| TO DO |
|
|
Closet before drywall-6/26 |
Closet is in. Needs drywall. 7/11 |
|
|
|
Bonus room vanity upgrade |
|
|
|
|
Few missing trim pieces in kitchen (likely after cabinet install) |
floor trim |
|
|
|
Custom plumbing - can we say no? |
|
|
|
|
Plumbing for washer and dryer on main level? |
|
|
|
|
Notches in cabinets for granite? |
|
|
|
|
Patch nail holes at trim around garage |
|
|
|
|
Staircase being built off deck? |
|
|
|
|
Missing light cover in bonus room |
|
|
|
|
Attic cover needed |
|
|
|
|
Dishwasher |
Waiting on CJ |
|
|
|
CODED LOCKBOX 6666 |
|
|
|
|
Paint door |
|
|
|
|
Basement closet shelving |
|
|
|
|
Mirrors |
|
|
|
|
Stain steps |
|
|
|
|
Screens |
for bedrooms, on order |
|
|
|
Repair scratch on toilet lid |
|
|
|
|
Clean |
|
|
|
|
Touch up paint |
|
|
|
|
Sand edges of doors |
|
|
|
|
Make the range, oven and stove function |
Plug it up or in |
|
|
|
Loose or fallen stones on front of townhouse need to be secured |
Jill |
|
|
| UPGRADES |
| --- |
|
| CRITICAL PATH |
|
|
|
Association Packet Received (0) 11.21.2021 |
|
|
|
Tue
|
Feb 3
|
Set Forms (2) |
in process 3/24 |
|
|
Thu
|
Feb 5
|
Pour Foundation Walls (1) |
|
|
|
Fri
|
Feb 6
|
Pour Slab (1) * |
|
|
|
|
|
Settlement Agent Confirmed (0) 11.21.2021 |
|
|
|
|
|
Order Tubs / Showers (0) |
|
|
|
Mon
|
Feb 9
|
Framing III (8) * |
|
|
|
|
|
Verify Window & Roof Structure (0) |
|
|
|
|
|
Install Stairs (0) * |
|
|
|
|
|
Deck (0) 10.10.2021 |
|
|
|
|
|
Rough In Microwave Vent (0) |
|
|
|
Thu
|
Feb 19
|
Inspection (Rough In HVAC) (1) |
Tuesday, 6/22 |
|
|
|
|
Set Electric Meter (0) * |
|
|
|
|
|
Order Plumbing / Lighting Fixtures (0) |
|
|
|
|
|
Cover Floors (0) 10.21.2021 |
|
|
|
|
|
Deliver Plumbing / Lighting Fixtures (0) 10.20.2021 |
|
|
|
Fri
|
Feb 20
|
Blower Door Test (1) |
|
|
|
Mon
|
Feb 23
|
Closing (1) 11.01.2021 |
Friday, 10/29 at 4:00 PM |
|
|
| TO DO - COMPLETED OR DELETED |
|
|
Touch up scuff mark on wall in stairwell |
|
|
|
| UPGRADES - COMPLETED |
| |
|
Finish Bonus Room and Bath with vanity upgrade and closet
|
|
| |
|
White painted kitchen cabinetry
|
|
| |
|
LVP in Bonus Room
|
|
| |
|
Expanded Driveway
|
|
| |
|
Expanded Deck 12x18
|
|
| |
|
Expanded patio under deck 12 x 18
|
|
| |
|
Picket fence allowance
|
|
| |
|
Amendment from $279,900 to $301,000
|
|
|
| CRITICAL PATH - COMPLETED |
| -- |
-- |
Ratified Contract? (0) 11.21.2021 |
|
|
| -- |
-- |
$2500 Deposit Received (0) 11.21.2021 |
|
|
| -- |
-- |
Association Packet Requested (0) 11.21.2021 |
|
|
| -- |
