CONGERS - 20  ::  2884 Belgian Drive
[ BUILD: 20200002172 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Nov 4      Ratified Contract? (0)      
Tue    Nov 4      $2500 Deposit Received (0)      
Tue    Nov 4      Association Packet Requested (0)      
Tue    Nov 4      Association Packet Received (0)      
Tue    Nov 4      Selections Meeting (0)      
Tue    Nov 4      Selections Sheet Signed (0)      
Tue    Nov 4      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Nov 4      Deposit For Upgrades Received (0)      
Tue    Nov 4      Inspection (Concrete Wall) (1)      
Wed    Nov 5      Inspection (Conduit Under Slab) (1)      
Thu    Nov 6      Inspection (Drain Tile) (0)      
Thu    Nov 6      Settlement Agent Confirmed (0)      
Thu    Nov 6      Verify Window & Roof Structure (0)      
Thu    Nov 6      Patio (0)      
Thu    Nov 6      Rough In Microwave Vent (0)      
Thu    Nov 6      Inspection (Rough In Plumbing) (1)      
Fri    Nov 7      Inspection (Rough In Electric) (1)      
Mon    Nov 10      Inspection (Framing) (1) *       
Tue    Nov 11      Inspection (Deck Piers) (0)      
Tue    Nov 11      Exterior Stone (0)      
Tue    Nov 11      Set Electric Meter (0) *       
Tue    Nov 11      Inspection (Main Water Line) (0)      
Tue    Nov 11      Loan Approval (0)      
Tue    Nov 11      Deed Preparation (0)      
Tue    Nov 11      Mailbox (0)      
Tue    Nov 11      Order Plumbing / Lighting Fixtures (0)      
Tue    Nov 11      Interior Trim - Paint (1)      
Wed    Nov 12      Ceiling Fans (0)      
Wed    Nov 12      Blower Door Test (1)      
Thu    Nov 13      Inspection (Final HVAC) (1)      
Fri    Nov 14      Inspection (Final Plumbing) (1)      
Mon    Nov 17      Inspection (Final Electric) (1)      
Tue    Nov 18      Stain Hardwood Stairs (1) *       
--   --   Selections 2:00 PM 1/22
--   --   Piece of staircase missing 4/17
--   --   When is buyer to have iron rails installed TJ installing 8/25
--   --   Drywall missing/framing 5/26 Needs finished. Installed 7/11
--   --   Hole in steps
--   --   Vanity in LR Countertop in kitchen
--   --   Drywall repairs needed before paint 2 to stairwell
--   --   Hall bath handle needed Black - vanity - Tom
--   --   Homeowner laying his own floor starting on July 19 In process 7/21
--   --   Elevated area at top of landing 7/24
--   --   Tom-check floors for defects
--   --   Vanity in living room? and basement - move to CC15 garage
--   --   Missing trim near banister
--   --   Dishwasher
--   --   Attic cover Jill
--   --   Gap between cabinet and counter-repair? Painter
--   --   Transition strip between LTV and stairs
--   --   Powder bath trim out needed All baths
--   --   Gaps b/w shoe molding and flooring
--   --   Electric: wall sconce. Powder light. Dining chandelier. Few bulbs.
--   --   Bath trim out needed. All bathrooms
--   --   Master bed closet shelving needed And under the stairs shelf.
--   --   Clean out basement room
--   --   Vanity bulbs
--   --   Powder bath mirror Jill
--   --   Hall bath mirror Jill
--   --   Shelving needed in MB AND UNDER STEPS Joe
--   --   Paint risers Friday, 8/27
--   --   Light bulbs in bathroom fixtures Tom
--   --   Paint railings?
--   --   Remove sink top in garage Jill
--   --   power wash the siding, rocks and driveway Stanley
--   --   shelving needed in the laundry room
--   --   missing closet door handles
--   --   master bedroom closet door needs shaved off a little Trim guy
--   --   LR floor outlet
--   --   paint touch up needed on the ceiling by chandelier
--   --   drywall mud on the pendant light in kitchen
--   --   wall above the living room windows needs another coat of paint
--   --   attic access door needs to be installed
--   --   get the glue off the mirror in the small bathroom on 3rd floor
--   --   nail holes in the baseboard in the master bedroom. painters needs to check all baseboard throughout home.
--   --   get the stickers off the globes on both lights on the top landing Jill
--   --   paint touch up needed throughout home.
-- -- Building Permit (30) *       
    Painted Kitchen Cabinets  
    Upgraded Carpet Pad  
    CREDIT- for not installing stair half walls and standard railing.  
    CREDIT- Buyer to install LVP after closing in two smaller bedrooms.  
    Expanded Driveway  
    Eggshell Paint  
    Credit for buyer installation of LVP on main level  
    Staining buyer supplied rail posts  
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)       in process 2/14
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       in process 3/7
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *        Black hinges
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)       SS Standard
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *   09.06.2021    
-- -- Sod / Seed / Landscaping (0)  09.07.2021    
-- -- HVAC Rough In (4)       Almost complete 4/17
-- -- Plumbing Rough In (4)       In process 5/8
-- -- Electric Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       Note on wall. Tom appears to have addressed issues. 5/15
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       Black hinges
-- -- Drywall (Hang) (4) *        In process 5/22
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process 5/26
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)  08.25.2021    
-- -- Cabinet Installation (2) *        June 22
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3) *        In process 6/23
-- -- Luxury Vinyl Plank (3) *        Will be done 7/26
-- -- Luxury Vinyl Tile (0)       Will be done 7/24
-- -- Paint 2 (3)       In process 7/28
-- -- Cover Floors (1)  08.30.2021    
-- -- Deliver Plumbing / Lighting Fixtures (0)       Black plumbing; black lighting
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *   08.21.2021     Black levers and bathroom accessories-in process 8/18
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3) *   08.21.2021     Black Lighting. In process 8/18
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *        Black Plumbing
-- -- Install Appliances (0) *        Dishwasher needed
-- -- Paint 3 (2) *   08.21.2021     Almost complete 8/4
-- -- Carpet (2)  08.30.2021     Almost finished 8/25
-- -- Appraiser Confirms Construction Completion (0)  09.09.2021     Mike Shirfey, 9/8?
-- -- Inspection (Final Building) (2) *   09.01.2021     Re-inspect Mon, Aug 30
-- -- Pre Walk Through (0)  08.30.2021    
-- -- Cleaning (1)  08.30.2021     Sat, Aug 28
-- -- Certificate of Occupancy (1) *   09.01.2021    
-- -- C.O. to Lender (0)  09.01.2021    
-- -- Schedule Closing (0)  09.11.2021    
-- -- Buyer Walk Through (1) *   09.02.2021     Mon, Aug 30, 4:30 PM?
-- -- Payment for Upgrades (0)  09.11.2021     $75
-- -- Keys to Settlement Agent (0)  09.02.2021    
-- -- Review Settlement Statement (0)  09.02.2021    
-- -- Jerry Signs Closing Documents (0)  09.02.2021     9/1/2021?
-- -- Request Trash Tote From POA Manager (0)  09.02.2021    
-- -- Closing (1)  09.11.2021     Week of 9/7
-- -- Remove Coded Lockbox (0)  09.06.2021