|
| TO DO |
|
|
Needs screens |
Jill |
|
|
| UPGRADES |
| --- |
|
|
|
Ratified Contract? (0) |
|
|
|
|
|
$2500 Deposit Received (0) |
|
|
|
|
|
Association Packet Requested (0) |
|
|
|
|
|
Association Packet Received (0) |
|
|
|
|
|
Selections Meeting (0) |
|
|
|
|
|
Selections Sheet Signed (0) |
|
|
|
|
|
Amendment for Upgrades (B,S,L,T,BCP) (0) |
|
|
|
|
|
Deposit For Upgrades Received (0) |
|
|
|
| CRITICAL PATH |
|
Tue
|
Feb 3
|
Inspection (Concrete Wall) (1) |
|
|
|
Wed
|
Feb 4
|
Inspection (Conduit Under Slab) (1) |
|
|
|
|
|
Inspection (Drain Tile) (0) |
|
|
|
|
|
Settlement Agent Confirmed (0) |
|
|
|
|
|
Verify Window & Roof Structure (0) |
|
|
|
|
|
Patio (0) |
|
|
|
|
|
Rough In Microwave Vent (0) |
|
|
|
Thu
|
Feb 5
|
Inspection (Rough In Plumbing) (1) |
|
|
|
Fri
|
Feb 6
|
Inspection (Rough In Electric) (1) |
|
|
|
Mon
|
Feb 9
|
Inspection (Framing) (1) * |
|
|
|
|
|
Inspection (Deck Piers) (0) |
|
|
|
|
|
Exterior Stone (0) |
|
|
|
|
|
Set Electric Meter (0) * |
|
|
|
|
|
Inspection (Main Water Line) (0) |
|
|
|
|
|
Loan Approval (0) |
|
|
|
|
|
Deed Preparation (0) |
|
|
|
|
|
Mailbox (0) |
|
|
|
|
|
Order Plumbing / Lighting Fixtures (0) |
|
|
|
Tue
|
Feb 10
|
Interior Trim - Paint (1) |
|
|
|
|
|
Ceiling Fans (0) |
|
|
|
Wed
|
Feb 11
|
Blower Door Test (1) |
|
|
|
|
|
Inspection (Final HVAC) (0) |
|
|
|
|
|
Inspection (Final Plumbing) (0) |
|
|
|
|
|
Inspection (Final Electric) (0) |
|
|
|
Thu
|
Feb 12
|
Stain Hardwood Stairs (1) * |
|
|
|
| TO DO - COMPLETED OR DELETED |
|
|
Design Appointment Monday January 18 at 11:00 AM |
|
|
|
|
Fence location |
How far to side, front - Julie asks |
|
|
|
Need vanity for powder bath |
mid July |
|
|
|
NOTE- ONLY LIGHTING IS BLACK_ ALL ESLE IS BN |
|
|
|
|
NOTE- ONLY LIGHTING BLACK- ALL ELSE BN |
|
|
|
|
Top for powder bath vanity needed 7/11 |
Waiting on install as of 7/19 |
|
|
|
Patio crack |
|
|
|
|
Kate - ok to switch to a different color? |
Kate will connect with Tom |
|
|
|
Patio crack |
|
|
|
|
Bath globe broken 7/24 |
Jill is aware |
|
|
|
Few hinges are black-doorknobs are silver? |
Jill/Kate making VA installations aware 8/9 |
|
|
|
Some rock has fallen on front of garage 7/28 |
|
|
|
|
Trim needed between vanity and wall -powder 7/28 |
Trim guys will repair. Jill has told them. |
|
|
|
CODED LOCKBOX 1818 |
|
|
|
|
Stain stairs (2) |
Jill will schedule |
|
|
|
Light needed in pantry |
Snap light needed - Tom will tell electrician |
|
|
|
Blemish in driveway? |
Tom will check it out |
|
|
|
Weather stripping |
|
|
|
|
Clean garage |
Jill will schedule |
|
|
|
Shelving in basement closet correct? |
|
|
|
|
Few paint/trim touch ups |
8/16 |
|
|
|
Paint railings |
8/16 |
|
|
|
Shoe molding piece in bonus room |
|
|
|
|
Garage drywall repairs |
In process 8/21 |
|
|
|
Paint garage |
painter |
|
|
|
Few screens need installed |
Jill |
|
|
|
Ceiling patch touch up master bed |
painter |
|
|
|
exposed screw heads at top of first set of stairs |
Maher |
|
|
|
paint touch up throughout home |
painter |
|
|
|
re clean after all touch up painting is completes |
|
|
|
|
re-clean after all punch out is completed. |
|
|
|
|
adjust front door threshold. |
Tom |
|
|
|
