CONGERS - 13  ::  2844 Belgian Drive
[ BUILD: 20200001994 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Nov 4      Ratified Contract? (0)      
Tue    Nov 4      $2500 Deposit Received (0)      
Tue    Nov 4      Association Packet Requested (0)      
Tue    Nov 4      Association Packet Received (0)      
Tue    Nov 4      Selections Meeting (0)      
Tue    Nov 4      Selections Sheet Signed (0)      
Tue    Nov 4      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Nov 4      Deposit For Upgrades Received (0)      
Tue    Nov 4      Inspection (Concrete Wall) (1)      
Wed    Nov 5      Inspection (Conduit Under Slab) (1)      
Thu    Nov 6      Inspection (Drain Tile) (0)      
Thu    Nov 6      Settlement Agent Confirmed (0)      
Thu    Nov 6      Verify Window & Roof Structure (0)      
Thu    Nov 6      Patio (0)      
Thu    Nov 6      Rough In Microwave Vent (0)      
Thu    Nov 6      Inspection (Rough In Plumbing) (1)      
Fri    Nov 7      Inspection (Rough In Electric) (1)      
Mon    Nov 10      Inspection (Framing) (1) *       
Tue    Nov 11      Inspection (Deck Piers) (0)      
Tue    Nov 11      Exterior Stone (0)      
Tue    Nov 11      Set Electric Meter (0) *       
Tue    Nov 11      Inspection (Main Water Line) (0)      
Tue    Nov 11      Loan Approval (0)      
Tue    Nov 11      Deed Preparation (0)      
Tue    Nov 11      Mailbox (0)      
Tue    Nov 11      Interior Trim - Paint (1)      
Wed    Nov 12      Ceiling Fans (0)      
Wed    Nov 12      Blower Door Test (1)      
Thu    Nov 13      Inspection (Final HVAC) (1)      
Fri    Nov 14      Inspection (Final Plumbing) (1)      
Mon    Nov 17      Inspection (Final Electric) (1)      
Tue    Nov 18      Stain Hardwood Stairs (1) *       
--   --   Kate - Buyer Needs To Make Selections Wednesday 1/6 at 2:00 PM
--   --   Fence easement for Lot 7 Next steps, Jerry?
--   --   Window size on 2nd vs 3rd floor
--   --   Basement vanity (5/3) top (11th)
--   --   Extra vanity in Lr 5/19
--   --   Hole in trim on stair landing to bedroom level
--   --   Garage window broken 6/6
--   --   Missing carpet for steps and bonus room 6/16 Bonus room in process 6/19
--   --   Stain steps Jill will follow up
--   --   Stain steps
--   --   Handrails needed
--   --   Attic cover needed Needs to be painted
--   --   Finish front door weather stripping Painter or Tom - and garage weather stripping
--   --   Basement cabinet molding needed 9/13 - being ordered now
--   --   Touch up paint In process 6/30
--   --   CODED LOCKBOX 1313
--   --   Garage needs painting 6/30
--   --   Missing kick plate for kitchen cabinet
--   --   there is a couple spots on the master bedroom carpet that needs cleaned
--   --   clean all the window sills on the outside I think completed 7/11
--   --   needs more water pressure in showers Tom
--   --   the return air cent in the basement needs some mud on some nail holes on one side and needs painted I think completed 7/11
--   --   laundry room thresh hold is bent up on one side and its keeping the door from shutting Tom
--   --   both sides of the garage door there are alot of nail holes and rough places that need fixed I think completed 7/11
--   --   exposed gutter line In process 7/14 - Jill will check on this
--   --   adjustment of closet doors
--   --   exterior siding needed over front porch area (12 or 13)
--   --   holes in garage ceiling, near garage door sensors
--   --   Heat pump is frozen 7/18
-- -- Building Permit (30) *       
    Bonus Room Vanity Upgrade  
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)       in process 11/7
-- -- Inspection (Footers) (1)       11/9
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)       in process 1/6
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       in process 1/20
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
    Finished Bonus Room and Bathroom ($9500 included in amendment)  
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *        in process 2/14
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *        in process 2/10
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)       SS Standard
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
    Expanded 10 x 18 Patio ($900 included in amendment)  
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       In process 2/24
-- -- Plumbing Rough In (4)       In process 3/14
-- -- Electric Rough In (4)       In process. Will be done 3/17
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *        In process 5/15
-- -- Insulation (2) *        In process 3/24
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       BN hinges
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Needs final sanding 4/11
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Delivered 4/14 and delivered 4/15
-- -- Granite Installation (1) *        Scheduled for 4/29 or 4/30
-- -- Interior Trim - Install (3) *        Needs painting. 5/8
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)       Started 6/6
-- -- Cover Floors (1)       after carpet is completed
-- -- Deliver Plumbing / Lighting Fixtures (0)       ( Plumbing PO sent- Tom call for delivery) Lighting Ordered
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        BN Levers and BN Bathroom accessories; Bonus Bath. In process 6/26
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3) *        In process 6/23
-- -- HVAC Trim Out (1) *        in process 5/19
-- -- Plumbing Trim Out (2) *        Standard BN Plumbing
-- -- Install Appliances (0) *        Dishwasher is in 6/19
-- -- Paint 3 (2) *       
-- -- Carpet (2)       One room in basement
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        By Friday, June 25
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1) *        Wednesday 7/7 at 12:30 PM
-- -- Payment for Upgrades (0)       $200
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Request Trash Tote From POA Manager (0)      
-- -- Closing (1)       7/23/2021 @ 2:00 PM
-- -- Remove Coded Lockbox (0)