CONGERS - 18  ::  2876 Belgian Drive
[ BUILD: 20200002162 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Needs screens Jill
Tue    Nov 4      Ratified Contract? (0)      
Tue    Nov 4      $2500 Deposit Received (0)      
Tue    Nov 4      Association Packet Requested (0)      
Tue    Nov 4      Association Packet Received (0)      
Tue    Nov 4      Selections Meeting (0)      
Tue    Nov 4      Selections Sheet Signed (0)      
Tue    Nov 4      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Nov 4      Deposit For Upgrades Received (0)      
Tue    Nov 4      Inspection (Concrete Wall) (1)      
Wed    Nov 5      Inspection (Conduit Under Slab) (1)      
Thu    Nov 6      Inspection (Drain Tile) (0)      
Thu    Nov 6      Settlement Agent Confirmed (0)      
Thu    Nov 6      Verify Window & Roof Structure (0)      
Thu    Nov 6      Patio (0)      
Thu    Nov 6      Rough In Microwave Vent (0)      
Thu    Nov 6      Inspection (Rough In Plumbing) (1)      
Fri    Nov 7      Inspection (Rough In Electric) (1)      
Mon    Nov 10      Inspection (Framing) (1) *       
Tue    Nov 11      Inspection (Deck Piers) (0)      
Tue    Nov 11      Exterior Stone (0)      
Tue    Nov 11      Set Electric Meter (0) *       
Tue    Nov 11      Inspection (Main Water Line) (0)      
Tue    Nov 11      Loan Approval (0)      
Tue    Nov 11      Deed Preparation (0)      
Tue    Nov 11      Mailbox (0)      
Tue    Nov 11      Order Plumbing / Lighting Fixtures (0)      
Tue    Nov 11      Interior Trim - Paint (1)      
Wed    Nov 12      Ceiling Fans (0)      
Wed    Nov 12      Blower Door Test (1)      
Thu    Nov 13      Inspection (Final HVAC) (1)      
Fri    Nov 14      Inspection (Final Plumbing) (1)      
Mon    Nov 17      Inspection (Final Electric) (1)      
Tue    Nov 18      Stain Hardwood Stairs (1) *       
--   --   Design Appointment Monday January 18 at 11:00 AM
--   --   Fence location How far to side, front - Julie asks
--   --   Need vanity for powder bath mid July
--   --   NOTE- ONLY LIGHTING IS BLACK_ ALL ESLE IS BN
--   --   NOTE- ONLY LIGHTING BLACK- ALL ELSE BN
--   --   Top for powder bath vanity needed 7/11 Waiting on install as of 7/19
--   --   Patio crack
--   --   Kate - ok to switch to a different color? Kate will connect with Tom
--   --   Patio crack
--   --   Bath globe broken 7/24 Jill is aware
--   --   Few hinges are black-doorknobs are silver? Jill/Kate making VA installations aware 8/9
--   --   Some rock has fallen on front of garage 7/28
--   --   Trim needed between vanity and wall -powder 7/28 Trim guys will repair. Jill has told them.
--   --   CODED LOCKBOX 1818
--   --   Stain stairs (2) Jill will schedule
--   --   Light needed in pantry Snap light needed - Tom will tell electrician
--   --   Blemish in driveway? Tom will check it out
--   --   Weather stripping
--   --   Clean garage Jill will schedule
--   --   Shelving in basement closet correct?
--   --   Few paint/trim touch ups 8/16
--   --   Paint railings 8/16
--   --   Shoe molding piece in bonus room
--   --   Garage drywall repairs In process 8/21
--   --   Paint garage painter
--   --   Few screens need installed Jill
--   --   Ceiling patch touch up master bed painter
--   --   exposed screw heads at top of first set of stairs Maher
--   --   paint touch up throughout home painter
--   --   re clean after all touch up painting is completes
--   --   re-clean after all punch out is completed.
--   --   adjust front door threshold. Tom
--   --   patio screen door needs to be installed
--   --   island panel has a few staple holes that need filled in.