-- |
Selections Meeting (0) 11.21.2021 |
|
|
| -- |
-- |
Selections Sheet Signed (0) 11.21.2021 |
|
|
| -- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 11.21.2021 |
|
|
| -- |
-- |
Deposit For Upgrades Received (0) 11.21.2021 |
|
|
| -- |
-- |
Building Permit (30) * |
|
|
| -- |
-- |
Order Roof & Floor Trusses (1) |
|
|
| -- |
-- |
Order Windows & Doors (0) |
|
|
| -- |
-- |
Stake Out Home (1) |
|
|
| -- |
-- |
Excavate (2) |
|
|
| -- |
-- |
Inspection (Footers) (1) |
|
|
| -- |
-- |
Inspection (Concrete Wall) (1) 02.11.2023 |
|
|
| -- |
-- |
Pour Footers (1) * |
|
|
| -- |
-- |
Plumb Slab (2) |
|
|
| -- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
| -- |
-- |
Inspection (Conduit Under Slab) (1) 02.11.2023 |
|
|
| -- |
-- |
Prepare Slab (1) |
|
|
| -- |
-- |
Inspection (Slab) (1) |
|
|
| -- |
-- |
Inspection (Drain Tile) (0) 02.11.2023 |
|
|
| -- |
-- |
Framing I (9) |
in process 5/1 |
|
| -- |
-- |
Order Steps (0) |
|
|
| -- |
-- |
Framing II (8) |
|
|
| -- |
-- |
Windows & Doors (0) * |
in process 6/6 |
|
| -- |
-- |
House Number and Status in Window (0) |
|
|
| -- |
-- |
Roofing (0) * |
in process 6/6 |
|
| -- |
-- |
Order Cabinets (0) |
|
|
| -- |
-- |
Order Appliances (0) 08.30.2021 |
SS Standard |
|
| -- |
-- |
Gutters (0) 10.18.2021 |
|
|
| -- |
-- |
Driveway (0) * 09.22.2021 |
|
|
| -- |
-- |
Patio (0) 02.11.2023 |
|
|
| -- |
-- |
Privacy Divider / Fence (0) * 10.18.2021 |
|
|
| -- |
-- |
Sod / Seed / Landscaping (0) 11.01.2021 |
|
|
| -- |
-- |
HVAC Rough In (4) |
|
|
| -- |
-- |
Plumbing Rough In (4) |
|
|
| -- |
-- |
Electric Rough In (4) |
|
|
| -- |
-- |
Inspection (Rough In Plumbing) (1) 02.11.2023 |
|
|
| -- |
-- |
Inspection (Rough In Electric) (1) 02.11.2023 |
|
|
| -- |
-- |
Inspection (Framing) (1) * 02.11.2023 |
|
|
| -- |
-- |
Inspection (Deck Piers) (0) 02.11.2023 |
|
|
| -- |
-- |
Exterior Vinyl (0) * 10.02.2021 |
|
|
| -- |
-- |
Exterior Stone (0) 02.11.2023 |
|
|
| -- |
-- |
Insulation (2) * |
|
|
| -- |
-- |
Inspection (Insulation) (1) |
|
|
| -- |
-- |
Inspection (Electric Service) (0) 09.09.2021 |
|
|
| -- |
-- |
Inspection (Main Sewer Line) (0) |
|
|
| -- |
-- |
Inspection (Main Water Line) (0) 02.11.2023 |
|
|
| -- |
-- |
Order Interior Doors & Trim (0) |
BN Hinges |
|
| -- |
-- |
Drywall (Hang) (4) * |
In process 6/30 |
|
| -- |
-- |
Loan Approval (0) 11.21.2021 |
|
|
| -- |
-- |
Deed Preparation (0) 11.21.2021 |
|
|
| -- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
In process 7/14 |
|
| -- |
-- |
Paint 1 (1) |
