)      
Wed    Feb 4      Inspection (Conduit Under Slab) (1)      
    Inspection (Drain Tile) (0)      
    Settlement Agent Confirmed (0)      
    Verify Window & Roof Structure (0)      
    Patio (0)      
    Rough In Microwave Vent (0)      
Thu    Feb 5      Inspection (Rough In Plumbing) (1)      
Fri    Feb 6      Inspection (Rough In Electric) (1)      
Mon    Feb 9      Inspection (Framing) (1) *       
    Inspection (Deck Piers) (0)      
    Exterior Stone (0)      
    Set Electric Meter (0) *       
    Inspection (Main Water Line) (0)      
    Loan Approval (0)      
    Deed Preparation (0)      
    Mailbox (0)      
Tue    Feb 10      Interior Trim - Paint (1)      
    Ceiling Fans (0)      
Wed    Feb 11      Blower Door Test (1)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
Thu    Feb 12      Stain Hardwood Stairs (1) *       
TO DO - COMPLETED OR DELETED
Kate - Buyer Needs To Make Selections
ROUGH IN FOR FUTURE BATH IN BASEMENT
703-400-9068
Stair railing? Tom?
Back of cabinet piece-ordered Kate will check on it - installed by May 7
Trim needs paint 3/31
Trim needs paint 3/21
few missing pieces of front siding Hopefully 4/30
Remove sticker from board when installing remaining siding pieces 4/11
CODED LOCKBOX 0808
1/2 bath mirror Ron
Attic cover Needs painting
Piece of bathtub plumbing Tom
Wall sconces needed Need to be installed
Stair Railings needed Tom
Towel bar holder/broken? Kate to tell Ron
Weatherstripping on garage Jeff
Paint under site stair storage
Fill holes in patio door
Caulk bathtub tile
Cabinet trim Kimberly
Ceiling Crack
Trim needed on back of k island 5/5
Blue tape on wall sconce-needs bulb Christian
Drywall repairs MB ceiling
Kitchen cabinet drawer. Issue? Install front
Touch up ceiling paint on main level
Repair sconce in stairwell
Touch up paint
Ceiling touch up in kitchen 5/26
Touch up one split in hallway
Caulk/silicone on bathroom sidesplashes? Jill will remind the painters
Front water nozzle needs screwed to house Tom will tell the plumber
Few touch up paint areas
Few touch up paint areas
Patch/replace towel holder
Patch/replace towel holder
Few touch up paint areas
Few touch up paint areas
Repainting steps black
UPGRADES - COMPLETED
    Vent microwave to outside (price included in contract price)  
    White Kitchen Cabinets ($600 - in amendment)  
    Fantasy Brown Granite level 3 ($575 - in amendment)  
    French Model Fridge ($850 - in amendment)  
    White cabinets in bathrooms ($400 - in amendment)  
    garage keypad  
CRITICAL PATH - COMPLETED
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)       in process 12/9
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *        in process 1/16
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *        in process 2/6
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)       SS with French Fridge
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *        Patio completed
-- -- Privacy Divider / Fence (0) *        In process 4/21
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       in process 1/27
-- -- Plumbing Rough In (4)       in process 2/10
-- -- Electric Rough In (4)       in process 2/10
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       BLACK Hinges
-- -- Drywall (Hang) (4) *        Stocked 2/17
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Needs final sanding 3/3
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Week of Mar 8
-- -- Granite Installation (1) *        Some installed 3/31
-- -- Interior Trim - Install (3) *        In process 3/10
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)      
-- -- Cover Floors (0)      
-- -- Deliver Plumbing / Lighting Fixtures (0)       Black plumbing; black lighting
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *        Almost completed 4/25
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (1) *       
-- -- Electric Trim Out (3) *        Wall sconces. Rest is completed.
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *        Standard Black. Need bath/shower faucets
-- -- Install Appliances (0) *        5/5 ( fridge) 5/6 DW, Range, OTR
-- -- Paint 3 (2) *       
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (4) *       
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Kate & Jill working on this
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)       June 16?
-- -- Buyer Walk Through (1) *        Will come back at 9:00 on 6/16
-- -- Payment for Upgrades (0)       Buyer will bring $100 to closing
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Request Trash Tote From POA Manager (0)      
-- -- Closing (1)       6/16 at 10AM
-- -- Remove Coded Lockbox (0)