patio screen door needs to be installed |
|
|
|
|
island panel has a few staple holes that need filled in. |
|
|
|
|
sconce lights on landing need to be turned down |
electrician |
|
|
|
exposed screw heads at top of first set of stairs |
|
|
|
|
paint touch up throughout home |
|
|
|
|
re-clean after all the punch out is completed |
|
|
|
|
adjust the front door threshold |
|
|
|
|
need a patio screen door installed |
Tom and Jill |
|
|
|
the big panel on the island has a few nail holes in it that need filled in |
Jill |
|
|
|
sconce lights on the landing need turned down |
|
|
|
|
patio door doesnt latch properly |
Tom |
|
|
|
clean vent at the top of the stairs on the 3rd floor |
return - Jill |
|
|
|
vanity has nails/staples that are sticking out of the side of the cabinet where it was put together at on the front corner peice to the right. |
Tom will look at it - owner suggests a second thin strip of that same color of cabinet to cover it |
|
|
|
pressure wash the driveway and the rocks on the front corner of home |
Jill will coordinate |
|
|
|
chip concrete off of the sewer cleanout by the front door outside |
Jill will coordinate |
|
|
|
Landscaping out front |
Kate will follow up 8/26 |
|
|
|
Another coat of poly on stairs |
|
|
|
|
Adjust water pressure |
Tom |
|
|
|
Adjust dining area light (swag) |
|
|
|
|
Remove blue top above garage |
Jill |
|
|
| UPGRADES - COMPLETED |
| |
|
Finished Bonus Room Behind Garage (carpet, full bathroom with pedestal sink, tub/shower) ($9500 included in contract price)
|
|
| |
|
Add Bonus Room Window
|
|
| |
|
Add Bonus Rom Closet
|
|
| |
|
eggshell paint
|
|
| |
|
Custom Paint Color
|
|
| |
|
Painted Kitchen and Bath Cabinetry
|
|
| |
|
Cabinet Crown Moulding
|
|
| |
|
Main Level Crown Moulding
|
|
| |
|
Level III Quartz Kitchen Counters
|
|
| |
|
LVP in Upstairs Hallway and Bedrooms
|
|
| |
|
LVP in Bonus Room
|
|
| |
|
Oak Stairs to bedroom level
|
|
| |
|
Upgrade from cultured marble to level III quartz for all bath vanities
|
|
| |
|
Expanded Driveway
|
|
| |
|
Upgraded vanity over pedestal for bonus bath
|
|
| |
|
Double pull out waste basket
|
|
| |
|
Upgraded vanity over pedestal for powder bath
|
|
| |
|
Expanded Patio- 10x18
|
|
|
| CRITICAL PATH - COMPLETED |
| -- |
-- |
Building Permit (30) * |
|
|
| -- |
-- |
Order Roof & Floor Trusses (1) |
|
|
| -- |
-- |
Order Windows & Doors (0) |
|
|
| -- |
-- |
Stake Out Home (1) |
|
|
| -- |
-- |
Excavate (2) |
|
|
| -- |
-- |
Inspection (Footers) (1) |
|
|
| -- |
-- |
Pour Footers (1) * |
|
|
| -- |
-- |
Set Forms (2) |
|
|
| -- |
-- |
Pour Foundation Walls (1) |
|
|
| -- |
-- |
Plumb Slab (2) |
in process 2/14 |
|
| -- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
| -- |
-- |
Prepare Slab (1) |
|
|
| -- |
-- |
Inspection (Slab) (1) |
|
|
| -- |
-- |
Pour Slab (1) * |
|
|
| -- |
-- |
Framing I (9) |
in process 3/7 |
|
| -- |
-- |
Order Steps (0) |
|
|
| -- |
-- |
Order Tubs / Showers (0) |
|
|
| -- |
-- |
Framing II (8) |
|
|
| -- |
-- |
Framing III (8) * |
|
|
| -- |
-- |
Install Stairs (0) * |
|
|
| -- |
-- |
Windows & Doors (0) * |
|
|
| -- |
-- |
House Number and Status in Window (0) |
|
|
| -- |
-- |
Roofing (0) * |