|
|
| -- |
-- |
Garage Door (0) 09.15.2021 |
|
|
| -- |
-- |
House Numbers (0) 10.02.2021 |
|
|
| -- |
-- |
Mailbox (0) 11.21.2021 |
|
|
| -- |
-- |
Cabinet Installation (2) * 08.25.2021 |
8/26 |
|
| -- |
-- |
Granite Installation (1) * 09.22.2021 |
|
|
| -- |
-- |
Interior Trim - Install (3) * 08.21.2021 |
Just needs paint 8/18 |
|
| -- |
-- |
Interior Trim - Paint (1) 02.11.2023 |
|
|
| -- |
-- |
Luxury Vinyl Plank (3) * 09.22.2021 |
|
|
| -- |
-- |
Luxury Vinyl Tile (0) 09.22.2021 |
|
|
| -- |
-- |
Paint 2 (3) 10.06.2021 |
|
|
| -- |
-- |
Shoe Moulding (0) 10.10.2021 |
In process 10/6 |
|
| -- |
-- |
Shelving, Door Knobs, Fire Extinguisher (1) * 10.20.2021 |
BN Levers and BN Bathroom accessories; Bonus Bath- Tuesday 10/19 |
|
| -- |
-- |
Install Coded Lockbox (add extra keys) (0) 10.21.2021 |
|
|
| -- |
-- |
Pay Water / Sewer Taps (0) 10.14.2021 |
|
|
| -- |
-- |
Set Water Meter (1) * 10.14.2021 |
|
|
| -- |
-- |
Electric Trim Out (3) * 10.20.2021 |
In process 10/16 |
|
| -- |
-- |
Ceiling Fans (0) 02.11.2023 |
|
|
| -- |
-- |
HVAC Trim Out (1) * 10.25.2021 |
Almost complete 10/20 |
|
| -- |
-- |
Plumbing Trim Out (2) * 10.20.2021 |
Completed except dishwasher |
|
| -- |
-- |
Install Appliances (0) * 10.20.2021 |
10/18 |
|
| -- |
-- |
Paint 3 (2) * 10.06.2021 |
|
|
| -- |
-- |
Carpet (2) 10.21.2021 |
In process 10/13-almost complete 10/16 |
|
| -- |
-- |
Appraiser Confirms Construction Completion (0) 10.28.2021 |
Wed, Oct 27 - Joe Chadwell |
|
| -- |
-- |
Inspection (Final HVAC) (0) 02.11.2023 |
|
|
| -- |
-- |
Inspection (Final Plumbing) (0) 02.11.2023 |
|
|
| -- |
-- |
Inspection (Final Electric) (0) 02.11.2023 |
|
|
| -- |
-- |
Inspection (Final Building) (4) * 10.25.2021 |
Fri, 10/22 |
|
| -- |
-- |
Pre Walk Through (0) 10.25.2021 |
|
|
| -- |
-- |
Stain Hardwood Stairs (1) * 02.11.2023 |
|
|
| -- |
-- |
Cleaning (1) 10.27.2021 |
Fri, 10/22 |
|
| -- |
-- |
Certificate of Occupancy (1) * 10.25.2021 |
|
|
| -- |
-- |
C.O. to Lender (0) 10.25.2021 |
|
|
| -- |
-- |
Schedule Closing (0) 10.26.2021 |
|
|
| -- |
-- |
Buyer Walk Through (1) * 10.28.2021 |
Wed, 10/27 at 4PM |
|
| -- |
-- |
Payment for Upgrades (0) 10.27.2021 |
|
|
| -- |
-- |
Keys to Settlement Agent (0) 10.27.2021 |
|
|
| -- |
-- |
Review Settlement Statement (0) 10.27.2021 |
|
|
| -- |
-- |
Jerry Signs Closing Documents (0) 11.01.2021 |
Thursday, 10/28 at 2:30 PM |
|
| -- |
-- |
Request Trash Tote From POA Manager (0) 10.27.2021 |
|
|
| -- |
-- |
Remove Coded Lockbox (0) 11.04.2021 |
|
|