CONGERS - 13  ::  2844 Belgian Drive
[ BUILD: 20200001994 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
    Ratified Contract? (0)      
    $2500 Deposit Received (0)      
    Association Packet Requested (0)      
    Association Packet Received (0)      
    Selections Meeting (0)      
    Selections Sheet Signed (0)      
    Amendment for Upgrades (B,S,L,T,BCP) (0)      
    Deposit For Upgrades Received (0)      
    Bonus Room Vanity Upgrade  
CRITICAL PATH
Tue    Feb 3      Inspection (Concrete Wall) (1)      
Wed    Feb 4      Inspection (Conduit Under Slab) (1)      
    Inspection (Drain Tile) (0)      
    Settlement Agent Confirmed (0)      
    Verify Window & Roof Structure (0)      
    Patio (0)      
    Rough In Microwave Vent (0)      
Thu    Feb 5      Inspection (Rough In Plumbing) (1)      
Fri    Feb 6      Inspection (Rough In Electric) (1)      
Mon    Feb 9      Inspection (Framing) (1) *       
    Inspection (Deck Piers) (0)      
    Exterior Stone (0)      
    Set Electric Meter (0) *       
    Inspection (Main Water Line) (0)      
    Loan Approval (0)      
    Deed Preparation (0)      
    Mailbox (0)      
Tue    Feb 10      Cabinet Installation (2) *        Delivered 4/14 and delivered 4/15
Thu    Feb 12      Interior Trim - Paint (1)      
Fri    Feb 13      Shelving, Door Knobs, Fire Extinguisher (1) *        BN Levers and BN Bathroom accessories; Bonus Bath. In process 6/26
Mon    Feb 16      Set Water Meter (1) *       
    Ceiling Fans (0)      
Tue    Feb 17      Blower Door Test (1)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
Wed    Feb 18      Stain Hardwood Stairs (1) *       
TO DO - COMPLETED OR DELETED
Kate - Buyer Needs To Make Selections Wednesday 1/6 at 2:00 PM
Fence easement for Lot 7 Next steps, Jerry?
Window size on 2nd vs 3rd floor
Basement vanity (5/3) top (11th)
Extra vanity in Lr 5/19
Hole in trim on stair landing to bedroom level
Garage window broken 6/6
Missing carpet for steps and bonus room 6/16 Bonus room in process 6/19
Stain steps Jill will follow up
Stain steps
Handrails needed
Attic cover needed Needs to be painted
Finish front door weather stripping Painter or Tom - and garage weather stripping
Basement cabinet molding needed 9/13 - being ordered now
Touch up paint In process 6/30
CODED LOCKBOX 1313
Garage needs painting 6/30
Missing kick plate for kitchen cabinet
there is a couple spots on the master bedroom carpet that needs cleaned
clean all the window sills on the outside I think completed 7/11
needs more water pressure in showers Tom
the return air cent in the basement needs some mud on some nail holes on one side and needs painted I think completed 7/11
laundry room thresh hold is bent up on one side and its keeping the door from shutting Tom
both sides of the garage door there are alot of nail holes and rough places that need fixed I think completed 7/11
exposed gutter line In process 7/14 - Jill will check on this
adjustment of closet doors
exterior siding needed over front porch area (12 or 13)
holes in garage ceiling, near garage door sensors
Heat pump is frozen 7/18
UPGRADES - COMPLETED
    Finished Bonus Room and Bathroom ($9500 included in amendment)  
    Expanded 10 x 18 Patio ($900 included in amendment)  
CRITICAL PATH - COMPLETED
-- -- Building Permit (30) *   12.14.2025    
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)  12.14.2025     in process 11/7
-- -- Inspection (Footers) (1)       11/9
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)       in process 1/6
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       in process 1/20
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *        in process 2/14
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *        in process 2/10
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)       SS Standard
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       In process 2/24
-- -- Plumbing Rough In (4)       In process 3/14
-- -- Electric Rough In (4)       In process. Will be done 3/17
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *        In process 5/15
-- -- Insulation (2) *        In process 3/24
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       BN hinges
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Needs final sanding 4/11
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Granite Installation (1) *        Scheduled for 4/29 or 4/30
-- -- Interior Trim - Install (3) *        Needs painting. 5/8
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)       Started 6/6
-- -- Cover Floors (0)       after carpet is completed
-- -- Deliver Plumbing / Lighting Fixtures (0)       ( Plumbing PO sent- Tom call for delivery) Lighting Ordered
-- -- Shoe Moulding (0)      
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3) *        In process 6/23
-- -- HVAC Trim Out (1) *        in process 5/19
-- -- Plumbing Trim Out (2) *        Standard BN Plumbing
-- -- Install Appliances (0) *        Dishwasher is in 6/19
-- -- Paint 3 (2) *       
-- -- Carpet (2)       One room in basement
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (4) *        By Friday, June 25
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1) *        Wednesday 7/7 at 12:30 PM
-- -- Payment for Upgrades (0)       $200
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Request Trash Tote From POA Manager (0)      
-- -- Closing (1)       7/23/2021 @ 2:00 PM
-- -- Remove Coded Lockbox (0)