|
|
| -- |
-- |
Order Cabinets (0) |
|
|
| -- |
-- |
Order Appliances (0) |
SS Standard |
|
| -- |
-- |
Deck (0) |
|
|
| -- |
-- |
Gutters (0) |
Installing 8/2 |
|
| -- |
-- |
Driveway (0) * |
concrete theyBuyer request- "dig just a little deeper so our pavers are more ground level?" |
|
| -- |
-- |
Privacy Divider / Fence (0) * 09.07.2021 |
Week of Aug 30 |
|
| -- |
-- |
Sod / Seed / Landscaping (0) |
|
|
| -- |
-- |
HVAC Rough In (4) |
In process 4/14 |
|
| -- |
-- |
Plumbing Rough In (4) |
In process 5/1 |
|
| -- |
-- |
Electric Rough In (4) |
In process 5/1 |
|
| -- |
-- |
Inspection (Rough In HVAC) (1) |
|
|
| -- |
-- |
Exterior Vinyl (0) * |
In process 7/18 |
|
| -- |
-- |
Insulation (2) * |
|
|
| -- |
-- |
Inspection (Insulation) (1) |
|
|
| -- |
-- |
Inspection (Electric Service) (0) |
|
|
| -- |
-- |
Inspection (Main Sewer Line) (0) |
|
|
| -- |
-- |
Order Interior Doors & Trim (0) |
BN hinges |
|
| -- |
-- |
Drywall (Hang) (4) * |
|
|
| -- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
In process 5/12 |
|
| -- |
-- |
Paint 1 (1) |
|
|
| -- |
-- |
Garage Door (0) |
doors are in! |
|
| -- |
-- |
House Numbers (0) 08.30.2021 |
numbers need to be added to mailboxes |
|
| -- |
-- |
Cabinet Installation (2) * |
|
|
| -- |
-- |
Granite Installation (1) * |
Kate to follow up with Joy |
|
| -- |
-- |
Interior Trim - Install (3) * |
On site 5/31 |
|
| -- |
-- |
Luxury Vinyl Plank (3) * |
Almost complete 8/11 |
|
| -- |
-- |
Luxury Vinyl Tile (0) |
supposed to arrive Saturday 8/7 |
|
| -- |
-- |
Paint 2 (3) |
In process 7/18 |
|
| -- |
-- |
Cover Floors (0) |
|
|
| -- |
-- |
Deliver Plumbing / Lighting Fixtures (0) |
BN Plumbing; Black Lighting |
|
| -- |
-- |
Shoe Moulding (0) |
In process 8/11 |
|
| -- |
-- |
Shelving, Door Knobs, Fire Extinguisher (1) * |
BN Levers and BN Bathroom accessories; Bonus Bath |
|
| -- |
-- |
Install Coded Lockbox (add extra keys) (0) |
|
|
| -- |
-- |
Pay Water / Sewer Taps (0) |
|
|
| -- |
-- |
Set Water Meter (1) * |
|
|
| -- |
-- |
Electric Trim Out (3) * |
Black Lighting-in process 7/24 |
|
| -- |
-- |
HVAC Trim Out (1) * |
|
|
| -- |
-- |
Plumbing Trim Out (2) * |
Install toilets 8/11 |
|
| -- |
-- |
Install Appliances (0) * |
SS and French Model Fridge. Friday 8/6 |
|
| -- |
-- |
Paint 3 (2) * |
|
|
| -- |
-- |
Carpet (2) |
|
|
| -- |
-- |
Appraiser Confirms Construction Completion (0) |
|
|
| -- |
-- |
Inspection (Final Building) (4) * |
Fri, Aug 13 |
|
| -- |
-- |
Pre Walk Through (0) |
|
|
| -- |
-- |
Cleaning (1) |
8/17 |
|
| -- |
-- |
Certificate of Occupancy (1) * |
|
|
| -- |
-- |
C.O. to Lender (0) |
|
|
| -- |
-- |
Schedule Closing (0) |
|
|
| -- |
-- |
Buyer Walk Through (1) * |
Wed, 8/18, 2PM |
|
| -- |
-- |
Payment for Upgrades (0) 08.21.2021 |
$276,400 + $18,725 = $295,125 |
|
| -- |
-- |
Keys to Settlement Agent (0) 08.21.2021 |
|
|
| -- |
-- |
Review Settlement Statement (0) 08.21.2021 |
|
|
| -- |
-- |
Jerry Signs Closing Documents (0) 08.24.2021 |
Monday, 8/23, 1:30 PM |
|
| -- |
-- |
Request Trash Tote From POA Manager (0) 08.23.2021 |
|
|
| -- |
-- |
Closing (1) 08.26.2021 |
Tuesday, 8/24, 3:30 PM |
|
| -- |
-- |
Remove Coded Lockbox (0) 08.30.2021 |
|
|