ADDR
CONGERS - 12  ::  2840 Belgian Drive
[ BUILD: 202000001993 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
    Ratified Contract? (0)      
    $2500 Deposit Received (0)      
    Association Packet Requested (0)      
    Association Packet Received (0)      
    Selections Meeting (0)      
    Selections Sheet Signed (0)      
    Amendment for Upgrades (B,S,L,T,BCP) (0)      
    Deposit For Upgrades Received (0)      
CRITICAL PATH
Tue    Feb 3      Inspection (Concrete Wall) (1)      
Wed    Feb 4      Inspection (Conduit Under Slab) (1)      
    Inspection (Drain Tile) (0)      
    Settlement Agent Confirmed (0)      
    Verify Window & Roof Structure (0)      
    Patio (0)      
    Rough In Microwave Vent (0)      
Thu    Feb 5      Inspection (Rough In Plumbing) (1)      
Fri    Feb 6      Inspection (Rough In Electric) (1)      
Mon    Feb 9      Inspection (Framing) (1) *       
    Inspection (Deck Piers) (0)      
    Exterior Stone (0)      
    Set Electric Meter (0) *       
    Inspection (Main Water Line) (0)      
    Loan Approval (0)      
    Deed Preparation (0)      
    Mailbox (0)      
Tue    Feb 10      Interior Trim - Paint (1)      
    Ceiling Fans (0)      
Wed    Feb 11      Blower Door Test (1)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
Thu    Feb 12      Stain Hardwood Stairs (1) *       
TO DO - COMPLETED OR DELETED
Kate - Buyer Needs To Make Selections Wednesday 1/6 at 2:00 PM
Question on dishwasher piece of cabinetry
Basement vanity (5/3) top (11th) Top/vanity in living room 5/12
No garage door?
Garage hardware needed
Extra vanity in LR 5/19
Lease starting July 1
Clean out basement for carpet 5/31
Extra quill vanity and top Move to model garage-in garage of 12 6/30
Drywall repairs kitchen
Hole at door lock-Ron
Hole at door lock-Ron
CODED LOCKBOX 1212
Touch up pain
Few mirrors/shower rods need installed 6/23 Wed, June 30. Just MB mirror needs installed 6/30
Attic cover Needs painting 6/26
Paint touch up 6/23
Garage door 6/26
Remove appliances Moving to 20 on 6/28/2021. One left 6/30
Garage needs painting when emptied (primed only) Joanna
Shower rod basement bath
Toilet paper holder up bath
Hole in deadbolt
Remove vanity and top from garage Tom
Touch up paint
Screens kitchen window
Finish front door weather stripping and garage weather stripping
clean mechanical room
clean back patio and door Jill handling after pipe is buried
upstairs hall bathroom has a hole in the wall where the shower head is attached to the wall
stain in master bedroom closet Jill doing it
seal around the black aluminum at front door Tom
need a bigger downspout on the front of the house by garage door Tom/Bridges taking care of-i think completed 7/18
clean all the window sills on the outside
at the bottom of both sides of the garage door on the inside has a hole that needs patched and paint
there is a hole Above the garage door opener at the ceiling.
need paint where the drywallers fixed holes (3 in garage I in 3rd floor hall bathroom) Maher taking care of
Caulk around front porch area
Fix front porch siding
Sagging weather stripping
Fix black side of porch roof
Blistered paint on closet door Maher
Black caulk around front porch support beam
UPGRADES - COMPLETED
    Finished Bonus Room and Bathroom ($9500 included in amendment)  
    Expanded 10 x 18 Patio ($900 included in amendment)  
    Bonus Room Vanity Upgrade  
CRITICAL PATH - COMPLETED
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)       in process 1/6
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       in process 1/20
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *        in process 2/24
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *        in process 2/10
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)       SS Standard
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)       In process 3/10
-- -- Electric Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *        In process 3/17
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       BN hinges
-- -- Drywall (Hang) (4) *        In process 3/28
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Just needs sanding 3/31
-- -- Paint 1 (1)      
-- -- Garage Door (0)       Need correct door - should arrive 6/14
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Delivered 4/14 installed 4/15
-- -- Granite Installation (1) *        Scheduled for 4/29 or 4/30
-- -- Interior Trim - Install (3) *        Needs painting 5/12
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)       In process 6/2
-- -- Cover Floors (0)      
-- -- Deliver Plumbing / Lighting Fixtures (0)       Plumbing PO sent- Tom call for delivery. Lighting ordered
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *        In process 6/19
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (1) *       
-- -- Electric Trim Out (3) *        In process 6/23
-- -- HVAC Trim Out (1) *        in process 5/19
-- -- Plumbing Trim Out (2) *        Plumber working- 6/10
-- -- Install Appliances (0) *        Dishwasher - week of June 14
-- -- Paint 3 (2) *       
-- -- Carpet (2)       In process 5/31
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (4) *        Re-inspect Friday, 6/25
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       In process 6/30
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1) *        Wednesday 7/7 at 12:30 PM
-- -- Payment for Upgrades (0)       $200
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Request Trash Tote From POA Manager (0)      
-- -- Closing (1)       7/23/2021 @ 2:00 PM
-- -- Remove Coded Lockbox (0)