--   --   sconce lights on landing need to be turned down electrician
--   --   exposed screw heads at top of first set of stairs
--   --   paint touch up throughout home
--   --   re-clean after all the punch out is completed
--   --   adjust the front door threshold
--   --   need a patio screen door installed Tom and Jill
--   --   the big panel on the island has a few nail holes in it that need filled in Jill
--   --   sconce lights on the landing need turned down
--   --   patio door doesnt latch properly Tom
--   --   clean vent at the top of the stairs on the 3rd floor return - Jill
--   --   vanity has nails/staples that are sticking out of the side of the cabinet where it was put together at on the front corner peice to the right. Tom will look at it - owner suggests a second thin strip of that same color of cabinet to cover it
--   --   pressure wash the driveway and the rocks on the front corner of home Jill will coordinate
--   --   chip concrete off of the sewer cleanout by the front door outside Jill will coordinate
--   --   Landscaping out front Kate will follow up 8/26
--   --   Another coat of poly on stairs
--   --   Adjust water pressure Tom
--   --   Adjust dining area light (swag)
--   --   Remove blue top above garage Jill
-- -- Building Permit (30) *       
    eggshell paint  
    Custom Paint Color  
    Painted Kitchen and Bath Cabinetry  
    Cabinet Crown Moulding  
    Main Level Crown Moulding  
    Level III Quartz Kitchen Counters  
    LVP in Upstairs Hallway and Bedrooms  
    LVP in Bonus Room  
    Oak Stairs to bedroom level  
    Upgrade from cultured marble to level III quartz for all bath vanities  
    Expanded Driveway  
    Upgraded vanity over pedestal for bonus bath  
    Double pull out waste basket  
    Upgraded vanity over pedestal for powder bath  
    Expanded Patio- 10x18  
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
    Add Bonus Room Window  
-- -- Plumb Slab (2)       in process 2/14
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       in process 3/7
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
    Finished Bonus Room Behind Garage (carpet, full bathroom with pedestal sink, tub/shower) ($9500 included in contract price)  
    Add Bonus Rom Closet  
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)       SS Standard
-- -- Deck (0)      
-- -- Gutters (0)       Installing 8/2
-- -- Driveway (0) *        concrete theyBuyer request- "dig just a little deeper so our pavers are more ground level?"
-- -- Privacy Divider / Fence (0) *   09.07.2021     Week of Aug 30
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       In process 4/14
-- -- Plumbing Rough In (4)       In process 5/1
-- -- Electric Rough In (4)       In process 5/1
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *        In process 7/18
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       BN hinges
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process 5/12
-- -- Paint 1 (1)      
-- -- Garage Door (0)       doors are in!
-- -- House Numbers (0)  08.30.2021     numbers need to be added to mailboxes
-- -- Cabinet Installation (2) *       
-- -- Granite Installation (1) *        Kate to follow up with Joy
-- -- Interior Trim - Install (3) *        On site 5/31
-- -- Luxury Vinyl Plank (3) *        Almost complete 8/11
-- -- Luxury Vinyl Tile (0)       supposed to arrive Saturday 8/7
-- -- Paint 2 (3)       In process 7/18
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)       BN Plumbing; Black Lighting
-- -- Shoe Moulding (0)       In process 8/11
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        BN Levers and BN Bathroom accessories; Bonus Bath
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3) *        Black Lighting-in process 7/24
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *        Install toilets 8/11
-- -- Install Appliances (0) *        SS and French Model Fridge. Friday 8/6
-- -- Paint 3 (2) *       
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Fri, Aug 13
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       8/17
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1) *        Wed, 8/18, 2PM
-- -- Payment for Upgrades (0)  08.21.2021     $276,400 + $18,725 = $295,125
-- -- Keys to Settlement Agent (0)  08.21.2021    
-- -- Review Settlement Statement (0)  08.21.2021    
-- -- Jerry Signs Closing Documents (0)  08.24.2021     Monday, 8/23, 1:30 PM
-- -- Request Trash Tote From POA Manager (0)  08.23.2021    
-- -- Closing (1)  08.26.2021     Tuesday, 8/24, 3:30 PM
-- -- Remove Coded Lockbox (0)  08.30.2021